BC Hydro

Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022

Completed: 2022

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: December 17, 2021 @ 2:44 pm
G-26-22 Final Order with Reasons for Decision February 8, 2022

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
November 05, 2021 A-5 CONFIDENTIAL - Letter dated November 5, 2021 – BCUC Confidential Information Request No. 1 to BC Hydro
November 05, 2021 A-4 Letter dated November 5, 2021 – BCUC Information Request No. 1 to BC Hydro
November 09, 2021 A-6 Letter dated November 9, 2021 – BCUC Order G-327-21 amending the regulatory timetable
October 01, 2021 A-2 Letter dated October 1, 2021 – BCUC Order G-287-21 establishing a regulatory timetable
October 15, 2021 A-3 Letter dated October 15, 2021 – BCUC Order G-299-21 establishing a further regulatory timetable
September 10, 2021 A-1 Letter dated September 10, 2021 – Appointing the Panel for the review of British Columbia Hydro and Power Authority Application for Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022

B Exhibits - Applicant Documents

Date Title Document Description
August 31, 2021 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Letter dated August 31, 2021 submitting Application for Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022
August 31, 2021 B-1-1 CONFIDENTIAL - BC Hydro submitting Application for Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022 dated August 31, 2021
October 06, 2021 B-2 CONFIDENTIAL – Letter dated October 6, 2021 - BC Hydro submitting documents to be referenced in the in-camera session
November 08, 2021 B-3 Letter dated November 8, 2021 - BC Hydro submitting request to amend regulatory timetable
November 26, 2021 B-4 Letter dated November 26, 2021 - BC Hydro submitting responses to BCUC Information Request No. 1
November 26, 2021 B-4-1 CONFIDENTIAL - Letter dated November 26, 2021 - BC Hydro submitting confidential responses to BCUC Information Request No. 1
November 26, 2021 B-5 CONFIDENTIAL - Letter dated November 26, 2021 - BC Hydro submitting responses to BCUC Confidential Information Request No. 1
December 17, 2021 B-6 Letter dated December 17, 2021 - BC Hydro submitting response to Letters of Comment

Transcripts

Date Title Document Description
October 07, 2021 Transcript Volume 1a Confidential In-camera Session October 7, 2021