FBC is seeking BCUC approval to construct a new substation with two new 20 MVA transformers at 2064 Grieve Road, Fruitvale, BC and the decommissioning of the existing Fruitvale and Hearns substations.
Title | Document Description |
---|---|
Order C-4-24 | Final Order September 4, 2024 |
EXHIBIT LIST | Updated: July 9, 2024 @ 10:50 am |