Other

Ravens Landing Industrial Park Ltd. Application for an Exemption from Part 3 of the Utilities Commission Act

Completed: 2020

Hearing and Other Documents

Title Document Description
Exhibit List Updated: January 29, 2020 @ 3:27 pm
G-108-20 Final Order May 6, 2020

Arguments/Submissions

Title Document Description
CEC Final Argument Final Argument October 15, 2019
Ravens Landing Reply Argument Reply Argument October 29, 2019

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
June 06, 2019 A-1 Letter dated June 6, 2019 - Appointing the Panel for the review of Ravens Landing Industrial Park Ltd’s Application for an Exemption from Part 3 of the Utilities Commission Act
June 06, 2019 A-2 Letter dated June 6, 2019 – Order G-124-19, establishing the regulatory timetable
June 19, 2019 A-3 Letter dated June 19, 2019 – Order G-133-19 amending the regulatory timetable
July 04, 2019 A-4 Letter dated July 4, 2019 – BCUC Information Request No. 1 to RLIP
August 29, 2019 A-5 Letter dated August 29, 2019 – Order G-206-19 amending the regulatory timetable
November 21, 2019 A-6 Letter dated November 21, 2019 – BCUC Exemption Approval letter to the Minister of Energy, Mines and Petroleum Resources
January 15, 2020 A-7 Letter dated January 15, 2020 – BCUC request for comments on draft order
January 29, 2020 A-8 Letter dated January 29, 2020 – BCUC Exemption Approval letter to the Minister of Energy, Mines and Petroleum Resources

B Exhibits - Applicant Documents

Date Title Document Description
April 15, 2019 B-1 RAVENS LANDING INDUSTRIAL PARK LTD. (RAVENS LANDING) Letter dated April 15, 2019 – Application for an Exemption from Part 3 of the Utilities Commission Act
July 30, 2019 B-2 Letter dated July 30, 2019 – Ravens Landing Responses to BCUC Information Request No. 1
July 30, 2019 B-2-1 CONFIDENTIAL - Letter dated July 30, 2019 – Ravens Landing Confidential Responses to BCUC Information Request No. 1 Questions 2.2 and 3.3
July 30, 2019 B-2-2 CONFIDENTIAL - Letter dated July 30, 2019 – Ravens Landing Confidential Responses to BCUC Information Request No. 1 Questions 2.3
July 30, 2019 B-3 Letter dated July 30, 2019 – Ravens Landing Responses to CEC Information Request No. 1
July 30, 2019 B-4 Letter dated July 30, 2019 – Ravens Landing Responses to Eppic Information Request No. 1

C Exhibits - Intervener Documents

D Exhibits — Interested Party Documents

Date Title Document Description
June 11, 2019 D-1 FORTISBC INC. – Submission dated June 11, 2019 request for Interested Party Status

E Exhibits - Letters of Comment

Date Title Document Description
July 08, 2019 E-1 ANDERSON, D. – Letter of Comment dated July 8, 2019

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more