BC Transmission Corporation

British Columbia Transmission System - System Control Modernization Project

Completed: 2004

Hearing and Other Documents

Title Document Description
* Exhibit List Updated January 24, 2005
* Distribution List
* Order No. C-1-05 and Reasons For Decision

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
December 09, 2004 A-1 Letter No. L-54-04 and Information Request No. 1 to British Columbia Transmission Corporation dated November 5, 2004
December 09, 2004 A-2 Letter No. L-59-04 responding to Letters of Comment and setting Regulatory Agenda - dated December 8, 2004
December 20, 2004 A-3 Information Request No. 2 to British Columbia Transmission Corporation dated December 6, 2004

B Exhibits - Applicant Documents

Date Title Document Description
December 09, 2004 B-1 British Columbia Transmission Corporation Application dated October 15, 2004 for a Certificate of Public Convenience and Necessity for the System Control Modernization Project (Binder)
December 09, 2004 B-2 Responses to Commission Information Request No. 1 - dated November 19, 2004 (Binder)
December 09, 2004 B-3 CONFIDENTIAL – Letter regarding three questions in response to Commission Information Request No. 1 – dated November 19, 2004 - Exhibit B-2 (Confidential, for Panel and BCUC Staff, not for posting)
December 09, 2004 B-4 Further details regarding submissions by BC Hydro and JIESC – dated December 3, 2004
December 31, 2004 B-5 Response to Commission Information Request No. 2 and BC Hydro Information Request – dated December 31, 2004. CONFIDENTIAL – Response to Commission Information Request No. 2 Question 1.2 and BC Hydro Information Request 6.1(Confidential, for Panel and BCUC Staff, not for posting)
January 07, 2005 B-6 Supplemental Response to Commission Information Request No. 2, Question 1.1 dated January 7, 2004
January 20, 2005 B-7 Final Response to Intervenor Submissions dated January 17, 2005

C Exhibits - Intervener Documents

E Exhibits - Letters of Comment

Date Title Document Description
December 09, 2004 E-1 R. Brian Wallace, Bull, Housser & Tupper on behalf of Joint Industry Electricity Steering Committee - Comment regarding Application – dated November 26, 2004