Completed: 2023
FBC seeks approval to replace the A.S. Mawdsley (ASM) Terminal Station by expanding the Warfield Terminal Station (WTS). The Project includes the installation of two new 150 MVA 63/161 kV transformers, associated substation alterations at WTS and the decommissioning and demolition of the existing ASM Terminal Station.
Title | Document Description |
---|---|
Decision and C-6-23 | Decision and C-6-23 December 6, 2023 |
EXHIBIT LIST | Updated: October 10, 2023 @ 6:53 pm |