Completed: 2022
On June 14, 2022, Plateau Pipe Line Ltd. (Plateau) submitted an application to the BCUC for approval for the abandonment of service as a common carrier on the Southern Segment of its Western pipeline system.
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: October 4, 2022 @ 9:26 am |
G-282-22 | Final Order October 11, 2022 |
Date | Title | Document Description |
---|---|---|
July 13, 2022 | A-1 | Letter dated July 13, 2022 – BCUC appointment of panel for the review of the Application for Abandonment of Service for the Western System (South) |
August 17, 2022 | A-2-1 | Letter dated August 17, 2022 – BCUC issuing Order G-233-22A establishing the regulatory timetable |
August 24, 2022 | A-3 | Letter dated August 24, 2022 – BCUC adjourning the proceeding |
August 24, 2022 | A-2 | Letter dated August 17, 2022 – BCUC issuing Order G-233-22 establishing the regulatory timetable – Replaced by Exhibit A-2-1 |
August 31, 2022 | A-4 | Letter dated August 31, 2022 – BCUC issuing Order G-246-22 amending the regulatory timetable and varying Order G-233-22A |
September 08, 2022 | A-5 | Letter dated September 8, 2022 – BCUC issuing Information Request No. 1 to Plateau |
Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.