Due DateUtilities & ProceedingRegulatory ItemOrder/Letter
2016/04/29 Creative NEFC Neighbourhood Energy Agreement Amendments
Creative Energy Vancouver Platforms Inc. Restated and Amended Northeast False Creek and Chinatown Neighbourhood Energy Agreement Application ~ Project No.3698868

Panel: H. Harowitz Panel Chair, R. Revel

Hearing Location:
Date & Time: @
Location: , ,

Creative ReplyA-6
2016/05/02 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

Commission & Intervener IR No. 3 limited in scope to issues concerning BC Hydro’s Duty to ConsultTranscript Volume 2
2016/05/03 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

All Parties Reply Submission Residential E-Plus rate designA-28
2016/05/04 FEI Proposal for Depreciation & Net Salvage Rate Changes
FortisBC Energy Inc. Proposal for Depreciation and Net Salvage Rate Changes ~ Project No.3698871

Panel: D. Cote Panel Chair, D. Enns

Hearing Location:
Date & Time: @
Location: , ,

FEI Response to Commission and Intervener IR No. 1G-41-16
2016/05/06 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

BC Hydro Responses to Commission & Intervener IR No. 3Transcript Volume 2
2016/05/06 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

BC Hydro Final Written Argument Transcript Volume 2
2016/05/06 PNG 2016-17 Revenue Requirements
Pacific Northern Gas Ltd. 2016-2017 Revenue Requirements Application ~ Project No.3698859

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

Commission and Intervener IRs No. 2G-13-16
2016/05/09 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

Intervener EvidenceG-50-16
2016/05/09 FEI Proposal for Depreciation & Net Salvage Rate Changes
FortisBC Energy Inc. Proposal for Depreciation and Net Salvage Rate Changes ~ Project No.3698871

Panel: D. Cote Panel Chair, D. Enns

Hearing Location:
Date & Time: @
Location: , ,

FEI and Intervener Submissions on Further ProcessG-41-16
2016/05/11 Creative Energy 2016-17 RR & RD for Northeast False Creek
Creative Energy 2016-2017 Revenue Requirements and Rate Design for Northeast False Creek Hot Water Service Application ~ Project No.3698872

Panel: D. Cote Panel Chair, N. MacMurchy, W. Everett

Hearing Location:
Date & Time: @
Location: , ,

Commission Information Request No. 1G-49-16
2016/05/13 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

Intervener Final Written ArgumentsTranscript Volume 2
2016/05/13 PNGNE 2016-17 Revenue Requirements
Pacific Northern Gas (N.E.) Fort St. John/Dawson Creek Division and Tumbler Ridge Division 2016-2017 Revenue Requirements Application ~ Project No.3698860

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

Commission and Intervener Information Request No. 2G-14-16
2016/05/13 Creative Energy 2016-17 RR & RD for Northeast False Creek
Creative Energy 2016-2017 Revenue Requirements and Rate Design for Northeast False Creek Hot Water Service Application ~ Project No.3698872

Panel: D. Cote Panel Chair, N. MacMurchy, W. Everett

Hearing Location:
Date & Time: @
Location: , ,

Intervener Information Request No. 1G-49-16
2016/05/17 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

BC Hydro Reply Written ArgumentsTranscript Volume 2
2016/05/18 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

Notification of need for Additional Oral Argument Transcript Volume 2
2016/05/20 BC Hydro WAC Bennett Riprap Upgrade Project
British Columbia Hydro and Power Authority W.A.C. Bennett Riprap Upgrade Project Application ~ Project No.3698854

Panel: D. Morton Panel Chair, H. Harowitz, N. MacMurchy

Hearing Location:
Date & Time: @
Location: , ,

Oral Argument, if requiredTranscript Volume 2
2016/05/20 PNG 2016-17 Revenue Requirements
Pacific Northern Gas Ltd. 2016-2017 Revenue Requirements Application ~ Project No.3698859

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

PNG Response to IRs No. 2G-13-16
2016/05/24 Superior Propane Rate Application for Seascapes Grid System
Superior Propane Rate Application for Seascapes Grid System ~ Project No.3698870

Panel Chair: H. Harowitz

Hearing Location:
Date & Time: @
Location: , ,

Commission and Intervener IR No. 2 to Superior PropaneG-56-16
2016/05/27 PNGNE 2016-17 Revenue Requirements
Pacific Northern Gas (N.E.) Fort St. John/Dawson Creek Division and Tumbler Ridge Division 2016-2017 Revenue Requirements Application ~ Project No.3698860

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

PNG Responses to Information Request No. 2G-14-16
2016/05/30 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

IR No. 1 on Intervener EvidenceG-50-16
2016/05/30 Creative Energy 2016-17 RR & RD for Northeast False Creek
Creative Energy 2016-2017 Revenue Requirements and Rate Design for Northeast False Creek Hot Water Service Application ~ Project No.3698872

Panel: D. Cote Panel Chair, N. MacMurchy, W. Everett

Hearing Location:
Date & Time: @
Location: , ,

Creative Energy responses to Information Requests No. 1G-49-16
2016/06/01 Creative Energy 2016-17 RR & RD for Northeast False Creek
Creative Energy 2016-2017 Revenue Requirements and Rate Design for Northeast False Creek Hot Water Service Application ~ Project No.3698872

Panel: D. Cote Panel Chair, N. MacMurchy, W. Everett

Hearing Location:
Date & Time: @
Location: , ,

Intervener submissions on further process and timetable for comment attached as Appendix BG-49-16
2016/06/03 PNG 2016-17 Revenue Requirements
Pacific Northern Gas Ltd. 2016-2017 Revenue Requirements Application ~ Project No.3698859

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

PNG Final ArgumentG-13-16
2016/06/07 Superior Propane Rate Application for Seascapes Grid System
Superior Propane Rate Application for Seascapes Grid System ~ Project No.3698870

Panel Chair: H. Harowitz

Hearing Location:
Date & Time: @
Location: , ,

Superior Propane Response to Commission and Intervener IR No. 2G-56-16
2016/06/07 Creative Energy 2016-17 RR & RD for Northeast False Creek
Creative Energy 2016-2017 Revenue Requirements and Rate Design for Northeast False Creek Hot Water Service Application ~ Project No.3698872

Panel: D. Cote Panel Chair, N. MacMurchy, W. Everett

Hearing Location:
Date & Time: @
Location: , ,

Creative Energy reply on further process and timetable for comment attached as Appendix BG-49-16
2016/06/10 PNGNE 2016-17 Revenue Requirements
Pacific Northern Gas (N.E.) Fort St. John/Dawson Creek Division and Tumbler Ridge Division 2016-2017 Revenue Requirements Application ~ Project No.3698860

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

PNG Final ArgumentG-14-16
2016/06/14 PNG 2016-17 Revenue Requirements
Pacific Northern Gas Ltd. 2016-2017 Revenue Requirements Application ~ Project No.3698859

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

Intervener Final ArgumentG-13-16
2016/06/14 Superior Propane Rate Application for Seascapes Grid System
Superior Propane Rate Application for Seascapes Grid System ~ Project No.3698870

Panel Chair: H. Harowitz

Hearing Location:
Date & Time: @
Location: , ,

Superior Propane and Intervener Submissions on Further Regulatory ProcessG-56-16
2016/06/17 Superior Propane Rate Application for Seascapes Grid System
Superior Propane Rate Application for Seascapes Grid System ~ Project No.3698870

Panel Chair: H. Harowitz

Hearing Location:
Date & Time: @
Location: , ,

Superior Propane and Intervener Reply on Further Regulatory ProcessG-56-16
2016/06/21 PNGNE 2016-17 Revenue Requirements
Pacific Northern Gas (N.E.) Fort St. John/Dawson Creek Division and Tumbler Ridge Division 2016-2017 Revenue Requirements Application ~ Project No.3698860

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

Intervener Final ArgumentG-14-16
2016/06/22 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

Intervener Response to IR No. 1G-50-16
2016/06/23 PNG 2016-17 Revenue Requirements
Pacific Northern Gas Ltd. 2016-2017 Revenue Requirements Application ~ Project No.3698859

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

PNG Reply ArgumentG-13-16
2016/06/30 PNGNE 2016-17 Revenue Requirements
Pacific Northern Gas (N.E.) Fort St. John/Dawson Creek Division and Tumbler Ridge Division 2016-2017 Revenue Requirements Application ~ Project No.3698860

Panel: K. Keitly Panel Chair, H. Harowitz and R. Revel

Hearing Location:
Date & Time: @
Location: , ,

PNG Reply ArgumentG-14-16
2016/07/06 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

BC Hydro Rebuttal EvidenceG-50-16
2016/08/05 BCUC RIB Rate Report
British Columbia Utilities Commission Residential Inclining Block Rate Report to the Government of British Columbia ~ Project No.3698845



Hearing Location:
Date & Time: @
Location: , ,

Filing of ReportsA-10
2016/08/16 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

Oral Hearing August 16-18G-50-16
2016/08/23 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

Oral Hearing August 23-24G-50-16
2016/08/25 BC Hydro 2015 Rate Design Application
British Columbia Hydro and Power Authority 2015 Rate Design Application ~ Project No.3698781

Panel: D. Morton Panel Chair, K. Keilty, and D. Cote

Hearing Location:
Date & Time: @
Location: , ,

Additional Oral Hearing Days, if required August 25-26G-50-16