British Columbia Hydro and Power Authority Fleet Electrification Rate Application ~ Project No. 1599032

Timetable

SubjectDate
Intervener RegistrationWednesday, September 18, 2019
BCUC Information Request (IR) No. 1 to BC HydroMonday, September 30, 2019
Intervener IR No. 1 to BC HydroMonday, October 07, 2019
BC Hydro responses to BCUC and Intervener IR No. 1Wednesday, October 30, 2019
  

Hearing Location

Hearing and Other Documents

Download a Document

TitleDocument Description
*_EXHIBIT LIST Updated: September 18, 2019 @ 11:43 am
  

Arguments

TitleDocument Description
  

Exhibits

"A" Exhibits - Commission Documents

TitleDocument Description
A-1 Letter dated August 21, 2019 - Appointing the Panel for the review of the British Columbia Hydro and Power Authority Fleet Electrification Rate Application
A-2 Letter dated August 23, 2019 – BCUC Order G-198-19 establishing the Regulatory Timetable
  

"B" Exhibits - Applicant Documents

TitleDocument Description
B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Letter dated August 7, 2019 – Fleet Electrification Rate Application
B-2 Letter dated September 9, 2019 – BC Hydro Submission in compliance with Order G-198-19
  

"C" Exhibits - Intervener Documents

TitleDocument Description
  

"D" Exhibits - Interested Party Documents

TitleDocument Description
D-1 CITY OF WEST KELOWNA (COWK) Letter dated September 5, 2019 – Request for Interested Party Status by Stacey Harding
D-2 ECOWEST DRIVEN Letter dated September 5, 2019 – Request for Interested Party Status by Jarvis Shaver
D-3 SIEMENS DIGITAL GRID Letter dated September 12, 2019 – Request for Interested Party Status by Chris King
D-4 DISTRICT OF SAANICH (SAANICH) - Submission dated September 16, 2019 Request for Interested Party Status by Steven Wiebe
D-5 CHARGEPOINT - Letter dated September 18, 2019 Request for Interested Party Status by Suzanne Goldberg
  

"E" Exhibits - Letters of Comment

TitleDocument Description
  

Transcripts

TitleDocument Description