November 02, 2015 |
B-45 |
Letter dated October 31, 2015 - Creative Energy submitting First Amending Agreement |
September 18, 2015 |
B-44 |
Letter dated September 18, 2015 - Creative Energy submitting Undertakings |
September 18, 2015 |
B-43 |
Letter dated September 18, 2015 - Creative Energy submitting UBC Undertakings |
September 17, 2015 |
B-42 |
Submitted at Oral Hearing September 16, 2015 – Creative Energy IR RESPONSES BY FAES TO THE BCUC IN THE MARINE GATEWAY PROCEEDINGS |
September 17, 2015 |
B-41-1 |
Submitted at Oral Hearing September 16, 2015 – Creative Energy EXCERPTS FROM FORTISBC ENERGY INC. BIOMETHANE ENERGY RECOVERY CHARGE RATE METHODOLOGY APPLICATION |
September 17, 2015 |
B-41 |
Submitted at Oral Hearing September 16, 2015 – Creative Energy ELECTRONIC COPY OF FORTISBC ENERGY INC. BIOMETHANE ENERGY RECOVERY CHARGE RATE
METHODOLOGY APPLICATION
|
September 16, 2015 |
B-40 |
Submitted at Oral Hearing September 15, 2015 – Creative Energy WITNESS AID, "RE: COST PER MEGAWATT HOUR FUEL VEERSUS COST PER MEGAWATT HOUR IN USE" |
September 16, 2015 |
B-39 |
Submitted at Oral Hearing September 15, 2015 – Creative Energy WITNESS AID, "RE: MAINTENANCE COSTS" |
September 16, 2015 |
B-38 |
Submitted at Oral Hearing September 15, 2015 – Creative Energy WITNESS AID "RE: ON-SITE BOILERS WITH RNG" |
September 15, 2015 |
B-37 |
Submitted at Oral Hearing September 14, 2015 - Creative Energy PROJECT SCHEDULE UPDATE |
September 15, 2015 |
B-36 |
Submitted at Oral Hearing September 14, 2015 - Creative Energy DETAILED ZONING MAP |
September 11, 2015 |
B-35 |
Letter dated September 11, 2015 - Creative Energy submitting Opening Statement |
September 10, 2015 |
B-34 |
Letter dated September 9, 2015 - Creative Energy submitting Rebuttal Testimony of Orion Henderson, University of British Columbia |
September 10, 2015 |
B-33 |
Letter dated September 9, 2015 - Creative Energy submitting Rebuttal Evidence of Reshape Infrastructure Strategies |
September 10, 2015 |
B-32 |
Letter dated September 8, 2015 - Creative Energy submitting Direct Testimony of Jim Manson |
September 08, 2015 |
B-31 |
Letter dated September 8, 2015 - Creative Energy submitting Connection Agreement, Form of Statutory Right of Way and Customer Agreement |
September 08, 2015 |
B-30 |
Letter dated September 4, 2015 - Creative Energy submitting expert witness testimony |
August 24, 2015 |
B-29 |
Letter dated August 21, 2015 - Creative Energy submitting Information Request No. 1 to FEI |
August 24, 2015 |
B-28-1 |
Removed - to B-24-1 |
August 24, 2015 |
B-28 |
Letter dated August 21, 2015 - Creative Energy submitting Information Request No. 1 to FAES |
August 24, 2015 |
B-27 |
Letter dated August 21, 2015 - Creative Energy submitting Information Request No. 1 to Dr. Ware |
August 06, 2015 |
B-26 |
Letter dated August 5, 2015 – Creative Energy submitting responses to UDI Information Request No. 2 |
August 06, 2015 |
B-25 |
Letter dated August 5, 2015 – Creative Energy submitting responses to CEC Information Request No. 2 |
August 06, 2015 |
B-24-1 |
Letter dated September 4, 2015 -Creative Energy submitting responses to FAES to IR 2.2.1 |
August 06, 2015 |
B-24 |
Letter dated August 5, 2015 – Creative Energy submitting responses to FAES Information Request No. 2 |
August 06, 2015 |
B-23 |
Letter dated August 5, 2015 – Creative Energy submitting responses to FortisBC Energy Information Request No. 2 |
August 06, 2015 |
B-22-3 |
Letter dated August 31, 2015 – Creative Energy submitting Cover Letter to Confidential IR |
August 06, 2015 |
B-22-2 |
Letter dated August 6, 2015 – Creative Energy submitting the working Excel Spreadsheet for BCUC IR2-19.2 |
August 06, 2015 |
B-22-1 |
CONFIDENTIAL Letter dated August 5, 2015 – Creative Energy submitting confidential responses to BCUC Information Request No. 2 |
August 06, 2015 |
B-22 |
Letter dated August 5, 2015 – Creative Energy submitting responses to BCUC Information Request No. 2 |
July 21, 2015 |
B-21 |
Letter dated July 20, 2015 – Creative Energy submitting response to Exhibit A-9 |
July 20, 2015 |
B-20 |
Letter dated July 20, 2015 – Creative Energy submitting response to FEI extension request |
July 20, 2015 |
B-19 |
Letter dated July 20, 2015 – Creative Energy submitting supplemental responses to FAES IR No. 1 |
July 17, 2015 |
B-18 |
Letter dated July 16, 2015 – Creative Energy submitting supplemental responses to CEC IR No. 1 |
July 17, 2015 |
B-17-1 |
Letter dated July 20, 2015 – Creative Energy submitting further supplemental responses to FEI IR No. 1 |
July 17, 2015 |
B-17 |
Letter dated July 16, 2015 – Creative Energy submitting supplemental responses to FEI IR No. 1 |
July 17, 2015 |
B-16-1 |
Letter dated July 20, 2015 – Creative Energy submitting further supplemental responses to BCUC IR No. 1 |
July 17, 2015 |
B-16 |
Letter dated July 16, 2015 – Creative Energy submitting supplemental responses to BCUC IR No. 1 |
July 10, 2015 |
B-15 |
Letter dated July 9, 2015 – Creative Energy proposed revised regulatory process and schedule |
June 30, 2015 |
B-14 |
Letter dated June 29, 2015 - Creative Energy response to UDI IR No. 1 |
June 30, 2015 |
B-13 |
Letter dated June 29, 2015 - Creative Energy response to Onni IR No. 1 |
June 30, 2015 |
B-12 |
Letter dated June 29, 2015 - Creative Energy response to Geo-Exchange IR No. 1 |
June 30, 2015 |
B-11 |
Letter dated June 29, 2015 - Creative Energy response to FEI IR No. 1 |
June 30, 2015 |
B-10 |
Letter dated June 29, 2015 - Creative Energy response to FAES IR No. 1 |
June 30, 2015 |
B-9 |
Letter dated June 29, 2015 - Creative Energy response to CEC IR No. 1 |
June 30, 2015 |
B-8 |
Letter dated June 29, 2015 - Creative Energy response to BCOAPO IR No. 1 |
June 30, 2015 |
B-7 |
Confidential Letter dated June 29, 2015 - Creative Energy response to Confidential BCUC IR No. 1 |
June 30, 2015 |
B-6-3 |
Letter dated July 17, 2015 – Creative Energy submitting updated response to BCUC IR 13.3 |
June 30, 2015 |
B-6-2 |
Letter dated July 7, 2015 - Creative Energy submitting updated tables IR 1.X.2 and UR I.X.3 |
June 30, 2015 |
B-6-1 |
Letter dated July 2, 2015 - Creative Energy re-submitting Appendices 1-7 |
June 30, 2015 |
B-6 |
Letter dated June 29, 2015 - Creative Energy response to BCUC IR No. 1 |
June 01, 2015 |
B-5 |
Letter dated May 29, 2015 – Creative Energy response to comments on process |
May 26, 2015 |
B-4 |
Letter dated May 25, 2015 – Creative Energy Request to Respond to items regarding the Streamlined Review Process |
May 21, 2015 |
B-3 |
Letter dated May 20, 2015 – Creative Energy Submitting Building Compatibility Design Guide |
May 06, 2015 |
B-2 |
Letter dated May 6, 2015 – Creative Energy Submitting By-law updates and Schedule 8 |
May 01, 2015 |
B-1-3 |
Letter dated September 4, 2015 - Creative Energy submitting Errata to the Application |
May 01, 2015 |
B-1-2 |
Letter dated September 4, 2015 - Creative Energy submitting updated draft order |
May 01, 2015 |
B-1-1 |
CONFIDENTIAL Letter dated April 17, 2015 – Confidential Financial Model |
May 01, 2015 |
B-1 |
Creative Energy Vancouver Platforms Inc. (CREATIVE ENERGY) Letter dated April 17, 2015 – Application for a Certificate of Public Convenience and Necessity for a Low Carbon Neighbourhood Energy System for Northeast False Creek and Chinatown Neighbourhoods of Vancouver |