FortisBC Energy Inc. System Extension Fund (SEF) Pilot Program Compliance Filing and Application for Approval of the SEF on a Permanent Basis

Timetable

SubjectDate
FEI to provide Public NoticeFriday, August 14, 2020
Intervener registration deadlineThursday, August 27, 2020
BCUC Information Request (IR) No. 1Thursday, August 27, 2020
Intervener IR No. 1Thursday, September 10, 2020
FEI response to BCUC and Intervener IRs No. 1Thursday, September 24, 2020
FEI Final ArgumentThursday, October 8, 2020
Intervener Final ArgumentThursday, October 15, 2020
FEI Reply ArgumentThursday, October 22, 2020
  

Hearing and Other Documents

Exhibits

"A" Exhibits - Commission Documents

"B" Exhibits - Proponent Documents