Pacific Northern Gas Ltd. (PNG) - Application for a Certificate of Public Convenience and Necessity (CPCN) for Construction of Kitimat Regulating Station LDS1

Timetable

SubjectDate
PNG to provide Public Notice of ApplicationFriday, April 16, 2021
Intervener registration deadlineMonday, April 26, 2021
BCUC Information Request (IR) No. 1 to PNGThursday, April 29, 2021
Intervener IR No. 1 to PNGMonday, May 3, 2021
PNG responses to BCUC and Intervener IR No. 1Monday, May 10, 2021
PNG Final ArgumentFriday, May 14, 2021
Intervener Final ArgumentFriday, May 21, 2021
PNG Reply ArgumentFriday, May 28, 2021
  

Hearing and Other Documents

Exhibits

"A" Exhibits - Commission Documents

"B" Exhibits - Proponent Documents