Completed: 2024
FBC is seeking BCUC approval to construct a new substation with two new 20 MVA transformers at 2064 Grieve Road, Fruitvale, BC and the decommissioning of the existing Fruitvale and Hearns substations.
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: July 9, 2024 @ 10:50 am |
Order C-4-24 | Final Order September 4, 2024 |
Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.
Learn more