Kyuquot Power

2024 Revenue Requirements

Completed: 2024

Kyuquot Power Ltd. is seeking BCUC approval to change its rate schedules for electricity service and other related rate matters.

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: November 8, 2023 @ 9:15 am
Decision and G-53-24 Decision and Order G-53-24 February 29, 2024

Arguments/Submissions

Title Document Description
KPL Reply Argument Reply Argument December 11, 2023
KPL Final Argument Final Argument November 16, 2023
KCFN Final Argument Final Argument November 30, 2023

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
July 04, 2023 A-1 Letter dated July 4, 2023 – Appointing the Panel for the review of Kyuquot Power Limited 2024 Revenue Requirements Application
August 02, 2023 A-2 Letter dated August 2, 2023 – BCUC Order G-206-23 establishing a regulatory timetable
September 01, 2023 A-3 Letter dated September 1, 2023 – BCUC Information Request No. 1 to KPL
September 14, 2023 A-4 Letter dated September 14, 2023 – BCUC Order G-243-23 with an amended regulatory timetable
October 24, 2023 A-5 Letter dated October 24, 2023 – BCUC Order G-288-23 with an amended regulatory timetable
October 24, 2023 A-6 Letter dated October 24, 2023 – BCUC submitting Panel Information Request No. 1 to KPL
September 01, 2023 A2-1 Letter dated September 1, 2023 – Staff submitting KPL Response to Directive 6 of Order G-302-22
September 01, 2023 A2-2 Letter dated September 1, 2023 – Staff submitting KPL Response to Directive 8 of Order G-302-22

B Exhibits - Applicant Documents

Date Title Document Description
June 12, 2023 B-1 KYUQUOT POWER LIMITED (KPL) - 2024 Revenue Requirements Application (RRA) dated June 12, 2023
June 12, 2023 B-1-1 CONFIDENTIAL - Letter dated June 12, 2023 – KPL submitting 2024 RRA confidential Appendices
June 30, 2023 B-1-2 Letter dated June 30, 2023 – KPL submitting replacement amendment errata to the 2024 RRA
August 14, 2023 B-2 Letter dated August 14, 2023 – KPL submitting compliance to Order G-206-23 Directive 5
September 12, 2023 B-3 Letter dated September 12, 2023 – KPL submitting extension request to file responses to BCUC Information Request No. 1
October 11, 2023 B-4 Letter dated October 11, 2023 – KPL submitting responses to BCUC Information Request No. 1
October 11, 2023 B-5 Letter dated October 11, 2023 – KPL submitting responses to KCFN Information Request No. 1
November 07, 2023 B-6 Letter dated November 7, 2023 – KPL submitting response to BCUC Panel Information Request No. 1

C Exhibits - Intervener Documents

D Exhibits - Letters of Comment

Date Title Document Description
June 30, 2023 D-1 KYUQUOT CHECKLESAHT FIRST NATIONS (KCFN) – Letter of Comment dated June 30, 2023

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more