Completed: 2023
FBC seeks approval to replace the A.S. Mawdsley (ASM) Terminal Station by expanding the Warfield Terminal Station (WTS). The Project includes the installation of two new 150 MVA 63/161 kV transformers, associated substation alterations at WTS and the decommissioning and demolition of the existing ASM Terminal Station.
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: October 10, 2023 @ 6:53 pm |
Decision and C-6-23 | Decision and C-6-23 December 6, 2023 |
Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.
Learn more