Documents of Note

Utilities Commission Act

BC Hydro 2012 CPCN-Dawson Creek/Chetwynd Area Transmission Project

British Columbia Hydro and Power Authority ~ Certificate of Public Convenience and Necessity for the Dawson Creek/Chetwynd Area Transmission Project ~ Project No.3698640


Timetable

SubjectDate
  


Hearing Location

SubjectLocationDateTimeAddress
     

 

Hearing and Other Documents

TitleDocument DescriptionSubmitted Date/TimeApproved Date
*_Exhibit List Updated: August 22, 2012 @ 10:43 am2011/07/15 02:18:00 PM2012/05/14
*_Email Fax List Updated: June 15, 2012 @ 2:52 pm2011/07/26 09:56:00 AM2011/07/26
*_Distribution List Updated: June 15, 2012 @ 2:52 pm2011/07/26 09:57:00 AM2011/07/26
*_2012 Decision October 10, 20122012/10/10 04:04:00 PM2012/10/10
*_BC Hydro Compliance Report Public April 8, 20132013/04/22 10:07:00 AM2013/04/22
*_BC Hydro Compliance Report Confidential April 8, 20132013/04/22 10:07:00 AM2013/04/22
*_West Moberly Letter of Support April 8,20132013/04/22 10:08:00 AM2013/04/22
*_C-5-13 2013 Reasons for Decision April 25, 2013 Reasons for Decision2013/04/26 11:05:00 AM2013/04/26
    

Arguments

TitleDocument DescriptionSubmitted Date/TimeApproved Date
BC Hydro Final Submission BC Hydro Final Submission July 24, 20122012/07/24 02:40:00 PM2012/07/24
BC Hydro CONFIDENTIAL Final Submission July 24, 20122012/07/24 04:23:00 PM2012/07/24
GMR Submission GMR Submission July 30, 20122012/07/30 01:47:00 PM2012/07/30
City of Dawson Creek Final Submission DC Final Submission August 2, 20122012/08/02 09:47:00 AM2012/08/02
AEM Final Submission AEM Final Submission August 2, 20122012/08/02 02:22:00 PM2012/08/02
CAPP Final Submission CAPP Final Submission August 2, 20122012/08/02 02:24:00 PM2012/08/02
CSI Final Submission CSI Final Submission August 2, 20122012/08/02 02:26:00 PM2012/08/02
BCSEA Final Submission BCSEA Final Submission August 2, 20122012/08/02 05:46:00 PM2012/08/03
ALC Final Submission ALC Final Submission August 2, 20122012/08/03 08:56:00 AM2012/08/03
AMPC Final Submission AMPC Final Submission August 2, 20122012/08/03 09:02:00 AM2012/08/03
CEA Final Submission CEA Final Submission August 2, 20122012/08/03 09:04:00 AM2012/08/03
CEC Final Submission CEC Final Submission August 2, 20122012/08/03 09:06:00 AM2012/08/03
Shell Final Submission SC Final Submission August 2, 20122012/08/03 09:08:00 AM2012/08/03
WMFN CONFIDENTIAL Final Submission August 2, 20122012/08/03 09:10:00 AM2012/08/03
BC Hydro Response to WMFN Confidential Argument BC Hydro Response to WMFN August 3, 20122012/08/03 04:03:00 PM2012/08/08
BC Hydro Reply Submission BC Hydro Reply Submission August 8, 20122012/08/08 03:53:00 PM2012/08/08
WMFN PUBLIC Final Submission WMFN PUBLIC Final Submission - August 8, 20122012/08/09 09:21:00 AM2012/08/09
WMFN Final Submission Book of Authorities WMFN Final Submission Book of Authorities - August 9, 20122012/08/09 05:07:00 PM2012/08/09
BCPSO Final Submission BCPSO Final Submission August 2, 20122012/08/13 05:01:00 PM2012/08/13
BC Hydro Filing Adams Lake BCCA Decision Filed August 17, 20122012/08/17 02:07:00 PM2012/08/20
    

Exhibits

"A" Exhibits - Commission Documents

TitleDocument DescriptionSubmitted Date/TimeApproved Date
A-1 Letter dated July 26, 2011 – Order G-132-11 establishing Initial Regulatory Timetable and Procedural Conference2011/07/27 08:54:00 AM2011/07/27
A-2 Letter dated July 27, 2011 – Appointment of Commission Panel2011/08/04 02:51:00 PM2011/08/04
A-3 Letter dated August 17, 2011 – Issuing Commission Information Request No. 1 to BC Hydro2011/08/17 04:34:00 PM2011/08/17
A-4 Letter dated September 15, 2011 – Order G-160-11 issuing Amended Regulatory Timetable – Rescheduling of Procedural Conference2011/09/15 03:11:00 PM2011/09/15
A-5 Letter dated September 22, 2011 – Interim Participant Assistance/Cost Award (PACA)2011/09/22 05:04:00 PM2011/09/22
A-6 Letter dated September 29, 2011 – Response to BC Hydro request to Comment2011/09/29 11:31:00 AM2011/09/29
A-7 Letter dated October 4, 2011 – West Moberly First Nation Extension to file Information Request No. 22011/10/05 09:25:00 AM2011/10/05
A-8 Letter dated October 6, 2011 – Issuing Commission Information Request No. 2 to BC Hydro2011/10/06 09:41:00 AM2011/10/06
A-9 CONFIDENTIAL Letter dated October 6, 2011 – Issuing CONFIDENTIAL Commission Information Request No. 2 to BC Hydro 2011/10/06 09:43:00 AM2011/10/06
A-10 Letter dated October 7, 2011 –Comments regarding the submission of CEC IR-22011/10/07 01:30:00 PM2011/10/07
A-11 Letter dated October 13, 2011 – Request BC Hydro response regarding Confidential Information Request No. 22011/10/13 01:56:00 PM2011/10/13
A-12 Letter dated October 13, 2011 – Response to West Moberly First Nation additional filing extension for Information Request No. 22011/10/13 01:58:00 PM2011/10/13
A-13 Letter dated October 14, 2011 – Panel Determination on the CEC request for interim PACA Funding2011/10/14 03:25:00 PM2011/10/14
A-14 Letter dated October 17, 2011 – Request BC Hydro response regarding West Moberly First Nation access to Confidential Information Request No. 22011/10/17 03:53:00 PM2011/10/17
A-15 Letter dated October 18, 2011 –Determination regarding confidential IR No. 2 questions2011/10/18 04:03:00 PM2011/10/18
A-16 Letter dated October 26, 2011 – Procedural Conference Items2011/10/26 03:01:00 PM2011/10/26
A-17 Letter dated October 27, 2011 – Response to BC Hydro2011/10/27 02:43:00 PM2011/10/27
A-18 Letter dated November 8, 2011 – Order G-184-11 issuing Revised Regulatory Timetable2011/11/08 04:42:00 PM2011/11/08
A-19 Letter dated November 14, 2011 – Request comments regarding WMFN request for stay of Application2011/11/14 02:51:00 PM2011/11/14
A-20 Letter dated November 15, 2011 – Commission Panel Information Request No. 1 to BC Hydro2011/11/15 04:22:00 PM2011/11/15
A-21 Letter dated November 18, 2011 – Commission Information Request No. 3 to BC Hydro2011/11/18 05:12:00 PM2011/11/18
A-22 Letter dated November 24, 2011 – Commission Response to Request for Suspension of Hearing2011/11/24 03:31:00 PM2011/11/24
A-23 Letter dated November 30, 2011 – Suspension of Hearing until Further Notice2011/11/30 09:57:00 AM2011/11/30
A-24 Letter dated December 13, 2011 – Commission Response to Request for Late Intervener Status2011/12/13 10:48:00 AM2011/12/13
A-25 Letter dated March 27, 2012 - Request to Interveners to Provide Comments Regarding Reactivation of Hearing Process2012/03/28 08:59:00 AM2012/03/28
A-26 Letter dated April 11, 2012 – Letter L-23-12 Hearing Reactivation2012/04/11 12:08:00 PM2012/04/11
A-27 Letter dated April 24, 2012 – Letter L-26-12 Request Comments on Draft Revised Regulatory Timetable2012/04/24 03:15:00 PM2012/04/24
A-28 Letter dated May 7, 2012 – Commission Order G-56-12 issuing Revised Regulatory Timetable2012/05/07 05:09:00 PM2012/05/07
A-29 Letter dated May 11, 2012 – Commission Information Request No. 4 to BC Hydro2012/05/14 11:30:00 AM2012/05/14
A-30 Letter dated June 14, 2012 - Commission Information Request No. 1 to CSI2012/06/14 02:22:00 PM2012/06/14
A-31 Letter dated June 15, 2012 - Letter L-36-12 Specific Matters Relating to Electric Tariff No. 6 to be Addressed in Final Submissions2012/06/15 12:28:00 PM2012/06/15
A-32 Letter dated June 29, 2012 – Confirmation of Oral Hearing on First Nations’ Consultation2012/06/29 01:38:00 PM2012/06/29
A-33 Letter dated July 13, 2012 – Letter L-41-12 issuing Revised Regulatory Timetable2012/07/13 11:37:00 AM2012/07/13
A-34 Letter dated August 8, 2012 – Commission Response regarding WMFN Confidential Final Submission2012/08/08 11:53:00 AM2012/08/08
A2-1 Letter dated November 3, 2011 – Commission staff submission British Columbia Hydro and Power Authority 2010 Electrical Load Forecast for 2010/11 to 2030/312011/11/03 04:30:00 PM2011/11/03
A2-2 Letter dated June 13, 2012 - Commission staff submission Utility System Extension Test Guidelines dated September 5, 19962012/06/13 02:15:00 PM2012/06/13
A2-3 Letter dated June 29, 2012 - Commission staff submission British Columbia Transmission Corporation – Peace Region Load Serving Capability June 24, 2009 Information Release – Load Serving Capability for New Load Interconnections in the Dawson Creek and Chetwynd Area2012/06/29 01:41:00 PM2012/06/29
    

"B" Exhibits - Applicant Documents

TitleDocument DescriptionSubmitted Date/TimeApproved Date
B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) Letter dated July 11, 2011 – Application for Certificate of Public Convenience and Necessity for the Dawson Creek-Chetwynd Area Transmission Project2011/07/15 02:17:00 PM2011/07/15
B-1-1 Letter dated July 11, 2011 – BCH Submitting Errata revised Appendix E2011/07/15 02:17:00 PM2011/08/03
B-1-2 Letter dated September 15, 2011 – BCH Submitting Errata to the Application2011/07/15 02:17:00 PM2011/09/16
B-1-3 Letter dated March 23, 2012 – BCH Submitting Updates to the Application2011/07/15 02:17:00 PM2012/03/26
B-2 Letter dated July 22, 2011 – BCH Submitting Workshop Presentation2011/07/22 09:11:00 AM2011/07/22
B-3 Letter dated August 16, 2011 – BCH Submitting Compliance with BCUC Order G 132 11 Directive 32011/08/16 11:24:00 AM2011/08/16
B-4 Letter dated September 13, 2011 – BCH Request for Amendments to the Regulatory Timetable2011/09/13 05:44:00 PM2011/09/14
B-5 Letter dated September 15, 2011 – BCH Responses to BCUC Information Request No. 12011/09/16 10:11:00 AM2011/09/16
B-5-1 CONFIDENTIAL Letter dated September 15, 2011 – BCH CONFIDENTIAL Responses to BCUC Information Request No. 12011/09/16 10:13:00 AM2011/09/16
B-5-2 Letter dated September 22, 2011 – BCH Submitting Amended Response to BCUC IR 1.38.2.12011/09/23 11:22:00 AM2011/09/23
B-5-3 Letter dated September 29, 2011 – BCH Response to BCUC IR 1.38.2.22011/09/23 11:22:00 AM2011/09/30
B-5-4 CONFIDENTIAL Letter dated September 29, 2011 – BCH CONFIDENTIAL Response to BCUC IR 1.38.2.32011/09/23 11:22:00 AM2011/09/30
B-6 Letter dated September 22, 2011 – BCH Submitting Responses to Intervener Information Requests No. 12011/09/23 11:23:00 AM2011/09/23
B-6-1 CONFIDENTIAL Letter dated September 22, 2011 – BCH Submitting CONFIDENTIAL Responses to Intervener Information Requests No. 12011/09/23 11:27:00 AM2011/09/23
B-6-2 Letter dated September 29, 2011 – Revised Responses to CEC IR 1.1.10, COPE IR 1.1.12011/09/23 11:27:00 AM2011/09/30
B-7 Letter dated September 28, 2011 – BCH Submitting request to comment on CEC interim PACA funding application2011/09/28 05:20:00 PM2011/09/29
B-8 Letter dated September 29, 2011 – BCH Submission regarding WMFN requesting access to Confidential Responses to BCUC Information Request No. 1 (Exhibit C5-3)2011/09/30 09:12:00 AM2011/09/30
B-9 Letter Dated October 3, 2011– BCH Submission regarding WMFN request for an extension (Exhibit C5-5)2011/10/03 05:04:00 PM2011/10/04
B-10 Letter Dated October 7, 2011– BCH Submitting comments on Interim PACA Funding Application of CECBC2011/10/07 04:36:00 PM2011/10/11
B-11 Letter Dated October 14, 2011– BCH Submitting Response to Exhibit A-112011/10/14 03:19:00 PM2011/10/14
B-12 Letter Dated October 18, 2011– BCH Submitting Response to Exhibit A-142011/10/18 03:46:00 PM2011/10/18
B-13 Letter Dated October 24, 2011– BCH Reply Submission in Compliance with Exhibit A-142011/10/24 04:00:00 PM2011/10/24
B-14 Letter Dated October 27, 2011– BCH Response to BCUC Information Request No. 22011/10/28 09:07:00 AM2011/10/28
B-14-1 CONFIDENTIAL Letter Dated October 27, 2011– BCH CONFIDENTIAL Response to BCUC Information Request No. 22011/10/28 09:09:00 AM2011/10/28
B-14-2 Letter Dated November 1, 2011– BCH Response to BCUC Information Request No. 2.29.22011/10/28 09:09:00 AM2011/11/02
B-14-3 CONFIDENTIAL Letter Dated November 1, 2011– BCH CONFIDENTIAL Response to BCUC Information Request No. 2.29.22011/10/28 09:09:00 AM2011/11/02
B-15 Letter Dated October 27, 2011– BCH Response to Interveners Information Request No. 22011/10/28 09:10:00 AM2011/10/28
B-15-1 Letter Dated November 1, 2011– BCH Response to WMFN2011/11/02 11:32:00 AM2011/11/02
B-16 CONFIDENTIAL Letter Dated November 1, 2011– BCH CONFIDENTIAL Response to WMFN Confidential Request2011/11/02 11:36:00 AM2011/11/02
B-17 Letter dated November 3, 2011 – BCH Submitting Public Response to BCUC Confidential Information Request No. 22011/11/03 04:55:00 PM2011/11/03
B-17-1 CONFIDENTIAL Letter dated November 3, 2011 – BCH Submitting CONFIDENTIAL Response to BCUC Confidential Information Request No. 22011/11/03 04:58:00 PM2011/11/03
B-18 Letter dated November 21, 2011 – BCH Submitting comments regarding WMFN Application for Adjournment2011/11/21 12:42:00 PM2011/11/21
B-19 Letter dated November 23, 2011 – BCH Submitting Request for Suspension of Proceeding and Comments on Information Requests 2011/11/23 02:00:00 PM2011/11/23
B-20 Letter dated November 29, 2011 – BCH Submitting reply to Interveners comments2011/11/29 01:00:00 PM2011/11/29
B-21 Letter dated March 7, 2012 - BCH Submitting Notice of Reactivation Application2012/03/07 04:06:00 PM2012/03/08
B-22 Letter dated March 23, 2012 – BCH Submitting Application Reactivation Request2012/03/26 09:07:00 AM2012/03/26
B-23 CONFIDENTIAL Letter dated March 23, 2012 – BCH Submitting CONFIDENTIAL Evidence2012/03/26 09:11:00 AM2012/03/26
B-24 Letter dated April 5, 2012 – BCH Reply to Intervener Procedural Comments2012/04/05 04:35:00 PM2012/04/05
B-25 Letter dated April 17, 2012 – BCH Submitting Response to Exhibit A-262012/04/17 07:07:00 PM2012/04/18
B-26 Letter dated April 12, 2012 – BC Hydro Response to Lance Mulvahill Exhibit E-12012/04/19 04:29:00 PM2012/04/19
B-27 Submitted at Procedural Conference May 2, 2012 - DCAT ROUND 3 IRS WHICH BC HYDRO COMMITS TO ANSWERING2012/05/03 09:09:00 AM2012/05/03
B-28 Submitted at Procedural Conference May 2, 2012 - BC HYDRO PROPOSED REGULATORY TIMETABLE2012/05/03 09:11:00 AM2012/05/03
B-29 Letter dated May 24, 2012 - BCH Submitting Responses to BCUC and Interveners Information Request No. 3 and BCUC Panel Information Request No. 12012/05/25 09:50:00 AM2012/05/25
B-29-1 CONFIDENTIAL Letter dated May 24, 2012 - BCH Submitting CONFIDENTIAL Responses to BCUC and Interveners Information Request No. 3 and BCUC Panel Information Request No. 12012/05/25 09:54:00 AM2012/05/25
B-30 Letter dated May 24, 2012 - BCH Submitting Responses to BCUC and Interveners Information Request No. 42012/05/25 09:55:00 AM2012/05/25
B-30-1 Letter dated May 25, 2012 - BCH Submitting Responses to CEC Information Request No. 42012/05/25 04:43:00 PM2012/05/25
B-31 Letter dated July 4, 2012 - BCH Submitting Security Arrangements Update2012/07/04 05:08:00 PM2012/07/05
B-32 Letter dated July 5, 2012 - BCH Submitting First Nations Consultation Summary2012/07/05 04:58:00 PM2012/07/05
B-33 CONFIDENTIAL Letter dated July 5, 2012 - BCH Submitting CONFIDENTIAL BC Hydro and West Moberly First Nations Log 2012/07/06 09:32:00 AM2012/07/06
B-34 Letter dated July 6, 2012 - BCH Submitting Evidentiary Update2012/07/06 04:52:00 PM2012/07/06
B-35 Submitted at Oral Hearing July 9, 2012 - OUTLINE (TABLE OF CONTENTS) OF DRAFT EXHIBIT C5-20 PROVIDED BY MR. SANDERSON2012/07/10 02:43:00 PM2012/08/22
B-36 Submitted at Oral Hearing July 10, 2012 - POWERPOINT PRESENTATION DATED JUNE 20102012/07/10 02:43:00 PM2012/08/22
B-37 Submitted at Oral Hearing July 10, 2012 - CURRICULUM VITAE OF TIM SLANEY2012/07/10 02:43:00 PM2012/08/22
B-38 Submitted at Oral Hearing July 10, 2012 - LIST OF DISCIPLINE LEADS AND SENIOR PERSONNEL2012/07/10 02:43:00 PM2012/08/22
B-39 Submitted at Oral Hearing July 10, 2012 - REPLACEMENT TABLE FOR PAGE 111 OF 207 EXHIBIT B-1, APPENDIX F2012/07/10 02:43:00 PM2012/08/22
B-40 Submitted at Oral Hearing July 10, 2012 - FULL SET OF MAPS WHICH HAD BEEN OMITTED FROM EXHIBIT B-342012/07/10 02:43:00 PM2012/08/22
B-41 Submitted at Oral Hearing July 10, 2012 - REPORT ENTITLED “POPULATION STATUS OF THREATENED CARIBOU HERDS IN THE CENTRAL ROCKIES ECO-REGION OF BRITISH COLUMBIA, 2011” BY DALE SEIP AND ELENA JONES, MAY 20112012/07/10 02:43:00 PM2012/08/22
B-42 CONFIDENTIAL Letter dated July 10, 2012 – BCH Submitting CONFIDENTIAL West Moberly First Nations Log and Relevant Material2012/07/12 09:31:00 AM2012/07/10
B-43 Letter dated July 11, 2012 – BCH Submitting confirmation of DCAT tour2012/07/12 09:32:00 AM2012/07/12
B-44 Letter dated July 12, 2012 – BCH Submitting response to WMFN response regarding DCAT tour2012/07/12 03:39:00 PM2012/07/12
B-45 Letter dated July 20, 2012 – BCH Submitting Security Arrangements Update2012/07/20 02:29:00 PM2012/07/23
B-46 Letter dated July 25, 2012 – BCH Submitting Tour Materials2012/07/25 04:07:00 PM2012/07/25
    

"C" Exhibits - Intervener Documents

TitleDocument DescriptionSubmitted Date/TimeApproved Date
C1-1 V.W.RUSKIN & ASSOCIATES (VR) Letter dated July 16, 2011 Via Email – Request for Intervener Status by Vernon Ruskin2011/07/19 11:31:00 AM2011/07/19
C1-2 Letter Dated September 27, 2011 Via Email –VW Submitting comments2011/09/28 10:32:00 AM2011/09/28
C1-3 Letter Dated October 11, 2011 Via Email – VR Submitting comments regarding the CEC PACA Application2011/10/12 03:33:00 PM2011/10/12
C1-4 Letter Dated November 2, 2011 Via Email – VR Submitting Comment on Procedural Conference2011/11/02 04:43:00 PM2011/11/02
C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) VIA EMAIL Letter Dated July 21, 2011- Request for Intervener Status by Christopher Weafer2011/07/21 02:22:00 PM2011/07/21
C2-2 Letter Dated August 24, 2011 – CEC Submitting Information Request No. 12011/08/24 04:26:00 PM2011/08/24
C2-3 Letter Dated October 6, 2011 – CEC Submitting extension request for Information Request No. 22011/10/07 10:31:00 AM2011/10/07
C2-4 Letter Dated October 11, 2011 – CEC Information Request No. 22011/10/11 04:11:00 PM2011/10/11
C2-5 Letter Dated October 12, 2011 – CEC Submitting Reply Comments on Interim PACA2011/10/13 01:50:00 PM2011/10/13
C2-6 Letter Dated October 28, 2011 – CEC Submitting Response to Exhibit A-132011/10/31 09:18:00 AM2011/10/31
C2-7 Letter Dated November 2, 2011– CEC Submitting Comment on Procedural Conference2011/11/02 04:45:00 PM2011/11/02
C2-8 Letter Dated November 2, 2011– CEC Submitting notice of intent to provide evidence2011/11/02 04:59:00 PM2011/11/02
C2-9 Letter dated November 18, 2011 – CEC Submitting Information Request No. 3 to BC Hydro2011/11/18 05:19:00 PM2011/11/18
C2-10 Letter dated November 28, 2011 – CEC Submitting Comment on BC Hydro request for adjournment2011/11/28 03:52:00 PM2011/11/28
C2-11 Letter dated April 3, 2012 – CEC Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 11:56:00 AM2012/04/05
C2-12 Letter dated April 24, 2012 – CEC Submitting Comments Regarding BC Hydro’s response to Exhibit A-262012/04/24 05:18:00 PM2012/04/24
C2-13 Letter dated May 14, 2012 – CEC Submitting Information Request No. 4 2012/05/14 04:21:00 PM2012/05/14
C3-1 ASSOCIATION OF MAJOR POWER CUSTOMERS OF BC (AMPC) Letter Dated July 28, 2011- Request for Intervener Status by Matthew Keen, Richard Stout, Lloyd Guenther and Brian Wallace2011/07/28 05:05:00 PM2011/07/28
C3-2 Letter Dated November 2, 2011– AMPC Submitting Comment on Procedural Conference2011/11/02 04:47:00 PM2011/11/02
C3-3 Letter dated November 18, 2011 – AMPC Submitting Information Request No. 3 to BC Hydro2011/11/18 05:20:00 PM2011/11/18
C3-4 Letter dated November 21, 2011 – AMPC Submitting comments regarding WMFN Application for Adjournment2011/11/21 04:22:00 PM2011/11/21
C3-5 Letter dated November 24, 2011 – AMPC Submitting comments regarding Suspension of Hearing2011/11/24 03:39:00 PM2011/11/24
C3-6 Letter dated April 3, 2012 – AMPC Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 11:56:00 AM2012/04/05
C3-7 Letter dated April 10, 2012 – AMPC Submitting Comments Regarding BC Hydro's supplemental letter commenting on intervener responses2012/04/11 12:01:00 PM2012/04/11
C3-8 Letter dated April 24, 2012 – AMPC Submitting Response to BC Hydro April 17, 2012 letter 2012/04/25 01:58:00 PM2012/04/25
C3-9 Letter dated May 14, 2012 – AMPC Submitting Information Request No. 4 to BC Hydro2012/05/15 12:04:00 PM2012/05/15
C3-10 Letter dated June 7, 2012 – AMPC Submitting Evidence2012/06/08 11:00:00 AM2012/06/08
C3-11 Letter dated June 14, 2012 – AMPC Submitting Response to BCOAPO Information Request No.12012/06/29 01:59:00 PM2012/06/29
C3-12 Letter dated June 28, 2012 – AMPC Submitting Response to BCSEA Information Request No.12012/06/29 02:00:00 PM2012/06/29
C3-13 Letter dated July 6, 2012 – AMPC Will Not Participate in Oral Hearing 2012/07/09 02:52:00 PM2012/07/09
C4-1 CANADIAN OFFICE AND PROFESSIONAL EMPLOYEES UNION LOCAL 378 (COPE 378) VIA EMAIL - Letter Dated July 28, 2011- Request for Intervener Status by Mark Oulton 2011/07/28 05:09:00 PM2011/07/29
C4-2 Letter Dated August 24, 2011 – Cope378 Submitting Information Request No. 12011/08/24 05:07:00 PM2011/08/24
C4-3 Letter Dated September 14, 2011 - Cope378 Submitting Comments regarding Exhibit B-42011/09/15 10:08:00 AM2011/09/15
C4-4 Letter Dated September 13, 2011 - Cope378 Updating Contact Information2011/09/15 10:10:00 AM2011/09/15
C4-5 Letter Dated September 26, 2011 - Cope 378 Comment regarding Exhibit A-52011/09/26 03:18:00 PM2011/09/26
C4-6 Letter Dated October 6, 2011 – Cope378 Submitting Information Request No. 22011/10/07 10:19:00 AM2011/10/07
C4-7 Letter Dated November 2, 2011– Cope378 Submitting Comment on Procedural Conference2011/11/02 04:49:00 PM2011/11/02
C4-8 Letter dated November 17, 2011 – Cope378 Submitting Information Request No. 32011/11/17 11:09:00 AM2011/11/17
C4-9 Letter dated November 17, 2011 – Cope378 Submitting response to Exhibit A-192011/11/17 04:27:00 PM2011/11/17
C4-10 Letter dated November 28, 2011 – COPE378 Submitting Comment on BC Hydro request for adjournment2011/11/28 03:56:00 PM2011/11/28
C5-1 WEST MOBERLY FIRST NATIONS (WMFN) Online registration dated August 3, 2011 - Request for Intervener Status by Allisun Rana2011/08/03 02:20:00 PM2011/08/03
C5-2 Letter Dated August 24, 2011 – WMFN Submitting Information Request No. 12011/08/24 04:52:00 PM2011/08/24
C5-3 Letter Dated September 22, 2011 - WMFN Submitting Response to BC Hydro Confidential Filings2011/09/22 04:32:00 PM2011/09/22
C5-4 Letter Dated September 30, 2011 - WMFN Submitting comments regarding BC Hydro Confidential Filings2011/10/03 12:04:00 PM2011/10/03
C5-5 Letter Dated October 3, 2011- WMFN Request for submission or Information Request No. 22011/10/03 04:47:00 PM2011/10/03
C5-6 Letter Dated October 4, 2011- WMFN Submitting comments regarding Exhibit B-92011/10/04 02:19:00 PM2011/10/04
C5-7 Letter Dated October 6, 2011- WMFN Submitting comments regarding confidential Information Requests2011/10/07 10:26:00 AM2011/10/07
C5-8 Letter Dated October 13, 2011- WMFN Submitting Information Request No. 22011/10/14 08:47:00 AM2011/10/14
C5-8-1 CONFIDENTIAL Letter Dated October 13, 2011- WMFN Submitting Confidential Information Request No. 22011/10/14 08:49:00 AM2011/10/14
C5-9 Letter Dated October 17, 2011 – WMFN Submitting comments regarding Exhibit B 112011/10/17 09:11:00 AM2011/10/17
C5-10 Letter Dated October 21, 2011 – WMFN Responses to Exhibits_A-9-and-B-122011/10/24 08:39:00 AM2011/10/24
C5-11 Letter Dated November 2, 2011– WMFN Submitting Comment on Procedural Conference2011/11/02 04:51:00 PM2011/11/02
C5-12 Letter Dated November 2, 2011– WMFN Submitting notice of intent to provide evidence2011/11/02 05:00:00 PM2011/11/02
C5-13 Letter dated November 9, 2011 – WMFN Submitting Adjournment Request 2011/11/10 09:01:00 AM2011/11/10
C5-14 Letter dated November 23, 2011 – WMFN Reply Submission on adjournment application2011/11/23 04:06:00 PM2011/11/23
C5-15 Letter dated November 28, 2011 – WMFN Reply Submission on BC Hydro request for adjournment2011/11/28 01:41:00 PM2011/11/28
C5-16 Letter dated April 4, 2012 – WMFN Submitting Comment on MEM Submission2012/04/05 09:08:00 AM2012/04/05
C5-17 Letter dated April 4, 2012 – WMFN Submitting Comment on SC Submission2012/04/05 09:09:00 AM2012/04/05
C5-18 Letter dated April 3, 2012 – WMFN Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 11:57:00 AM2012/04/05
C5-19 Letter dated June 6, 2012 - WMFN Submitting Draft Summary of the Evidence of WMFN Chief Roland Willson2012/06/07 11:04:00 AM2012/06/07
C5-20 Letter dated July 5, 2012 - WMFN Submitting Report2012/07/05 04:40:00 PM2012/07/05
C5-21 Letter dated July 5, 2012 - WMFN Submitting Oral Hearing Materials and Evidence2012/07/05 04:49:00 PM2012/07/05
C5-22 Submitted at Oral Hearing July 10, 2012 - COPY OF WEST MOBERLY POWERPOINT PRESENTATION2012/07/05 05:50:00 PM2012/08/22
C5-23 Letter dated July 12, 2012 – WMFN Submitting Response to BCH proposed tour 2012/07/12 10:31:00 AM2012/07/12
C6-1 MILL VALLEY AND INDIAN CREEK LAND OWNERS GROUP (MVICLOG) Letter Dated August 12, 2011- Request for Intervener Status by Gordon Reid2011/08/12 11:46:00 AM2011/08/12
C7-1 BC OLD AGE PENSIONSER ORGANIZATION ET AL (BCOAPO ET AL) VIA EMAIL Letter dated August 15, 2011 – Request for Intervener Status by Leigha Worth2011/08/15 05:20:00 PM2011/08/15
C7-2 Letter Dated August 24, 2011 – BCOAPO et al Submitting Information Request No. 12011/09/06 02:47:00 PM2011/09/06
C7-3 Letter Dated October 6, 2011 – BCOAPO et al Submitting Information Request No. 22011/10/07 09:53:00 AM2011/10/07
C7-4 Letter Dated October 12, 2011 – BCOAPO et al Submitting Comments regarding Interim PACA2011/10/13 02:04:00 PM2011/10/13
C7-5 Letter Dated November 2, 2011– BCOAPO et al Submitting Comment on Procedural Conference2011/11/02 04:53:00 PM2011/11/02
C7-6 Letter dated November 18, 2011 – BCOAPO Submitting Information Request No. 3 to BC Hydro2011/11/18 05:21:00 PM2011/11/18
C7-7 Letter dated November 21, 2011 – BCOAPO Submitting comments regarding WMFN Application for Adjournment2011/11/21 04:52:00 PM2011/11/21
C7-8 Letter dated November 28, 2011 – BCOAPO Submitting Comment on BC Hydro request for adjournment2011/11/28 04:01:00 PM2011/11/28
C7-9 Letter dated April 3, 2012 – BCOAPO et al Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 11:58:00 AM2012/04/05
C7-10 Letter dated April 5, 2012 – BCOAPO Submitting Undertaking of Confidentiality for Eugene Kung2012/04/10 04:10:00 PM2012/04/10
C7-11 Letter dated April 5, 2012 – BCOAPO Submitting Undertaking of Confidentiality for Leigha Worth2012/04/10 04:11:00 PM2012/04/10
C7-12 Letter dated April 11, 2012 – BCOAPO Submitting Undertaking of Confidentiality for William Harper 2012/04/11 04:16:00 PM2012/04/11
C7-13 Letter dated April 24, 2012 – BCOAPO Submitting Comments Regarding BC Hydro’s response to Exhibit A-262012/04/24 05:16:00 PM2012/04/24
C7-14 Letter dated May 14, 2012 – BCOAPO Submitting Information Request No. 4 2012/05/14 04:25:00 PM2012/05/14
C7-15 Letter dated June 14, 2012 - BCOAPO Information Request No. 1 to CSI2012/06/14 02:41:00 PM2012/06/14
C7-16 Letter dated June 14, 2012 - BCOAPO Information Request No. 1 to AMPC2012/06/14 02:43:00 PM2012/06/14
C7-17 Letter dated July 13, 2012 – BCOAPO comment regarding Revised Regulatory Timetable2012/07/13 11:46:00 AM2012/07/13
C7-18 Letter dated July 23, 2012 – BCOAPO Submitting notice of Name Change to British Columbia Pensioners’ and Seniors’ Organization (BCPSO) 2012/07/23 02:14:00 PM2012/07/23
C7-19 Letter dated July 25, 2012 – BCPSO Submitting Confidential Undertaking2012/07/25 04:33:00 PM2012/07/25
C8-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) VIA WEB Letter Dated August 15, 2011 – Request for Intervener Status by William J. Andrews2011/08/15 05:21:00 PM2011/08/15
C8-2 Letter Dated August 24, 2011 – BCSEA Submitting Information Request No. 12011/08/25 08:18:00 AM2011/08/25
C8-3 Letter Dated September 27, 2011 Via Email – BCSEA Submitting comments on CEC proposal2011/09/28 03:06:00 PM2011/09/28
C8-4 Letter Dated October 6, 2011 – BCSEA Submitting Information Request No. 22011/10/07 10:14:00 AM2011/10/07
C8-5 Letter Dated November 1, 2011– BCSEA Submitting Comment on Procedural Conference2011/11/01 10:43:00 PM2011/11/02
C8-6 Letter dated November 18, 2011 – BCSEA Submitting Information Request No. 3 to BC Hydro2011/11/18 05:22:00 PM2011/11/18
C8-7 Letter dated November 25, 2011 – BCSEA Submitting Comments Regarding the Proposed Suspension of Hearing2011/11/25 01:18:00 PM2011/11/25
C8-8 Letter dated April 3, 2012 – BCSEA Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/03 04:56:00 PM2012/04/03
C8-9 Letter dated May 14, 2012 – BCSEA Submitting Information Request No. 4 to BC Hydro2012/05/14 05:16:00 PM2012/05/15
C8-11 Letter dated June 14, 2012 - BCSEA Information Request No. 1 to AMPC2012/06/14 04:29:00 PM2012/06/14
C8-10 Letter dated June 14, 2012 - BCSEA Information Request No. 1 to CSI2012/06/14 04:30:00 PM2012/06/14
C9-1 SIERRA CLUB OF BRITISH COLUMBIA (SCBC) VIA WEB Letter Dated August 15, 2011 – Request for Intervener Status by William J. Andrews2011/08/15 05:23:00 PM2011/08/15
C10-1 CLEAN ENERGY ASSOCIATION OF B.C. (CEA) VIA EMAIL – Letter Dated August 15,2011 – Request for Intervener Status by David Austin2011/08/16 01:35:00 PM2011/08/16
C10-2 Letter Dated October 4, 2011 – CEA Submission regarding PACA 2011/10/05 03:55:00 PM2011/10/05
C10-3 Letter Dated October 6, 2011 – CEA Submitting Information Request No. 22011/10/07 10:17:00 AM2011/10/07
C10-4 Letter Dated November 2, 2011– CEA Submitting Comment on Procedural Conference2011/11/02 04:55:00 PM2011/11/02
C10-5 Letter dated November 18, 2011 – CEA Submitting Information Request No. 3 to BC Hydro2011/11/21 09:15:00 AM2011/11/21
C10-6 Letter dated November 28, 2011 – CEA Submitting Comment on BC Hydro request for adjournment2011/11/28 04:05:00 PM2011/11/28
C10-7 Letter dated April 3, 2012 – CEA Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 12:00:00 PM2012/04/05
C11-1 GARY AND MARILYN ROBINSON (GMR) Letter Dated December 12, 2011 - Request for Late Intervener Status by Darryl Carter2011/12/13 10:46:00 AM2011/12/13
C11-2 Letter Dated March 19, 2012 – GMR Submitting comments regarding Exhibit B-222012/03/30 03:07:00 PM2012/03/30
C11-3 Letter Dated December 16, 2011 – GMR Submitting Information Request2012/05/01 08:36:00 AM2012/05/01
C11-4 Letter Dated May 8, 2012 – GMR Submitting comments regarding Exhibit A-282012/05/08 04:24:00 PM2012/05/08
C11-5 Letter Dated May 14, 2012 – GMR Submitting Counsel Information2012/05/14 11:37:00 AM2012/05/14
C11-6 Letter Dated May 14, 2012 – GMR Submitting Evidence2012/05/15 01:38:00 PM2012/05/15
C12-1 CANADIAN ASSOCIATION OF PETROLEUM PRODUCERS (CAPP) Letter Dated March 8, 2012 - Request for Late Intervener Status by James Smellie2012/03/29 03:19:00 PM2012/03/29
C12-2 Letter dated April 3, 2012 – CAPP Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 12:00:00 PM2012/04/05
C13-1 AIR LIQUIDE CANADA (ALC) Letter Dated March 9, 2012 - Request for Late Intervener Status by Mark Underhill2012/03/29 03:24:00 PM2012/03/29
C13-2 Letter dated April 3, 2012 – ALC Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 12:01:00 PM2012/04/05
C14-1 SHELL CANADA LIMITED (SC) Letter Dated March 14, 2012 - Request for Late Intervener Status by Naomi Sanderson and John Landry2012/03/29 03:27:00 PM2012/03/29
C14-2 Letter dated April 3, 2012 – SC Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 12:02:00 PM2012/04/05
C14-3 Letter dated July 13, 2012 – SC Submitting Comment regarding site visit 2012/07/13 05:38:00 PM2012/07/13
C15-1 CURRENT SOLUTIONS INCORPORATED (CSI) Letter Dated March 19, 2012 - Request for Late Intervener Status by Jamie Shand2012/03/29 03:30:00 PM2012/03/29
C15-2 Letter dated April 3, 2012 – CSI Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/05 12:03:00 PM2012/04/05
C15-3 Letter dated April 24, 2012 – CSI Submitting Comments Regarding BC Hydro’s response to Exhibit A-262012/04/24 05:15:00 PM2012/04/24
C15-4 Letter dated May 14, 2012 – CSI Submitting Information Request No. 4 2012/05/14 04:28:00 PM2012/05/14
C15-5 Letter dated June 7, 2012 - CSI Submitting Evidence 2012/06/08 08:44:00 AM2012/06/08
C15-6 Letter dated June 28, 2012 – CSI Submitting Response to BCUC Information Request No.12012/06/29 02:01:00 PM2012/06/29
C15-7 Letter dated June 28, 2012 – CSI Submitting Response to BCSEA and BCOAPO Information Request No.12012/06/29 02:03:00 PM2012/06/29
C15-8 Letter dated July 9, 2012 – CSI Will Not Participate in Oral Hearing 2012/07/09 03:00:00 PM2012/07/09
C16-1 MINISTRY OF ENERGY AND MINES (MEM) Letter Dated March 19, 2012 - Request for Late Intervener Status by Jennifer Champion and Les MacLaren2012/03/29 03:33:00 PM2012/03/29
C16-2 Letter dated April 3, 2012 – MEM Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/04 11:32:00 AM2012/04/04
C17-1 ARC RESOURCES LTD., ENCANA CORPORATION AND MURPHY OIL COMPANY LIMITED (AEM) ) Letter Dated March 14, 2012 - Request for Late Intervener Status by D. G. Davies, David J. Kehrig, Nadia Monaghan, Heather Tanaka and Garland Auvigne2012/03/30 03:00:00 PM2012/03/30
C17-2 Letter dated April 3, 2012 – AEM Submitting Comments Regarding the Proposed Reactivation of Hearing2012/04/03 04:57:00 PM2012/04/03
C18-1 CITY OF DAWSON CREEK (DC) – Letter Dated April 24, 2012 – Request for Late Intervener Status by Paul Hildebrand, Lidstone & Company on behalf of the City of Dawson Creek2012/04/25 12:34:00 PM2012/04/25
C18-2 Submitted at Procedural Conference May 2, 2012 - WRITTEN REMARKS BY MR. HILDEBRAND ON BEHALF OF THE CITY OF DAWSON CREEK2012/05/03 09:13:00 AM2012/05/03
    

"D" Exhibits - Interested Party Documents

TitleDocument DescriptionSubmitted Date/TimeApproved Date
D-1 MURPHY OIL COMPANY ONLINE REGISTRATION Dated July 21, 2011 – Request for Interested Party Status by Garland Auvigne2011/07/21 02:27:00 PM2011/07/21
D-2 SHELL CANADA ONLINE REGISTRATION Dated July 29, 2011 – Request for Interested Party Status by Saif Imran2011/07/29 09:56:00 AM2011/07/29
D-3 ARC RESOURCES LTD. (ARC) Online Registration dated August 9, 2011 – Request for Interested Party Status by David Kehrig2011/08/09 10:09:00 AM2011/08/09
D-4 Online Registration dated December 13, 2011 – Request for Interested Party Status by Jason Beck2011/12/14 01:44:00 PM2011/12/14
    

"E" Exhibits - Letters of Comment

TitleDocument DescriptionSubmitted Date/TimeApproved Date
E-1 MULVAHILL, LANCE - Letter of Comment Dated March 22, 20122012/03/29 03:36:00 PM2012/03/29
    

Transcripts

TitleDocument DescriptionSubmitted Date/TimeApproved Date
Transcript Volume 1 - Procedural Conference Procedural Conference November 4, 20112011/11/04 04:17:00 PM2011/11/04
Transcript Volume 2 - Procedural Conference Procedural Conference May 2, 20122012/05/02 04:29:00 PM2012/05/02
Transcript Volume 1 - Proceeding Proceeding July 9, 20122012/07/09 06:15:00 PM2012/07/10
Transcript Volume 2 - Proceeding Proceeding July 10, 20122012/07/10 05:13:00 PM2012/07/11
    