CB Powerline Ltd. Application for an Exemption from Part 3 of the Utilities Commission Act, pursuant to section 88(3) ~ Project No. 1599020

Timetable

SubjectDate
BC Hydro response to BCUC Information Request (IR) No. 1Friday, December 13, 2019
BCUC and Intervener IR No. 2 to CBPThursday, December 19, 2019
CBP response to BCUC and Intervener IR No. 2Thursday, January 16, 2020
CBP Written Final ArgumentThursday, January 30, 2020
Intervener Written Final ArgumentThursday, February 6, 2020
CBP Reply ArgumentThursday, February 13, 2020
  

Hearing Location

Hearing and Other Documents

Download a Document

TitleDocument Description
*_Exhibit List Updated: December 5, 2019 @ 9:55 am
  

Arguments

TitleDocument Description
  

Exhibits

"A" Exhibits - Commission Documents

TitleDocument Description
A-1 Letter dated July 4, 2019 - Appointing the Panel for the review of the CB Powerline Ltd. Application for Exemption from Part 3 of the Utilities Commission Act, pursuant to section 88(3)
A-2 Letter dated July 8, 2019 – BCUC Order G-151-19 establishing the regulatory timetable
A-3 Letter dated August 28, 2019 – BCUC Information Request No. 1 to CBP
A-4 Letter dated October 23, 2019 – BCUC Order G-253-19 establishing a further regulatory timetable
A-5 Letter dated November 21, 2019 – BCUC Information Request No. 1 to BC Hydro
A-6 Letter dated December 5, 2019 – BCUC Order G-315-19 amending the regulatory timetable
  

"B" Exhibits - Applicant Documents

TitleDocument Description
B-1 CB POWERLINE LTD. (CBP) – Application for Exemption from Part 3 of the Utilities Commission Act, pursuant to section 88(3) - Letter dated June 13, 2019 submitted by Pinter Electrical Consulting Inc.
B-2 Letter dated October 3, 2019 – CBP Submitting Responses to BCUC Information Request No. 1
B-3 Letter dated October 3, 2019 – CBP Submitting Responses to FBC Information Request No. 1
B-4 Letter dated October 17, 2019 – CBP Submission regarding further process
  

"C" Exhibits - Intervener Documents

TitleDocument Description
C1-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) - Letter dated August 9, 2019 Request to Intervene by Fred James
C1-2 Letter dated December 4, 2019 – BC Hydro Extension Request to file responses to BCUC Information Request No. 1
C2-1 FORTISBC INC. (FBC) - Letter dated August 22, 2019 - Request to Intervene by Doug Slater
C2-2 Letter dated September 5, 2019 - FBC Information Request No. 1 to CBP
C2-3 Letter dated October 17, 2019 – FBC Submitting no comment on further process
  

"D" Exhibits - Interested Party Documents

TitleDocument Description
D-1 SUNELL, G. – Letter dated August 8, 2019 – Request for Interested Party Status
  

"E" Exhibits - Letters of Comment

TitleDocument Description
E-1 FLINTOFF, D. – Letter of Comment dated October 28, 2019
  

Transcripts

TitleDocument Description