Barriere Ridge Power

Exemption from Public Utility under the UCA, Part 3 and Section 71

Completed: 2022

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: January 11, 2022 @ 11:50 am
G-311-22 Final Order November 2, 2022

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
April 20, 2021 A-1 Letter dated April 20, 2021 – Appointing the Panel for the review of the Barriere Ridge Application for Partial Relief/Exemption from Public Utility under the UCA, Part 3 and Section 71
April 29, 2021 A-2 Letter dated April 29, 2021 – BCUC Order G-130-21 establishing a regulatory timetable
May 20, 2021 A-3 Letter dated May 20, 2021 – BCUC Information Request No. 1 to BR Power
June 16, 2021 A-4 Letter dated June 16, 2021 – BCUC Order G-186-21 amending the regulatory timetable
August 18, 2021 A-5 Letter dated August 18, 2021 – BCUC Order G-246-21 establishing a further regulatory timetable
August 18, 2021 A-6 Letter dated August 18, 2021 – BCUC invitation to the Province of BC to participate in the proceeding
October 26, 2021 A-7 Letter dated October 26, 2021 – BCUC Order G-304-21 amending the regulatory timetable
October 29, 2021 A-8 Letter dated October 29, 2021 – BCUC Order G-309-21 amending the regulatory timetable
January 11, 2022 A-9 Letter dated January 11, 2022 – BCUC letter to Minister of Energy, Mines and Low Carbon Innovation containing Panel Report seeking advance approval for an exemption order for Barriere Ridge from parts of UCA

B Exhibits - Applicant Documents

Date Title Document Description
March 16, 2021 B-1 BARRIERE RIDGE POWER LNC./BARRIERE RIDGE RESORT LTD. (BARRIERE RIDGE) - Application for Partial Relief/Exemption from Public Utility under the Utilities Commission Act (UCA),Part 3 and Section 71 dated March 16, 2021
June 14, 2021 B-2 Letter dated June 14, 2021 – Barriere Ridge late submission of partial responses to BCUC Information Request No. 1 and extension request
July 14, 2021 B-3 Letter dated July 14, 2021 – Barriere Ridge responses to BCUC Information Request No. 1
August 12, 2021 B-4 CONFIDENTIAL - Letter dated August 12, 2021 – Barriere Ridge submitting Confidential BC Hydro billing invoices
August 12, 2021 B-4-1 REDACTED - Letter dated August 12, 2021 – Barriere Ridge submitting redacted BC Hydro billing invoices
October 12, 2021 B-5 Letter dated October 12, 2021 - Barriere Ridge submitting evidence of providing notice as per G-246-21
October 27, 2021 B-6 Letter dated October 27, 2021 – Barriere Ridge submitting extension request
November 09, 2021 B-7 Letter dated November 9, 2021 – Barriere Ridge submitting confirmation of public notice in compliance with G-304-21 and G-309-21
December 02, 2021 B-8 Letter dated December 2, 2021 – Barriere Ridge submitting confirmation of public notice
December 09, 2021 B-9 Letter dated December 9, 2021 – Barriere Ridge submitting confirmation of Notice to Adams Lake Indian Band

Our Review Process