Boralex Ocean Falls Limited Partnership Application for Rates and Terms and Conditions for Service to the British Columbia Hydro and Power Authority - July 1, 2019 to December 31, 2022

Timetable

SubjectDate
Intervener RegistrationTuesday, November 19, 2019
Boralex Financial ModelMonday, November 25, 2019
Intervener Submissions on Regulatory ProcessFriday, November 29, 2019
Boralex Reply Submission on Regulatory ProcessFriday, December 13, 2019
  

Hearing Location

Hearing and Other Documents

Download a Document

TitleDocument Description
*_Exhibit List Updated: November 15, 2019 @ 11:46 am
  

Arguments

TitleDocument Description
  

Exhibits

"A" Exhibits - Commission Documents

TitleDocument Description
A-1 Letter dated October 17, 2019 - Appointing the Panel for the review of Boralex Ocean Falls Limited Partnership Application for Rates and Terms and Conditions for Service to British Columbia Hydro and Power Authority
A-2 Letter dated October 31, 2019 – BCUC Order G-265-19 establishing the Regulatory Timetable
  

"B" Exhibits - Applicant Documents

TitleDocument Description
B-1 BORALEX OCEAN FALLS LIMITED PARTNERSHIP (BORALEX LP) Application dated September 30, 2019 for Rates and Terms and Conditions of Service for Service to the British Columbia Hydro and Power Authority - July 1, 2019 to December 31, 2022
B-2 Letter dated November 13, 2019 – Boralex confirming compliance with Stakeholder notification process
  

"C" Exhibits - Intervener Documents

TitleDocument Description
C1-1 BC HYDRO AND POWER AUTHORITY (BC HYDRO) - Letter dated November 14, 2019 - Request for Intervener Status by Fred James
  

"D" Exhibits - Interested Party Documents

TitleDocument Description
D-1 HOULE-COUTURE, JUDITH (HOULE-COUTURE) - Submission dated October 29, 2019 Request for Interested Party Status
  

"E" Exhibits - Letters of Comment

TitleDocument Description
  

Transcripts

TitleDocument Description