Enbridge ACGS Acquisition Inc

Application to Acquire Control of the Shares of Aitken Creek Gas Storage ULC

Completed: 2023

Enbridge ACGS Acquisition Inc. is seeking BCUC approval to acquire control of the shares of Aitken Creek Gas Storage ULC pursuant to sections 54(7) and 54(9) of the Utilities Commission Act.

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: September 26, 2023 @ 3:17 pm
G-274-23 Final Order October 16, 2023

Arguments/Submissions

Title Document Description
Enbridge Final Argument Final Argument September 13, 2023
FEI Final Argument Final Argument September 25, 2023
CEC Final Argument Final Argument September 27, 2023
Enbridge No Reply Argument No Reply Argument September 28, 2023

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
June 02, 2023 A-1 Letter dated June 2, 2023 – Appointing the Panel for the review of Enbridge Application to Acquire Control of the Shares of Aitken Creek Gas Storage ULC
June 13, 2023 A-2 Letter dated June 13, 2023 – BCUC Order G-139-23 establishing a regulatory timetable
July 10, 2023 A-3 Letter dated July 10, 2023 – BCUC Information Request No. 1 to Enbridge
July 10, 2023 A-4 CONFIDENTIAL - Letter dated July 10, 2023 – BCUC Confidential Information Request No. 1 to Enbridge
August 23, 2023 A-5 Letter dated August 23, 2023 – BCUC Order G-223-23 amending the regulatory timetable
September 26, 2023 A-6 Letter dated September 26, 2023 – Amending the Panel for the review of the Application

B Exhibits - Applicant Documents

Date Title Document Description
May 12, 2023 B-2-1 CONFIDENTIAL - Letter dated May 12, 2023 - Enbridge submitting Confidential Purchase Agreement
May 12, 2023 B-1 ENBRIDGE AITKEN CREEK GAS STORAGE ULC ACQUISITION INC. (ENBRIDGE) - Application Pursuant to Sections 54(7) and (9) of the Utilities Commission Act (UCA) dated May 12, 2023
May 12, 2023 B-2 Letter dated May 12, 2023 - Enbridge submitting request for confidentiality
June 19, 2023 B-3 Letter dated June 19, 2023 - Enbridge submitting response regarding a Public Purchase Agreement
June 19, 2023 B-4 Letter dated June 19, 2023 - Enbridge submitting summary of Stakeholder Consultation
June 29, 2023 B-5 Letter dated June 29, 2023 – Enbridge submitting notice of compliance with Exhibit A-2
August 09, 2023 B-6 Letter dated August 9, 2023 – Enbridge submitting responses to FEI Information Request No. 1
August 09, 2023 B-7 Letter dated August 9, 2023 – Enbridge submitting responses to BCUC Information Request No. 1
August 09, 2023 B-8 CONFIDENTIAL - Letter dated August 9, 2023 – Enbridge submitting confidential responses to BCUC Confidential Information Request No. 1
August 09, 2023 B-8-1 PUBLIC - Letter dated August 9, 2023 – Enbridge submitting redacted confidential responses to BCUC Confidential Information Request No. 1
August 09, 2023 B-9 PUBLIC - Letter dated August 9, 2023 – Enbridge submitting redacted responses to CEC Information Request No. 1
August 09, 2023 B-9-1 CONFIDENTIAL - Letter dated August 9, 2023 – Enbridge submitting confidential responses to CEC Information Request No. 1
August 29, 2023 B-10 Letter dated August 29, 2023 – Enbridge submitting notice to file early Reply Argument
September 13, 2023 B-11 Letter dated September 13, 2023 – Enbridge submitting request regarding timing with respect to the transaction

C Exhibits - Intervener Documents



Date Title Document Description
June 28, 2023 C5-1 BP CANADA ENERGY GROUP ULC (BP CANADA) - Letter dated June 28, 2023 - Request for Intervener Status by Kim Johnston
June 27, 2023 C4-1 NOVA GAS TRANSMISSION LTD. (NGTL) - Letter dated June 27, 2023 - Request for Intervener Status by Martin Gonzalez
June 26, 2023 C3-1 TENASKA MARKETING CANADA (TMC) - Letter dated June 26, 2023 - Request for Intervener Status by Tomasz Lange
July 17, 2023 C2-2 Letter dated July 17, 2023 – CEC submitting Information Request No. 1 to Enbridge
June 23, 2023 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) - Letter dated June 23, 2023 - Request for Intervener Status by David Craig
July 17, 2023 C1-2 Letter dated July 17, 2023 – FEI submitting Information Request No. 1 to Enbridge
June 20, 2023 C1-1 FORTISBC ENERGY INC. (FEI) - Letter dated June 20, 2023 - Request for Intervener Status by Sarah Walsh