PKM Canada (Jet Fuel)

2019 Tariff Filing

Completed: 2022

Hearing and Other Documents

Title Document Description
P-6-19 Interim Toll Final Order with Reasons June 28, 2019
EXHIBIT LIST Updated: February 14, 2022 @ 5:03 pm
P-1-22 Final Order February 17, 2022

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
December 17, 2018 A-1 Letter dated December 17, 2018 – Appointing the Panel for the review of Kinder Morgan Canada (Jet Fuel) Inc.’s 2019 Tariff Filing Application
December 17, 2018 A-2 Letter dated December 17, 2018 – BCUC Order P-1-18 establishing a regulatory timetable
December 21, 2018 A-3 Letter dated December 21, 2018 – BCUC Information Request No. 1 to KMJF
December 28, 2018 A-4 Letter dated December 28, 2018 – BCUC Order P-2-18 amending the regulatory timetable
January 11, 2019 A-5 Letter dated January 11, 2019 – BCUC Order P-1-19 amend the regulatory timetable
February 07, 2019 A-6 Letter dated February 7, 2019 – BCUC Order P-2-19 amending the regulatory timetable
March 11, 2019 A-7 Letter dated March 11, 2019 – BCUC Order P-3-19 amending the regulatory timetable
March 14, 2019 A-8 Letter dated March 14, 2019 – BCUC Order P-3-19A amending and rescinding Order P-3-19
April 10, 2019 A-9 Letter dated April 10, 2019 – BCUC Order P-4-19 amending the regulatory timetable
April 30, 2019 A-10 Letter dated April 30, 2019 – Temporary suspension of the regulatory timetable
May 02, 2019 A-11 Letter dated May 2, 2019 – Amending the Panel to conduct the review of Kinder Morgan Canada (Jet Fuel) Inc.’s 2019 Tariff Filing Application
May 07, 2019 A-12 Letter dated May 7, 2019 – BCUC Order P-5-19 amending the regulatory timetable
July 08, 2019 A-13 Letter dated July 8, 2019 – BCUC Information Request No. 2 to KMJF
August 06, 2019 A-14 Letter dated August 6, 2019 – BCUC Order P-7-19 amending the regulatory timetable
September 12, 2019 A-15 Letter dated September 12, 2019 – BCUC Order P-8-19 amending the regulatory timetable
September 16, 2019 A-16 Letter dated September 16, 2019 – BCUC Order P-9-19 amending the regulatory timetable
November 08, 2019 A-17 Letter dated November 8, 2019 – BCUC response on Request for Confidentiality Order
November 19, 2019 A-18 Letter dated November 19, 2019 – BCUC Order P-10-19 with Reasons for Decision amending the regulatory timetable
November 21, 2019 A-19 Letter dated November 21, 2019 – BCUC Response to Confidential 2018 KMJF Cost of Debt Information Letter
November 27, 2019 A-20 Letter dated November 27, 2019 – BCUC Order P-11-19 amending the regulatory timetable
December 05, 2019 A-21 Letter dated December 5, 2019 – BCUC Order P-12-19 amending the regulatory timetable
December 05, 2019 A-22 Letter dated December 5, 2019 – BCUC response to KMJF letter dated November 12, 2019
December 20, 2019 A-23 Letter dated December 20, 2019 – BCUC Order P-13-19 with Reasons for Decision setting interim tariff
December 24, 2019 A-24 Letter dated December 24, 2019 – Panel request for intervener submissions on VAFFC’s application to temporarily suspend the regulatory timetable for further and better information request responses
January 10, 2020 A-25 Letter dated January 10, 2020 – BCUC Response to KMJF Confidentiality Request to Documents Filed in IRs 22.1 and 23.1
January 13, 2020 A-26 Letter dated January 13, 2020 - BCUC Order P-1-20 Suspending the Regulatory Timetable
January 21, 2020 A-27 Letter dated January 21, 2020 – BCUC Response to VAFFC Request to Access Confidential Documents filed in IR 22.1 and IR 23.1
April 09, 2020 A-28 Letter dated April 9, 2020 – BCUC Order P-2-20 establishing amended regulatory timetable with reasons for decision
May 01, 2020 A-29 Letter dated May 1, 2020 – BCUC Letter granting PKMJF’s request for confidentiality over non-redacted February 2020 Wetmore Retainer Agreement
May 05, 2020 A-30 Letter dated May 5, 2020 – BCUC Response to VAFFC Request to Access non-redacted February 2020 Wetmore Retainer Agreement
May 11, 2020 A-31 Letter dated May 11, 2020 – BCUC Information Request No. 3 to PKMJF
June 02, 2020 A-32 Letter dated June 2, 2020 – BCUC Order P-3-20 Amending the Regulatory Timetable
June 24, 2020 A-33 Letter dated June 24, 2020 – BCUC Letter L-39-20 Requesting PKMJF written response to VAFFC and Parkland Submissions
August 10, 2020 A-34 Letter dated August 11, 2020 – BCUC Order P-4-20 with reasons for decision and the amended regulatory timetable
August 18, 2020 A-35 Letter dated August 18, 2020 – BCUC Letter L-52-20 requesting comments from PKMJF on VAFFC request for suspension of regulatory timetable
August 24, 2020 A-36 Letter dated August 24, 2020 – BCUC Letter L-53-20 extending filing deadline for PKMJF supplementary IR responses
September 02, 2020 A-37 Letter dated September 2, 2020 – BCUC Order P-5-20 issuing an amended regulatory timetable
September 04, 2020 A-38 Letter dated September 4, 2020 – BCUC Response to PKMJF’s request for confidential treatment for certain IR responses
September 17, 2020 A-39 Letter dated September 17, 2020 – BCUC Order P-6-20 issuing an amended regulatory timetable
October 08, 2020 A-40 Letter dated October 8, 2020 – BCUC Response to PKMJF’s Request for Confidentiality, VAFFC Request for Unredacted Copies of Certain Documents, and VAFFC’s and Parkland’s Requests to Amend the Regulatory Timetable
October 22, 2020 A-41 Letter dated October 22, 2020 – BCUC response to VAFFC Request for Unredacted Copies of Certain Documents and VAFFC’s and Parkland Requests to Amend the Regulatory Timetable
November 12, 2020 A-42 Letter dated November 12, 2020 – BCUC response to PKMJF’s October 27, 2020 document submission and VAFFC’s and PKMJF’s October 29 and 30, 2020 letters, respectively
November 27, 2020 A-43 Letter dated November 27, 2020 – BCUC response to PKMJF’s November 19, 2020 request for confidentiality
December 02, 2020 A-44 Letter dated December 2, 2020 – BCUC Order P-7-20 further amending the regulatory timetable
December 10, 2020 A-45 Letter dated December 10, 2020 – BCUC Order P-8-20 extending interim toll
January 25, 2021 A-46 Letter dated January 25, 2021 – BCUC Information Request No. 1 to Parkland Refining (BC) Ltd.
January 25, 2021 A-47 CONFIDENTIAL Letter dated January 25, 2021 – BCUC Confidential Information Request No. 1 to Parkland
January 25, 2021 A-48 Letter dated January 25, 2021 – BCUC Information Request No. 1 to VAFFC
January 25, 2021 A-49 CONFIDENTIAL Letter dated January 25, 2021 – BCUC Confidential Information Request No. 1 to VAFFC
February 04, 2021 A-50 Letter dated February 4, 2021 – BCUC Order P-1-21 further amending the regulatory timetable
March 16, 2021 A-51 Letter dated March 16, 2021 – BCUC Order P-2-21 further amending the regulatory timetable
March 29, 2021 A-52 Letter dated March 29, 2021 – BCUC Order P-3-21 further amending the regulatory timetable
March 30, 2021 A-53 Letter dated March 30, 2021 – BCUC Information Request No. 4 to PKMJF
March 30, 2021 A-54 CONFIDENTIAL Letter dated March 30, 2021 – BCUC Confidential Information Request No. 1 to PKMJF
April 12, 2021 A-55 Letter dated April 12, 2021 – BCUC offering Parkland opportunity to submit a reply submission to Joint Suspension Request
April 15, 2021 A-56 Letter dated April 15, 2021 – BCUC Order P-4-21 with Reasons for Decision
April 27, 2021 A-57 Letter dated April 27, 2021 – BCUC response to Shell Canada regarding the regulatory timetable and letter of comment filing
May 17, 2021 A-58 Letter dated May 17, 2021 – BCUC request submissions regarding VAFFC request
May 27, 2021 A-59 Letter dated May 27, 2021 – BCUC Order P-5-21 further amending the regulatory timetable
June 18, 2021 A-60 Letter dated June 18, 2021 – BCUC letter postponing workshop
June 29, 2021 A-61 Letter dated June 29, 2021 – BCUC submitting procedural conference information and Order P-6-21 further amending the regulatory timetable
August 06, 2021 A-62 Letter dated August 6, 2021 – BCUC Request for Submissions regarding VAFFC’s request regarding adjournment of procedural conference
August 10, 2021 A-63 Letter dated August 10, 2021 – BCUC Order P-7-21 further amending the regulatory timetable and requesting submissions
September 20, 2021 A-64 Letter dated September 20, 2021 – BCUC request for submissions
September 24, 2021 A-65 Letter dated September 24, 2021 – BCUC response to PKMJF extension request
October 28, 2021 A-66 Letter dated October 28, 2021 – BCUC response to PKMJF request for Adjournment
December 01, 2021 A-67 Letter dated December 1, 2021 – BCUC response to PKMJF Request for Continued Adjournment
December 13, 2021 A-68 Letter dated December 13, 2021 – BCUC Order P-8-21 extending the Interim Toll
December 15, 2021 A-69 Letter dated December 15, 2021 – BCUC response to PKMJF Request for Continued Adjournment and PKMJF update on January 7, 2022
January 24, 2022 A-70 Letter dated January 24, 2022 – BCUC response to PKMJF Request for Continued Adjournment
July 08, 2019 A2-1 Letter dated July 8, 2019 – BCUC staff filing KMJF’s Appendix 1 of 2010 Tariff Filing dated December 7, 2010
January 25, 2021 A2-2 Letter dated January 25, 2021 – BCUC staff submitting Trans Mountain 2010 Tariff Filing Application dated December 7, 2009
May 05, 2021 A2-3 Letter dated May 5, 2021 – BCUC staff submitting compliance letter concerning PKMJF Shutdown of Jet Fuel Pipeline dated May 3, 2021
September 20, 2021 A2-4 Letter dated September 20, 2021 – BCUC staff submitting letter - Vancouver Airport Fuel Facilities Corporation - Complaint Regarding Jet Fuel Line Abandonment of Service - Evidentiary Update regarding Jet Fuel Supply dated August 31, 2021

B Exhibits - Applicant Documents

Date Title Document Description
February 11, 2022 B-94 Letter dated February 11, 2022 - PKMJF submitting Negotiated Settlement
February 07, 2022 B-93 Letter dated February 7, 2022 PKMJF submitting update regarding Agreement in Principle
January 21, 2022 B-92 Letter dated January 21, 2022 – PKMJF submitting extension request regarding Agreement in Principle
January 07, 2022 B-91 Letter dated January 7, 2022 – PKMJF submitting update regarding Agreement in Principle
December 13, 2021 B-90 Letter dated December 13, 2021 – PKMJF submitting request to extend the suspension of the Proceeding
December 08, 2021 B-89 Letter dated December 8, 2021 – PKMJF submission regarding interim toll
November 26, 2021 B-88 Letter dated November 26, 2021 – PKMJF submitting request for extension to the suspension of the regulatory timetable
November 19, 2021 B-87 Letter dated November 19, 2021 – PKMJF submitting update on negotiations and proceeding adjournment
October 25, 2021 B-86 Letter dated October 25, 2021 – PKMJF submitting request to suspend the Regulatory Timetable
October 04, 2021 B-85 Letter dated October 4, 2021 – PKMJF submitting response to BCUC request for submissions
September 22, 2021 B-84 Letter dated September 22, 2021 – PKMJF submitting extension request to file Evidentiary Update
September 01, 2021 B-83 Letter dated September 1, 2021 – PKMJF submitting reply regarding further process
August 27, 2021 B-82 Letter dated August 27, 2021 – PKMJF submitting Update on Negotiations
August 18, 2021 B-81 Letter dated August 18, 2021 – PKMJF submitting response regarding a Further Regulatory Timetable
August 09, 2021 B-80 Letter dated August 9, 2021 – PKMJF submitting response to VAFFC’s letter dated August 3, 2021
July 08, 2021 B-79 Letter dated July 8, 2021 – PKMJF submitting Confidentiality Declaration and Undertaking for Stephanie Ridge
June 10, 2021 B-78 Letter dated June 10, 2021 – PKMJF submitting independent expert Mr. Erik Wetmore is unavailable to attend Workshop
May 19, 2021 B-77 Letter dated May 19, 2021 – PKMJF submitting reply to VAFFC Response
May 18, 2021 B-76 Letter dated May 18, 2021 – PKMJF submitting response to BCUC request for submissions
May 14, 2021 B-75 Letter dated May 14, 2021 – PKMJF submitting Further Update regarding Pipeline Shut Down
May 11, 2021 B-74 Letter dated May 11, 2021 – PKMJF submitting Update regarding Pipeline Shut Down
May 11, 2021 B-73 Letter dated May 11, 2021 – PKMJF submitting Update regarding Status of Settlement Negotiations
May 04, 2021 B-72 Letter dated May 4, 2021 – PKMJF submitting response to BCUC Letter dated May 3, 2021 provided in Exhibit A2-3
April 30, 2021 B-71 Letter dated April 30, 2021 – PKMJF submitting notification provided to shippers
April 27, 2021 B-70-1 Letter dated April 27, 2021 – PKMJF submitting responses to BCUC Information Request No. 4 with redacted confidential responses
April 27, 2021 B-70 CONFIDENTIAL – Letter dated April 27, 2021 – PKMJF submitting Confidential responses to BCUC Confidential Information Request No. 4
April 27, 2021 B-69 CONFIDENTIAL – Letter dated April 27, 2021 – PKMJF submitting Confidential responses to BCUC Confidential Information Request No. 1
April 27, 2021 B-68 Letter dated April 27, 2021 – PKMJF submitting responses to VAFFC Information Request No. 3
April 27, 2021 B-67 Letter dated April 27, 2021 – PKMJF submitting responses to Parkland Information Request No. 3
April 27, 2021 B-66 Letter dated April 27, 2021 – PKMJF submitting update on status of settlement negotiations
April 12, 2021 B-65 Letter dated April 12, 2021 – PKMJF submitting response regarding VAFFC and Parkland submissions to suspend proceeding
March 24, 2021 B-64-3-1 REDACTED - Letter dated March 24, 2021 – PKMJF submitting redacted version of confidential Rebuttal Evidence of PKMJF
March 08, 2021 B-64-3 CONFIDENTIAL - Letter dated March 8, 2021 – PKMJF submitting Confidential Rebuttal Evidence with Attachments
March 08, 2021 B-64-2 Letter dated March 8, 2021 – PKMJF submitting Rebuttal Evidence Amended Revenue Requirements Schedules - confidentiality removed
March 24, 2021 B-64-1-1 REDACTED - Letter dated March 24, 2021 – PKMJF submitting redacted version of confidential Expert Rebuttal Report of Erik Wetmore
March 08, 2021 B-64-1 CONFIDENTIAL - Letter dated March 8, 2021 – PKMJF submitting Confidential Expert Rebuttal Evidence Attachments 1-6
March 08, 2021 B-64 Letter dated March 8, 2021 – PKMJF submitting Confidential Rebuttal Evidence- confidentiality removed
March 03, 2021 B-63 Letter dated March 3, 2021 – PKMJF submitting Confidentiality Declaration and Undertakings
February 03, 2021 B-62 Letter dated February 3, 2021 – PKMJF submitting response to VAFFC extension request to file Intervener Information Request Response
February 01, 2021 B-61-2 REDACTED - Letter dated February 1, 2021 – PKMJF redacted Confidential Information Request No. 1 to Parkland
January 25, 2021 B-61-1 CONFIDENTIAL - Letter dated January 25, 2020 – PKMJF submitting Information Request No. 1 to Parkland
January 25, 2021 B-61 Letter dated January 25, 2020 – PKMJF submitting Information Request No. 1 to Parkland
February 01, 2021 B-60-2 REDACTED - Letter dated February 1, 2021 – PKMJF redacted Confidential Information Request No. 1 to VAFFC
January 25, 2021 B-60-1 CONFIDENTIAL - Letter dated January 25, 2020 – PKMJF submitting Information Request No. 1 to VAFFC
January 25, 2021 B-60 Letter dated January 25, 2020 – PKMJF submitting Information Request No. 1 to VAFFC
January 04, 2021 B-59 Letter dated January 4, 2021 – PKMJF submitting Terri-Lee Oleniuk and David Tupper of Blake, Cassels & Graydon LLP as counsel
December 22, 2020 B-58 Letter dated December 22, 2020 – PKMJF submitting Rosa Wyman, Regulatory Law Chambers is no longer Lawyer of Record
December 17, 2020 B-57 Letter dated December 17, 2020 – PKMJF submitting 2021 Interim Tariff
December 07, 2020 B-56 Letter dated December 7, 2020 – PKMJF submitting Extension Request of 2021 Interim Tariff
December 01, 2020 B-55 Letter dated December 1, 2020 – PKMJF response regarding request for confidentiality
November 19, 2020 B-54-1 CONFIDENTIAL - Letter dated November 19, 2020 – PKMJF confidential response to BCUC letter dated November 12, 2020 (Exhibit A-42)
November 19, 2020 B-54 Letter dated November 19, 2020 – PKMJF response to BCUC letter dated November 12, 2020 (Exhibit A-42)
October 30, 2020 B-53 Letter dated October 30, 2020 – PKMJF response to VAFFC letter dated October 29, 2020 (Exhibit C2-34)
October 27, 2020 B-52-1 CONFIDENTIAL - Letter dated October 27, 2020 – PKMJF response to BCUC Exhibit A-41
October 27, 2020 B-52 Letter dated October 27, 2020 – PKMJF response to BCUC Exhibit A-41-Redacted
October 13, 2020 B-51 Letter dated October 13, 2020 – PKMJF response to VAFFC Request on Confidentiality
October 07, 2020 B-50 Letter dated October 7, 2020 – PKMJF response to Parkland and VAFFC Confidentiality Declaration and Undertaking Requests
October 01, 2020 B-49 Letter dated October 1, 2020 – PKMJF Confirmation of Providing Confidential Information to VAFFC and Parkland
September 21, 2020 B-48-1 Letter dated September 21, 2020 – PKMJF Submitting Supplemental Responses regarding Order P-6-20
September 21, 2020 B-48 CONFIDENTIAL_Letter dated September 21, 2020 – PKMJF Submitting confidential Supplemental Responses regarding Order P-6-20
September 14, 2020 B-47 Letter dated September 14, 2020 – PKMJF Submitting further extension request to file supplemental Responses to VAFFC and Parkland
September 10, 2020 B-46 Letter dated September 10, 2020 – PKMJF Submitting extension to file supplemental Responses to VAFFC and Parkland
August 20, 2020 B-45 Letter dated August 20, 2020 – PKMJF Submitting extension request to file Information Request responses to VAFFC and Parkland
June 30, 2020 B-44 Letter dated June 30, 2020 – PKMJF Submitting response to VAFFC and Parkland to compel further and better responses from IRs
June 23, 2020 B-43 Letter dated June 23, 2020 – PKMJF Submitting response to VAFFC and Parkland requesting access to confidential Information Requests
June 19, 2020 B-42-1 CONFIDENTIAL_Letter dated June 18, 2020 – PKMJF Submitting Confidential attachment for response to VAFFC Information Request No. 2
June 19, 2020 B-42 Letter dated June 18, 2020 – PKMJF Submitting response to VAFFC Information Request No. 2 with Redacted Confidential attachment
June 19, 2020 B-41-1 CONFIDENTIAL_Letter dated June 18, 2020 – PKMJF Submitting Confidential attachment for response to Parkland Information Request No. 2
June 19, 2020 B-41 Letter dated June 18, 2020 – PKMJF Submitting response to Parkland Information Request No. 2 with Redacted Confidential attachment
June 18, 2020 B-40-1 Letter dated June 18, 2020 – PKMJF Submitting Redacted Confidential response to VAFFC Information Request No. 2
June 18, 2020 B-40 CONFIDENTIAL Letter dated June 18, 2020 – PKMJF Submitting confidential response to VAFFC Information Request No. 2
June 17, 2020 B-39 Letter dated June 16, 2020 – PKMJF Submitting response to Parkland Information Request No. 2
June 16, 2020 B-38 Letter dated June 16, 2020 – PKMJF Submitting response to VAFFC Information Request No. 2
June 16, 2020 B-37 Letter dated June 16, 2020 – PKMJF Submitting response to BCUC Information Request No. 3
June 11, 2020 B-36 Letter dated June 11, 2020 – PKMJF Submitting updating of invoice records
April 27, 2020 B-35-1 CONFIDENTIAL Letter dated April 27, 2020 - PKMJF Submitting the Independent Expert Retainer Agreement
April 27, 2020 B-35 Letter dated April 27, 2020 - PKMJF Submitting the Independent Expert Retainer Agreement
April 27, 2020 B-34 Letter dated April 27, 2020 - PKMJF Submitting Supplementary Response
March 12, 2020 B-33 Letter dated March 12, 2020 –PKMJF Submission to BCUC on resumption of proceeding
January 17, 2020 B-32 Letter dated January 17, 2020 –PKMJF Submitting confirmation of Confidential Information Requests 22.1 and 23.1 to VAFFC and Parkland
January 07, 2020 B-31 Letter dated January 7, 2020 – PKMJF submitting request to remove Kinder Morgan individuals from the proceeding Distribution List
January 06, 2020 B-30 Letter dated January 6, 2020 – PKMJF submitting Notice of Pembina Pipeline Corporation Purchase of KMJF and name change to PKM Canada (Jet Fuel) Inc., also response regarding VAFFC’s request for further and better information responses, and the temporary suspension of the timetable
January 02, 2020 B-29 Letter dated January 2, 2020 – KMJF Submitting response to the BCUC’s request for submission on VAFFC’s application to temporarily suspend the regulatory timetable
December 23, 2019 B-28 Letter dated December 23, 2019 – KMJF Submitting response to VAFFC submissions
December 18, 2019 B-27-2 CONFIDENTIAL_Letter dated December 18, 2019 – KMJF Submitting Confidential documents provided in information request responses 22.1 and 23.1
December 18, 2019 B-27-1 Letter dated December 18, 2019 – KMJF Submitting redacted Confidential documents provided in information request responses 22.1 and 23.1
December 18, 2019 B-27 Letter dated December 18, 2019 – KMJF Submitting request for Confidentiality regarding certain documents provided in information request responses 22.1 and 23.1
December 12, 2019 B-26 Letter dated December 12, 2019 – KMJF Submitting response to intervener submissions on proposed interim rate extension
December 06, 2019 B-25 Letter dated December 6, 2019 – KMJF Submitting Supplemental Responses to BCUC Information Request Nos 22.1 and 23.1
December 02, 2019 B-24 Letter dated December 2, 2019 – KMJF email response regarding access to confidential information
December 02, 2019 B-23 Letter dated December 2, 2019 – KMJF application to permit the interim tariff approved by BCUC Order P-1-18 and P-6-19
November 26, 2019 B-22 Letter dated November 26, 2019 – KMJF submitting further information to Information Requests
November 25, 2019 B-21 Letter dated November 25, 2019 – KMJF submitting an extension request to file Information Request supplementary responses
November 12, 2019 B-20-1 CONFIDENTIAL – Appendix A to KMJF letter dated November 12, 2019 (Exhibit B-20)
November 12, 2019 B-20 Letter dated November 12, 2019 – KMJF Submitting Response to BCUC letter dated November 8, 2019 (Exhibit A-17)
October 30, 2019 B-19 Letter dated October 30, 2019 – KMJF submitting request to keep Confidential 2018 KMJF Cost of Debt Information
October 01, 2019 B-18 Letter dated October 1, 2019 – KMJF submitting Supplemental Responses to VAFFC Submission regarding Adequacy of KMJF Information Request Responses
September 25, 2019 B-17 Letter dated September 25, 2019 – KMJF submitting response to VAFFC regarding adequacy of KMJF Information Request responses
September 13, 2019 B-16 Letter dated September 13, 2019 –KMJF submitting response regarding VAFFC response regarding Further and Better Information Request Responses
September 04, 2019 B-15 Letter dated September 4, 2019 – KMJF submitting response to VAFFC request for further process steps and schedule
August 23, 2019 B-14 Letter dated August 23, 2019 - KMJF submitting Amended Revenue Requirement and Final Tolls Application for 2019-2021
August 22, 2019 B-13 Letter dated August 22, 2019 - KMJF submitting responses to VAFFC Information Request No. 1
August 22, 2019 B-12 Letter dated August 22, 2019 - KMJF submitting responses to Parkland Information Request No. 1
August 22, 2019 B-11 Letter dated August 22, 2019 - KMJF submitting responses to BCUC Information Request No. 2
August 16, 2019 B-10 Letter dated August 16, 2019 - KMJF submitting the Final Site-specific Abandonment Cost Estimate Report
July 31, 2019 B-9 Letter dated July 31, 2019 – KMJF submitting request for extension to file Information Request responses
June 07, 2019 B-8 Letter dated June 7, 2019 – KMJF filing 2019 Revenue Requirement and Final Tolls Application
May 30, 2019 B-7 Letter dated May 30, 2019 – KMJF submitting response to intervener submission on proposed changes to interim rate
April 29, 2019 B-6 Letter dated April 29, 2019 – KMJF submitting response to stakeholder comments
March 07, 2019 B-5 Letter dated March 7, 2019 – KMJF submitting request to amend the regulatory timetable
February 01, 2019 B-4 Letter dated February 1, 2019 – KMJF confirms support for VAFFC’s extension request
January 11, 2019 B-3 Letter dated January 11, 2019 – KMJF submitting responses to BCUC Information Request No. 1 and response regarding E-2
December 27, 2018 B-2 Submission dated December 27, 2018 – KMJF extension request for responses to BCUC IR No. 1
November 29, 2018 B-1 KINDER MORGAN CANADA (JET FUEL) INC. (KMJF) – Letter dated November 29, 2018 submitting 2019 Tariff Filing Application

C Exhibits - Intervener Documents



Date Title Document Description
April 18, 2019 C1-1 PARKLAND REFINING (BC) LTD. (PARKLAND) – Letter dated April 18, 2019 – Request for Intervener Status by Keith Bergner
July 11, 2019 C1-2 Letter dated July 11, 2019 – Parkland Information Request No. 1 to KMJF
December 09, 2019 C1-3 Letter dated December 9 2019 – Parkland Submission on proposed interim rate extension
December 10, 2019 C1-4 Letter dated December 10, 2019 – Parkland request for Access to Confidential Supplemental Cost of Debt Data
December 20, 2019 C1-5 Letter dated December 20, 2019 – Parkland submitting Confidentiality Declarations and Undertaking Form from Will Shaw
December 24, 2019 C1-6 Letter dated December 24, 2019 – Parkland request for Access to Confidential Documents Tables A
January 03, 2020 C1-7 Letter dated January 3, 2020 - Parkland submitting response to the BCUC’s request for submission on VAFFC’s application to temporarily suspend the regulatory timetable
May 19, 2020 C1-8 Letter dated May 19, 2020 – Parkland submitting Information Request No. 2 to Pembina Kinder Morgan (Jet Fuel) Inc.
June 19, 2020 C1-9 Letter dated June 19, 2020 – Parkland Submitting comment on PKMJF IR Responses
June 19, 2020 C1-10 Letter dated June 19, 2020 - Parkland request access to PKMJF confidential IR Responses
July 06, 2020 C1-11 Letter dated July 6, 2020 – Parkland comment to VAFFC letter regarding further and better responses from IRs
August 17, 2020 C1-12 Letter dated August 17, 2020 - Parkland submitting responses to P-4-20 and VAFFC submission
August 25, 2020 C1-13 Letter dated August 25, 2020 – Parkland submitting response to PKMJF letter and the Amended Regulatory Timetable
September 30, 2020 C1-14 Letter dated September 30, 2020 – Parkland submitting Confidential Undertakings of Craig Burkart of MNP
October 07, 2020 C1-15 Letter dated October 7, 2020 – Parkland submitting extension request
October 08, 2020 C1-16 Letter dated October 8, 2020 – Parkland submitting response to PKMJF request
October 16, 2020 C1-17 Letter dated October 16, 2020 – Parkland submitting reply to PKMJF response on extension request
December 09, 2020 C1-18 Letter dated December 9, 2020 – Parkland submitting response to PKMJF 2021 Interim Tariff Filing
December 16, 2020 C1-19 Letter dated December 16, 2020 – Parkland submitting evidence and confidentiality request
December 16, 2020 C1-19-1 CONFIDENTIAL - Letter dated December 16, 2020 – Parkland submitting J. Dyack Confidential Written Evidence
January 08, 2021 C1-19-2 Letter dated January 8, 2021 – Parkland submitting Redacted J. Dyack Confidential Written Evidence
January 12, 2021 C1-20 Letter dated January 12, 2021 – Parkland submitting Confidentiality Declaration and Undertaking for Nicolas Lindal
January 25, 2021 C1-21 Letter dated January 25, 2020 – Parkland submitting Information Request No. 1 to VAFFC
February 22, 2021 C1-22 REDACTED - Letter dated February 22, 2020 – Parkland submitting responses to BCUC Information Request No. 1 and Confidentiality Request - PUBLIC
February 22, 2021 C1-22-1 CONFIDENTIAL - Letter dated February 22, 2021 – Parkland submitting confidential response to BCUC Information Request No. 1
February 22, 2021 C1-23 CONFIDENTIAL - Letter dated February 22, 2020 – Parkland submitting responses to BCUC Confidential Information Request No. 1
February 22, 2021 C1-24 REDACTED - Letter dated February 22, 2021 – Parkland submitting response to PKMJF Confidential Information Request No. 1
February 22, 2021 C1-24-1 CONFIDENTIAL - Letter dated February 22, 2021 –Parkland submitting confidential responses to PKMJF Confidential Information Request No. 1
February 22, 2021 C1-25 Letter dated February 22, 2021 –Parkland submitting response to VAFFC Information Request No. 1
March 26, 2021 C1-26 Letter dated March 26, 2021 –Parkland submitting request for extension to file IRs on Rebuttal Evidence
March 31, 2021 C1-27 Letter dated March 31, 2021 –Parkland submitting Confidentiality Declarations and Undertakings for Paul Gray and Stewart Bailey
April 09, 2021 C1-28 Letter dated April 9, 2021 – Parkland submitting request for suspension of the proceeding for negotiations
April 13, 2021 C1-29 Letter dated April 13, 2021 – Parkland submitting reply submission regarding request for suspension of the proceeding
April 16, 2021 C1-30 Letter dated April 16, 2021 – Parkland Submitting Information Request No. 3 to PKMJF
May 14, 2021 C1-31 CONFIDENTIAL - Letter dated May 14, 2021 - Parkland submitting response to PKMJF submission regarding Pipeline Shut Down
May 14, 2021 C1-31-1 Letter dated May 14, 2021 - Parkland submitting response to PKMJF submission regarding Pipeline Shut Down – Redacted Version
May 19, 2021 C1-32 Letter dated May 19, 2021 – Parkland submitting response to BCUC request for submissions
August 09, 2021 C1-33 Letter dated August 9, 2021 – Parkland submitting response to VAFFC’s letter dated August 3, 2021
August 25, 2021 C1-34 Letter dated August 25, 2021 – Parkland submitting response to BCUC request for submissions regarding further process
October 04, 2021 C1-35 Letter dated October 4, 2021 – Parkland submitting redacted response to BCUC request for submissions
October 04, 2021 C1-35-1 CONFIDENTIAL - Letter dated October 4, 2021 – Parkland submitting confidential response to BCUC request for submissions
December 02, 2021 C1-36 Letter dated December 2, 2021 –Parkland submitting Confidentiality Declarations and Undertakings
February 14, 2022 C1-37 Letter dated February 14, 2022 - Parkland submitting Letter of Support to PKMJF’s Letter Agreement
April 24, 2019 C2-1 VANCOUVER AIRPORT FUEL FACILITIES CORPORATION (VAFFC) – Letter dated April 24, 2019 – Request for Intervener Status by Matthew Keen
May 16, 2019 C2-2 Letter dated May 16, 2019 – VAFFC Submission on Interim Rates
July 11, 2019 C2-3 Letter dated July 11, 2019 – VAFFC Information Request No. 1 to KMJF
September 03, 2019 C2-4 Letter dated September 3, 2019 – VAFFC submitting request for further Process Steps and Schedule
September 11, 2019 C2-5 Letter dated September 10, 2019 –VAFFC submitting further response regarding Further and Better Information Request Responses
September 13, 2019 C2-6 Letter dated September 13, 2019 – VAFFC submitting response to KMJF’s extension request
October 07, 2019 C2-7 Letter dated October 7, 2019 –VAFFC submitting reply to KMJF’s response regarding Further and Better Information Request Responses
October 31, 2019 C2-8 Letter dated October 31, 2019 – VAFFC response on KMJF Request for Confidentiality Order
November 25, 2019 C2-9 Letter dated November 25, 2019 – VAFFC submitting a request to Access Confidential Supplemental Cost of Debt Data
November 25, 2019 C2-10 Letter dated November 25, 2019 – VAFFC submitting a request to Amend the Regulatory Timetable
December 09, 2019 C2-11 Letter dated December 9, 2019 – VAFFC Submission on proposed interim rate extension
December 12, 2019 C2-12 Letter dated December 12, 2019 – VAFFC request for Access to Confidential Supplemental Cost of Debt Data
December 18, 2019 C2-13 Letter dated December 18, 2019 – VAFFC Submitting Confidential Undertaking for Melissa Davis
December 19, 2019 C2-14 Letter dated December 19, 2019 – VAFFC Submitting request to suspend the regulatory timetable
January 08, 2020 C2-15 Letter dated January 8, 2020 –VAFFC submitting response on PKMJF and Parkland request regarding further and better information responses, and the temporary suspension of the timetable
January 14, 2020 C2-16 Letter dated January 14, 2020 – VAFFC Submitting request for access to PKMJF Confidential responses to Information Request 22.1 and 23.1
March 20, 2020 C2-17 Letter dated March 20, 2020 – VAFFC Submitting response on resumption of process and PKMJF submissions
April 29, 2020 C2-18 Letter dated April 29, 2020 – VAFFC Submitting request for access to unredacted Retainer Agreement
May 12, 2020 C2-19 Letter dated May 12, 2020 – VAFFC Submitting confidential undertaking for Patrick Bowman
May 19, 2020 C2-21 Letter dated May 19, 2020 – VAFFC Submitting Redacted Confidential Information Request No. 2 to PKMJF
May 20, 2020 C2-20 Letter dated May 19, 2020 – VAFFC Submitting Information Request No. 2 to PKMJF
May 22, 2020 C2-21-1 CONFIDENTIAL - Letter dated May 19, 2020 – VAFFC Submitting Confidential Information Request No. 2 to PKMJF
May 29, 2020 C2-22 Letter dated May 29, 2020 – VAFFC Submitting request for revision of the regulatory timetable
June 18, 2020 C2-23 Letter dated June 18, 2020 – VAFFC Submitting comment on PKMJF IR Responses
June 18, 2020 C2-24 Letter dated June 18, 2020 - VAFFC request access to PKMJF confidential IR Responses
July 03, 2020 C2-25 Letter dated July 3, 2020 – VAFFC response to PKMJF letter regarding further and better responses from IRs
August 14, 2020 C2-26 Letter dated August 14, 2020 - VAFFC submitting request to suspend the regulatory timetable
August 25, 2020 C2-27 Letter dated August 25, 2020 – VAFFC submitting response to PKMJF letter and the Amended Regulatory Timetable
September 03, 2020 C2-28 Letter dated September 3, 2020 – VAFFC submitting Confidential Undertaking for Patricia Lee and Kaitlin Long
September 30, 2020 C2-29 Letter dated September 30, 2020 – VAFFC submitting Confidential Undertakings of Francesco Femia, Robert Iasenza, Paul Whitty and Lane Tamagi
October 02, 2020 C2-30 Letter dated September 30, 2020 – VAFFC submitting Confidential Undertakings of Cam Bertsch
October 06, 2020 C2-31 Letter dated October 6, 2020 – VAFFC submitting an extension request to file Intervener Evidence and Request for unredacted copies of documents
October 06, 2020 C2-31-1 CONFIDENTIAL - Letter dated October 6, 2020 – VAFFC submitting an extension request to file Intervener Evidence and Request for unredacted copies of documents
October 08, 2020 C2-32 Letter dated October 8, 2020 – VAFFC submitting response to PKMJF request
October 16, 2020 C2-33 Letter dated October 16, 2020 – VAFFC submitting reply to PKMJF October 13, 2020 letter
October 29, 2020 C2-34 Letter dated October 29, 2020 – VAFFC submitting a request for unredacted copies of PKMJF documents
December 09, 2020 C2-35 Letter dated December 9, 2020 – VAFFC submitting response to PKMJF 2021 Interim Tariff Filing
December 16, 2020 C2-36 Letter dated December 16, 2020 – VAFFC submitting evidence and confidentiality request
December 16, 2020 C2-36-1 CONFIDENTIAL - Letter dated December 16, 2020 – VAFFC submitting Confidential Written Evidence
January 15, 2021 C2-36-2 Letter dated January 15, 2021 – VAFFC submitting redacted evidence and confidentiality request
January 25, 2021 C2-37 Letter dated January 25, 2020 – VAFFC submitting Information Request No. 1 to Parkland
February 02, 2021 C2-38 Letter dated February 2, 2021 – VAFFC submitting extension request to file Intervener Information Request Response
February 17, 2021 C2-39 Letter dated February 17, 2021 – VAFFC submitting Confidentiality Declaration and Undertaking for Rosalind Endo
February 23, 2021 C2-40 CONFIDENTIAL - Letter dated February 23, 2021 – VAFFC submitting confidential responses to BCUC Information Request No. 1
February 23, 2021 C2-41 CONFIDENTIAL - Letter dated February 23, 2021 – VAFFC submitting confidential responses to BCUC Confidential Information Request No. 1
February 23, 2021 C2-42 Letter dated February 23, 2021 – VAFFC submitting responses to Parkland Information Request No. 1
February 23, 2021 C2-43 CONFIDENTIAL - Letter dated February 23, 2021 – VAFFC submitting confidential responses to PKMJF Information Request No. 1
March 10, 2021 C2-40-1 REDACTED - Letter dated March 10, 2021 – VAFFC submitting redacted version of confidential responses to BCUC Information Request No. 1
March 10, 2021 C2-41-1 REDACTED - Letter dated March 10, 2021 – VAFFC submitting redacted version of confidential responses to BCUC Confidential Information Request No. 1
March 10, 2021 C2-43-1 REDACTED - Letter dated March 10, 2021 – VAFFC submitting redacted version of confidential responses to PKMJF Information Request No. 1
March 12, 2021 C2-44-1 REDACTED - Letter dated March 12, 2021 – VAFFC Submitting InterGroup Working Paper
March 15, 2021 C2-44 CONFIDENTIAL - Letter dated March 12, 2021 – VAFFC Submitting InterGroup Working Papers
March 26, 2021 C2-45 Letter dated March 26, 2021 – VAFFC supporting Parkland’s request for an extension
April 09, 2021 C2-46 Letter dated April 9, 2021 – VAFFC submitting request for suspension of the proceeding
April 12, 2021 C2-47 Letter dated April 12, 2021 – VAFFC submitting response regarding PKMJF response to request to suspend proceeding
April 16, 2021 C2-48 Letter dated April 16, 2021 – VAFFC Submitting Information Request No. 3 to PKMJF
May 14, 2021 C2-49 Letter dated May 14, 2021 - VAFFC submitting response to PKMJF submission regarding Pipeline Shut Down and Status regarding settlement Negotiations
June 18, 2021 C2-50 Letter dated June 18, 2021 - VAFFC submitting request for a procedural conference
August 03, 2021 C2-51 Letter dated August 3, 2021 - VAFFC submission regarding adjournment of procedural conference
August 25, 2021 C2-52 Letter dated August 25, 2021 – VAFFC submitting response to BCUC request for submissions regarding further process
October 04, 2021 C2-53 Letter dated October 4, 2021 – VAFFC submitting response to BCUC request for submissions
October 21, 2021 C2-54 Letter dated October 21, 2021 – VAFFC submitting Confidentiality Declaration and Undertaking

D Exhibits — Interested Party Documents

Date Title Document Description
May 14, 2021 D-1 BC OIL AND GAS COMMISSION. (BCOGC) – Submission dated May 14, 2021 – Request for Interested Party status by Lauren Krakau
May 18, 2021 D-1-1 Letter dated May 18, 2021 – BCOGC submission regarding conference calls

E Exhibits - Letters of Comment

Date Title Document Description
December 06, 2018 E-1 AIR CANADA AND VANCOUVER AIRPORT FUEL FACILITIES CORPORATION (YVR CONSORTIUM) – Letter dated December 6, 2018 – Letter of Comment
January 10, 2019 E-2 PARKLAND FUEL CORPORATION (PARKLAND) – Letter dated January 10, 2019 – Letter of Comment
January 31, 2019 E-2-1 Letter dated January 31, 2019 – Parkland Letter of Comment
January 31, 2019 E-3 VANCOUVER AIRPORT FUEL FACILITIES CORPORATION (VAFFC) – Letter dated January 31, 2019 – Letter of Comment
April 05, 2019 E-3-1 Letter dated April 5, 2019 – VAFFC submitting comments on further process
April 05, 2019 E-2-2 Letter dated April 5, 2019 – Parkland submitting comments on further process
April 26, 2021 E-4 SHELL CANADA PRODUCTS (SHELL) – Letter dated April 26, 2021 – Letter of Comment
May 18, 2021 E-1-1 Letter dated May 18, 2021 – YVR submitting comments on further process

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more