BC Hydro

2021 Integrated Resource Plan

In Progress

Timetable

Subject Date
IRs on Intervener Evidence Thursday, February 9, 2023
Responses to IRs on Intervener Evidence Thursday, March 2, 2023
Filing of Rebuttal Evidence Thursday, March 9, 2023
Written submissions by BC Hydro and Interveners regarding scope of Oral Hearing Thursday, March 16, 2023
IRs on Rebuttal Evidence Thursday, March 30, 2023
Reply submissions by BC Hydro and Interveners regarding scope of Oral Hearing Thursday, March 30, 2023
Responses to IRs on Rebuttal Evidence Thursday, April 20, 2023
Placeholder Oral Hearing Dates - April 24 to May 5, 2023 Monday, April 24, 2023

Hearing and Other Documents

This section can include a list of all exhibits issued in the proceeding and the BCUC's final decision.

Title Document Description
EXHIBIT LIST Updated: January 20, 2023 @ 10:24 am

Exhibits

A Exhibits — BCUC Documents

A Exhibits are issued by the BCUC and can include panel appointment letters, procedural orders, and information requests. A2 exhibits are added to the proceeding by BCUC staff. These can include staff reports, consultant reports, or other relevant evidence filed outside of the proceeding.

Date Title Document Description
December 23, 2021 A-1 Letter dated December 23, 2021 – Appointing the Panel for the review of the BC Hydro 2021 Integrated Resource Plan
January 21, 2022 A-2 Letter dated January 21, 2022 – BCUC Order G-15-22 with Regulatory Timetable and Public Notice
March 11, 2022 A-3 Letter dated March 11, 2022 – BCUC Order G-71-22 amending the Regulatory Timetable
March 31, 2022 A-4 Letter dated March 31, 2022 – BCUC providing Guidance for Interveners
April 26, 2022 A-5 Letter dated April 26, 2022 – BCUC Information Request No. 1 to BC Hydro
April 26, 2022 A-6 CONFIDENTIAL - Letter dated April 26, 2022 - BCUC Confidential Information Request No. 1 to BC Hydro
May 03, 2022 A-7 Letter dated May 3, 2022 – BCUC Order G-118-22 Amending the Regulatory Timetable
May 13, 2022 A-8 Letter dated May 13, 2022 – BCUC Order G-129-22 Amending the Regulatory Timetable
June 03, 2022 A-9 Letter dated June 3, 2022 – BCUC Order G-151-22 Amending the Regulatory Timetable
July 14, 2022 A-10 Letter dated July 14, 2022 – BCUC providing Procedural Conference Information
August 12, 2022 A-11 Letter dated August 12, 2022 – BCUC Order G-227-22 with Regulatory Timetable and Reasons for Decision
August 19, 2022 A-12 Letter dated August 19, 2022 – BCUC providing further information regarding Unanswered Information Requests
September 01, 2022 A-13 Letter dated September 1, 2022 – BCUC request to BC Hydro regarding Unanswered Information Requests
September 09, 2022 A-14 Letter dated September 9, 2022 – BCUC Order G-250-22 with further Regulatory Timetable
September 13, 2022 A-15 Letter dated September 13, 2022 – BCUC Order G-252-22 with Reasons for Decision regarding data confidentiality
October 03, 2022 A-16 Letter dated October 3, 2022 – BCUC response to BC Hydro regarding confidential information requests
October 04, 2022 A-17 Letter dated October 4, 2022 – BCUC response to Capital Power’s request for access to Confidential BC Hydro Information Request responses
October 07, 2022 A-18 Letter dated October 7, 2022 – BCUC Order G-280-22 with Reasons regarding Information Request confidentiality
October 13, 2022 A-19 Letter dated October 13, 2022 – BCUC Information Request No. 2 to BC Hydro
November 04, 2022 A-20 Letter dated November 4, 2022 – BCUC Order G-316-22 amending the regulatory timetable
November 14, 2022 A-21 Letter dated November 14, 2022 – BCUC providing guidance for filing intervener evidence
November 23, 2022 A-22 Letter dated November 23, 2022 – BCUC Order G-333-22 with Reasons for Decision and the amended regulatory timetable
February 15, 2022 A2-1 Letter dated February 15, 2022 – BCUC staff submitting BC Hydro Fiscal 2023 to Fiscal 2025 Revenue Requirements Program Application Appendices U & V - F2022 to F2026 Electrification Plan & Low Carbon Electrification Program
April 22, 2022 A2-2 Letter dated April 22, 2022 – BCUC staff submitting BC Hydro Application to Amend Net Metering Service under Rate Schedule 1289, Compliance with BCUC Order G-168-20 - Net Metering Report No. 5
October 12, 2022 A2-3 Letter dated October 12, 2022 – BCUC staff submitting BC Hydro’s Annual Reporting of Reliability Indices
December 07, 2022 A2-4 Letter dated December 7, 2022 – BCUC staff submitting FEI and BCH Energy Scenarios – FEI Stage One Submission – Modeling Results and FEI Stage Two Submission

B Exhibits — Applicant Documents

B Exhibits are issued by the entity, person, or group that submitted the application to the BCUC (applicant). They can include the application, responses to information requests, and other evidence.

Date Title Document Description
December 21, 2021 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – 2021 Integrated Resource Plan dated December 21, 2021
December 21, 2021 B-1-1 CONFIDENTIAL - Letter dated December 21, 2021 - BC Hydro Confidential 2021 Integrated Resource Plan
July 21, 2022 B-1-2 Letter dated July 21, 2022 - BC Hydro submitting Application Errata No. 1
July 21, 2022 B-1-3 CONFIDENTIAL – Letter dated July 21, 2022 - BC Hydro submitting Application Confidential Errata No. 1
December 08, 2022 B-1-4 Letter dated December 8, 2022 - BC Hydro submitting Application Errata No. 2
February 11, 2022 B-2 Letter dated December 21, 2021 - BC Hydro submitting compliance with Order G-15-22 Directives
February 23, 2022 B-3 Letter dated February 23, 2022 – BC Hydro submitting an independent expert report by Dr. Ahmad Faruqui, Ph. D. entitled “Capacity Savings Estimates in BC Hydro’s 2021 IRP: An Independent Review.”
March 09, 2022 B-4 Letter dated March 9, 2022 – BC Hydro submitting request to revise the Regulatory Timetable
March 31, 2022 B-5 Letter dated March 31, 2022 – BC Hydro submitting evidence of an independent expert report by Mr. Paul J. Hibbard, Analysis Group Inc.
June 01, 2022 B-6 Letter dated June 1, 2022 – BC Hydro submitting extension request to file Information Request responses
June 13, 2022 B-7 Letter dated June 13, 2022 – BC Hydro submitting compliance with Order G-151-22 Directive 1
June 15, 2022 B-8 Letter dated June 15, 2022 – BC Hydro submitting Stage 1 Load Forecast Results
July 21, 2022 B-9 Letter dated July 21, 2022 – BC Hydro submitting responses to BCUC Information Request No. 1
July 21, 2022 B-9-1 CONFIDENTIAL – Letter dated July 21, 2022 – BC Hydro submitting Confidential responses to BCUC Information Request No. 1
December 08, 2022 B-9-1-1 CONFIDENTIAL –Letter dated December 8, 2022 – BC Hydro submitting revised Confidential response to BCUC Information Request No. 1.48.10 and 1.62.13 Attachment 1
August 12, 2022 B-9-2 Letter dated August 12, 2022 – BC Hydro submitting remaining responses to BCUC Information Request No. 1
December 08, 2022 B-9-3 PUBLIC - Letter dated December 8, 2022 – BC Hydro submitting revised public responses to BCUC Information Request No. 1.48.10 and 1.62.13
July 21, 2022 B-10 Letter dated July 21, 2022 – BC Hydro submitting responses to Intervener Information Request No. 1
July 21, 2022 B-10-1 CONFIDENTIAL – Letter dated July 21, 2022 – BC Hydro submitting Confidential responses to Intervener Information Request No. 1
September 29, 2022 B-10-1-1 CONFIDENTIAL – Letter dated September 29, 2022 – BC Hydro submitting supplemental confidential responses to Intervener Information Request No. 1
August 12, 2022 B-10-2 Letter dated August 12, 2022 – BC Hydro submitting remaining responses to Interveners IR No. 1
September 29, 2022 B-10-3 PUBLIC – Letter dated September 29, 2022 – BC Hydro submitting supplemental public responses to Intervener Information Request No. 1
December 08, 2022 B-10-4 PUBLIC – Letter dated December 8, 2022 – BC Hydro submitting revised supplemental public responses to AMPC Information Request No. 1.13.1 Attachment 1
July 21, 2022 B-11 CONFIDENTIAL – Letter dated July 21, 2022 – BC Hydro submitting Confidential responses to BCUC Confidential Information Request No. 1
July 21, 2022 B-12 CONFIDENTIAL – Letter dated July 21, 2022 – BC Hydro submitting Confidential responses to RCIA Confidential Information Request No. 1
July 21, 2022 B-13 Letter dated July 21, 2022 – BC Hydro submitting Public responses to RCIA Confidential Information Request No. 1
August 12, 2022 B-14 Letter dated August 12, 2022 – BC Hydro Stage 2 submission
August 17, 2022 B-15 Letter dated August 17, 2022 – BC Hydro submitting response to Intervener submissions on unanswered Information Requests
August 25, 2022 B-16 Letter dated August 25, 2022 – BC Hydro submitting reply to Intervener submissions on unanswered Information Requests
September 08, 2022 B-17 PUBLIC - Letter dated September 8, 2022 – BC Hydro submitting redacted submission on confidentiality of information provided by Hitachi and ICE Data LP
September 08, 2022 B-17-1 CONFIDENTIAL - Letter dated September 8, 2022 – BC Hydro submitting confidential submission on confidentiality of information provided by Hitachi and ICE Data LP
September 20, 2022 B-18 PUBLIC - Letter dated September 20, 2022 – BC Hydro submitting confirmation of submission provided to BCUC on confidentiality of information provided by Hitachi and ICE Data LP
September 20, 2022 B-18-1 CONFIDENTIAL - Letter dated September 20, 2022 – BC Hydro submitting confirmation of confidential submission provided to BCUC on confidentiality of information provided by Hitachi and ICE Data LP
September 29, 2022 B-19 Letter dated September 29, 2022 – BC Hydro submitting additional information for Stage 2 Energy Scenarios
October 06, 2022 B-20 Letter dated October 6, 2022 – BC Hydro submitting comments on confidential Information Requests
December 08, 2022 B-21 PUBLIC - Letter dated December 8, 2022 – BC Hydro submitting public responses to BCUC Information Request No. 2
December 08, 2022 B-21-1 CONFIDENTIAL - Letter dated December 8, 2022 – BC Hydro submitting confidential responses to BCUC Information Request No. 2
December 08, 2022 B-22 PUBLIC - Letter dated December 8, 2022 – BC Hydro submitting public responses to Interveners Information Request No. 2
December 08, 2022 B-22-1 CONFIDENTIAL - Letter dated December 8, 2022 – BC Hydro submitting confidential responses to Interveners Information Request No. 2
December 08, 2022 B-23 PUBLIC - Letter dated December 8, 2022 – BC Hydro submitting redacted confidential responses to Zone II RPG Confidential Information Request No. 2
December 08, 2022 B-23-1 CONFIDENTIAL - Letter dated December 8, 2022 – BC Hydro submitting responses to Zone II RPG Confidential Information Request No. 2

C Exhibits — Intervener Documents

C Exhibits are issued by registered interveners and can include information requests, submissions on process, and other evidence. To see the list of interveners in this proceeding, please click the "Intervener List" heading below.

Click here for Intervener List

BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) - Letter dated January 31, 2022 Request to Intervene by T. Hackney
FORTISBC ENERGY INC. AND FORTISBC INC. (COLLECTIVELY FORTISBC) – Letter dated January 6, 2022 submitting request to intervene by Diane Roy
BC SOLAR AND STORAGE INDUSTRIES ASSOCIATION (BCSSIA) – Letter dated February 17, 2022 – request to intervene by Steve Davis
NUU-CHAH-NULTH TRIBAL COUNCIL (NTC)– Letter dated March 2, 2022 request to intervene by Judith Sayers
CLEAN ENERGY BC (CEBC) – Letter dated March 14, 2022 request to intervene by Cameron Lusztig
ZONE II RATEPAYERS GROUP (ZONEII RPG) – Letter dated March 14, 2022 request to intervene by Jana McLean
RESIDENTIAL CONSUMER INTERVENER ASSOCIATION (RCIA) – Letter dated March 18, 2022 request to intervene by Matthew Matusiak
ASSOCIATION OF MAJOR POWER CUSTOMERS (AMPC) – Letter dated March 21, 2022 request to intervene by Carlo Dal Monte
BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION ET AL. (BCOAPO ET AL) – Letter dated March 22, 2022 request to intervene by Kristin Barham
CAPITAL POWER CORPORATION (CAPITAL POWER) – Letter dated March 22, 2022 request to intervene by Matthew Davis
COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) – Letter dated March 22, 2022 request to intervene by David Craig
BLUEARTH RENEWABLES (BLUEARTH)– Letter dated March 17, 2022 request to intervene by Roslyn McMann
PETERS FIRST NATION – Letter dated March 21, 2022 request to intervene by Drew Lawrenson
BC FIRST NATIONS ENERGY AND MINING COUNCIL (FNEMC) – Letter dated March 21, 2022 request to intervene by Andrew McLaren
KITSELAS GEOTHERMAL INC. (KGI) – Letter dated March 22, 2022 request to intervene by Alison Thompson
TRANSALTA CORPORATION (TRANSALTA) – Letter dated March 22, 2022 request to intervene by Akira Yamamoto
VANCOUVER ELECTRIC VEHICLE ASSOCIATION (VEVA) – Letter dated March 22, 2022 request to intervene by Robert Sparks
MOVEUP – Letter dated March 23, 2022 request to intervene by Jim Quail
CANADIAN MANUFACTURES AND EXPORTERS (CME) – Letter dated March 24, 2022 request to intervene by Paul Willis
CITY OF SURREY (SURREY)– Letter dated March 25, 2022 request to intervene by Benjie Lee
NET METERING RATEPAYERS GROUP AND BRITISH COLUMBIA COMMUNITY SOLAR COALITION (NMRG-BCCSC) – Letter dated March 25, 2022 request to intervene by Fred Weisberg
ZONE 1B RATEPAYERS GROUP (Zone1B-RPG) – Letter dated March 25, 2022 request to intervene by Fred Weisberg
CAYOOSE CREEK INDIAN BAND – Letter dated March 29, 2022 request to intervene by Drew Lawrenson
BC COMMUNITY SOLAR COALITION (BCCSC) – Letter dated May 9, 2022 submitting late request to intervene by Kjell Liem


Date Title Document Description
January 31, 2022 C1-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) - Letter dated January 31, 2022 Request to Intervene by T. Hackney
May 02, 2022 C1-2 Letter dated May 2, 2022 – BCSEA and VEVA submitting extension request to file Information Request No. 1
May 10, 2022 C1-3 Letter dated May 10, 2022 – BCSEA and VEVA submitting Information Request No. 1 to BC Hydro
August 16, 2022 C1-4 Letter dated August 16, 2022 – BCSEA submitting Confidentiality Declaration and Undertakings
October 13, 2022 C1-5 Letter dated October 13, 2022 – BCSEA and VEVA submitting Information Request No. 2 to BC Hydro
January 06, 2022 C2-1 FORTISBC ENERGY INC. AND FORTISBC INC. (COLLECTIVELY FORTISBC) – Letter dated January 6, 2022 submitting request to intervene by Diane Roy
May 03, 2022 C2-2 Letter dated May 3, 2022 – FortisBC submitting Information Request No. 1 to BC Hydro
October 13, 2022 C2-3 Letter dated October 13, 2022 – FortisBC submitting Information Request No. 2 to BC Hydro
February 17, 2022 C3-1 BC SOLAR AND STORAGE INDUSTRIES ASSOCIATION (BCSSIA) – Letter dated February 17, 2022 – request to intervene by Steve Davis
October 13, 2022 C3-2 Letter dated October 13, 2022 – BCSSIA submitting Information Request No. 2 to BC Hydro
March 02, 2022 C4-1 NUU-CHAH-NULTH TRIBAL COUNCIL (NTC)– Letter dated March 2, 2022 request to intervene by Judith Sayers
May 10, 2022 C4-2 Letter dated May 10, 2022 – NTC submitting Information Request No. 1 to BC Hydro
August 18, 2022 C4-3 Letter dated August 18, 2022 – NTC submission on BCH response on Intervener unanswered Information Requests
October 13, 2022 C4-4 Letter dated October 13, 2022 – NTC submitting Information Request No. 2 to BC Hydro
March 14, 2022 C5-1 CLEAN ENERGY BC (CEBC) – Letter dated March 14, 2022 request to intervene by Cameron Lusztig
May 02, 2022 C5-2 Letter dated May 2, 2022 – CEBC submitting Information Request No. 1 to BC Hydro
August 17, 2022 C5-3 Letter dated August 17, 2022 – CEBC submitting request more adequate BC Hydro responses on Intervener unanswered Information Requests
October 13, 2022 C5-4 Letter dated October 13, 2022 – CEBC submitting Information Request No. 2 to BC Hydro
December 21, 2022 C5-5 Letter dated December 21, 2022 – CEBC submitting Confidentiality Declaration and Undertaking
January 19, 2023 C5-6 Letter dated January 19, 2023 – CEBC submitting written evidence by Travis Lusney of Power Advisory LLC
March 14, 2022 C6-1 ZONE II RATEPAYERS GROUP (ZONEII RPG) – Letter dated March 14, 2022 request to intervene by Jana McLean
May 03, 2022 C6-2 Letter dated May 3, 2022 – ZoneII RPG submitting Information Request No. 1 to BC Hydro
August 18, 2022 C6-3 Letter dated August 18, 2022 – ZoneII RPG submitting nothing further on Intervener unanswered Information Requests
September 21, 2022 C6-4 Letter dated September 21, 2022 – ZoneII RPG submitting Confidentiality Declaration and Undertaking form
October 07, 2022 C6-5 Letter dated October 7, 2022 – ZoneII RPG submitting Confidentiality Declaration and Undertaking
October 13, 2022 C6-6 Letter dated October 13, 2022 – ZoneII RPG submitting Information Request No. 2 to BC Hydro
October 13, 2022 C6-7 CONFIDENTIAL - Letter dated October 13, 2022 – ZoneII RPG submitting Confidential Information Request No. 2 to BC Hydro
November 03, 2022 C6-8 Letter dated November 3, 2022 – ZoneII RPG submitting representative contact information update
March 18, 2022 C7-1 RESIDENTIAL CONSUMER INTERVENER ASSOCIATION (RCIA) – Letter dated March 18, 2022 request to intervene by Matthew Matusiak
March 22, 2022 C7-2 REVISED - Letter dated March 22, 2022 – RCIA submitting revised Confidentiality Declaration and Undertaking forms
May 09, 2022 C7-3 Letter dated May 9, 2022 – RCIA submitting Information Request No. 1 to BC Hydro
May 09, 2022 C7-4 CONFIDENTIAL - Letter dated May 9, 2022 – RCIA submitting Confidential Information Request No. 1 to BC Hydro
January 10, 2023 C7-5 Letter dated January 10, 2023 – RCIA submitting updated Confidentiality Declaration and Undertaking Forms
October 13, 2022 C7-6 Letter dated October 13, 2022 – RCIA submitting Information Request No. 2 to BC Hydro
November 03, 2022 C7-7 Letter dated November 3, 2022 – RCIA submitting intent to file Intervener Evidence
January 19, 2023 C7-8 Letter dated January 19, 2023 – RCIA submitting written evidence by Midgard Consulting Ltd.
March 21, 2022 C8-1 ASSOCIATION OF MAJOR POWER CUSTOMERS (AMPC) – Letter dated March 21, 2022 request to intervene by Carlo Dal Monte
May 02, 2022 C8-2 Letter dated May 2, 2022 – AMPC submitting extension request to file Information Request No. 1
May 10, 2022 C8-3 Letter dated May 10, 2022 – AMPC submitting Information Request No. 1 to BC Hydro
October 11, 2022 C8-4 Letter dated October 11, 2022 – AMPC submitting Confidentiality Declaration and Undertakings
October 13, 2022 C8-5 Letter dated October 13, 2022 – AMPC submitting Information Request No. 2 to BC Hydro
January 19, 2023 C8-6 Letter dated January 19, 2023 – AMPC submitting written evidence by Melissa Davies and Patrick Bowman
March 22, 2022 C9-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION ET AL. (BCOAPO ET AL) – Letter dated March 22, 2022 request to intervene by Kristin Barham
May 10, 2022 C9-2 Letter dated May 10, 2022 – BCOAPO submitting Information Request No. 1 to BC Hydro
October 13, 2022 C9-3 Letter dated October 13, 2022 – BCOAPO submitting Information Request No. 2 to BC Hydro
March 22, 2022 C10-1 CAPITAL POWER CORPORATION (CAPITAL POWER) – Letter dated March 22, 2022 request to intervene by Matthew Davis
May 03, 2022 C10-2 Letter dated May 3, 2022 – Capital Power submitting Information Request No. 1 to BC Hydro
August 18, 2022 C10-3 Letter dated August 18, 2022 – Capital Power submission on BCH response on Intervener unanswered Information Requests
October 04, 2022 C10-4 Letter dated October 3, 2022 – Capital Power submission on BCH response on Intervener unanswered Information Requests
October 13, 2022 C10-5 Letter dated October 13, 2022 – Capital Power submitting Information Request No. 2 to BC Hydro
November 10, 2022 C10-6 Letter dated November 10, 2022 – Capital Power reply submission to BCH Objection to Request for Access to Confidential Information in Exhibit B-10-1-1
November 24, 2022 C10-7 Letter dated November 24, 2022 – Capital Power submitting Confidentiality Declaration and Undertaking
January 19, 2023 C10-8 Letter dated January 19, 2023 – Capital Power submitting written evidence by Dragan Brankovich, M.Sc., P. Eng.
March 22, 2022 C11-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) – Letter dated March 22, 2022 request to intervene by David Craig
May 03, 2022 C11-2 Letter dated May 3, 2022 – CEC submitting Information Request No. 1 to BC Hydro
July 27, 2022 C11-3 Letter dated July 27, 2022 – CEC submitting Confidentiality Declaration and Undertaking
August 10, 2022 C11-4 Letter dated August 10, 2022 – CEC submitting Confidentiality Declaration and Undertaking
October 13, 2022 C11-5 Letter dated October 13, 2022 – CEC submitting Information Request No. 2 to BC Hydro
December 20, 2022 C11-6 Letter dated December 20, 2022 –CEC submitting summary of intervener evidence
January 19, 2023 C11-7 Letter dated January 19, 2023 – CEC submitting written evidence by David Ince
March 17, 2022 C12-1 BLUEARTH RENEWABLES (BLUEARTH)– Letter dated March 17, 2022 request to intervene by Roslyn McMann
March 21, 2022 C13-1 PETERS FIRST NATION – Letter dated March 21, 2022 request to intervene by Drew Lawrenson
August 18, 2022 C13-2 Letter dated August 18, 2022 – Peters First Nation submission on Intervener unanswered Information Requests
March 21, 2022 C14-1 BC FIRST NATIONS ENERGY AND MINING COUNCIL (FNEMC) – Letter dated March 21, 2022 request to intervene by Andrew McLaren
May 03, 2022 C14-2 Letter dated May 3, 2022 – FNEMC submitting Information Request No. 1 to BC Hydro
August 19, 2022 C14-3 Letter dated August 19, 2022 – FNEMC submission on BCH response on Intervener unanswered Information Requests
October 13, 2022 C14-4 Letter dated October 13, 2022 – FNEMC submitting Information Request No. 2 to BC Hydro
March 22, 2022 C15-1 KITSELAS GEOTHERMAL INC. (KGI) – Letter dated March 22, 2022 request to intervene by Alison Thompson
April 28, 2022 C15-2 Letter dated April 28, 2022 – KGI submitting Information Request No. 1 to BC Hydro
March 22, 2022 C16-1 TRANSALTA CORPORATION (TRANSALTA) – Letter dated March 22, 2022 request to intervene by Akira Yamamoto
March 22, 2022 C17-1 VANCOUVER ELECTRIC VEHICLE ASSOCIATION (VEVA) – Letter dated March 22, 2022 request to intervene by Robert Sparks
March 23, 2022 C18-1 MOVEUP – Letter dated March 23, 2022 request to intervene by Jim Quail
April 28, 2022 C18-2 Letter dated April 28, 2022 – MoveUP submitting Information Request No. 1 to BC Hydro
October 12, 2022 C18-3 Letter dated October 12, 2022 – MoveUP submitting Information Request No. 2 to BC Hydro
March 24, 2022 C19-1 CANADIAN MANUFACTURES AND EXPORTERS (CME) – Letter dated March 24, 2022 request to intervene by Paul Willis
March 22, 2022 C19-2 Letter dated March 22, 2022 – CME submitting Information Request No. 1 to BC Hydro
March 25, 2022 C20-1 CITY OF SURREY (SURREY)– Letter dated March 25, 2022 request to intervene by Benjie Lee
May 03, 2022 C20-2 Letter dated May 3, 2022 – Surrey submitting Information Request No. 1 to BC Hydro
March 25, 2022 C21-1 NET METERING RATEPAYERS GROUP AND BRITISH COLUMBIA COMMUNITY SOLAR COALITION (NMRG-BCCSC) – Letter dated March 25, 2022 request to intervene by Fred Weisberg
May 03, 2022 C21-2 Letter dated May 3, 2022 – NMRG-BCCSC submitting Information Request No. 1 to BC Hydro
March 25, 2022 C22-1 ZONE 1B RATEPAYERS GROUP (Zone1B-RPG) – Letter dated March 25, 2022 request to intervene by Fred Weisberg
March 29, 2022 C23-1 CAYOOSE CREEK INDIAN BAND – Letter dated March 29, 2022 request to intervene by Drew Lawrenson
August 18, 2022 C23-2 Letter dated August 18, 2022 – Cayoose Creek Indian Band submission on Intervener unanswered Information Requests
May 09, 2022 C24-1 BC COMMUNITY SOLAR COALITION (BCCSC) – Letter dated May 9, 2022 submitting late request to intervene by Kjell Liem
May 10, 2022 C24-2 Letter dated May 10, 2022 – BCCSC submitting late Information Request No. 1 to BC Hydro

D Exhibits — Interested Party Documents

D Exhibits include interested party registration forms. Registered interested parties receive email notifications when public information is posted during a BCUC proceeding.

Date Title Document Description
December 24, 2021 D-1 SMILLIE, S (SMILLIE) – Request for Interested Party status dated December 24, 2021
December 27, 2021 D-2 SYNEX RENEWABLE ENERGY CORP (SYNEX) – Request for Interested Party status by Daniel Russell dated December 27, 2021
January 04, 2022 D-3 CAPSTONE INFRASTRUCTURE CORPORATION (CAPSTONE INFRASTRUCTURE) – Request for Interested Party status by Patrick Leitch dated January 4, 2022
January 05, 2022 D-4 ZERO WASTE BC (ZERO WASTE) – Request for Interested Party status by Sue Maxwell dated January 5, 2022
January 17, 2022 D-5 EVOLUGEN BY BROOKFIELD RENEWABLE (EVOLUGEN) – Request for Interested Party status by Julien Wu dated January 17, 2022
January 27, 2022 D-6 KITO, M. (KITO) – Request for Interested Party status dated January 27, 2022
January 27, 2022 D-7 LAIL, K. (LAIL) – Request for Interested Party status dated January 27, 2022
January 28, 2022 D-8 FAIRLEY, P. (FAIRLEY) – Request for Interested Party status dated January 27, 2022
February 03, 2022 D-9 COCHRANE ENERGY MANAGEMENT CONSULTING (COCHRANE) – Request for Interested Party status by Penny Cochrane dated February 3, 2022
February 07, 2022 D-10 ZERO EMISSIONS BUILDING EXCHANGE (ZEBX) - Submission dated February 7, 2021 Request for Interested Party Status by Roberto Pecora
February 22, 2022 D-11 CORNWALL, C. (CORNWALL) – Request for Interested Party status dated February 22, 2022
February 23, 2022 D-12 CITY OF VANCOUVER (CoV) – Request for Interested Party status dated February 23, 2022 by Tina Barisky
March 18, 2022 D-13 TOWNSHIP OF LANGLEY (LANGLEY)– Request for Interested Party status dated March 18, 2022 by Greg Dennis
March 18, 2022 D-14 HESPV (HESPV) – Request for Interested Party status dated March 18, 2022 by Ed Knaggs
March 21, 2022 D-15 WEST MOBERLY FIRST NATION (WBFN) - Request for Interested Party status dated March 21, 2022 by Mackenzie Curran
March 21, 2022 D-16 EMPOWER ME (EMPOWER) - Request for Interested Party status dated March 21, 2022 by Yasmin Abraham
April 01, 2022 D-17 HELLER, M. (HELLER) – Request for Interested Party status dated April 1, 2022
April 26, 2022 D-18 CEBULKO, B. (CEBULKO) – Request for Interested Party status dated April 26, 2022
April 28, 2022 D-19 BC HYDRO RATEPAYERS (BCH RATEPAYERS) - Request for Interested Party status dated April 28, 2022 by Roger Bryenton
April 30, 2022 D-20 BOND, M. (BOND) – Request for Interested Party status dated April 30, 2022
October 05, 2022 D-21 UHL, A. (UHL) – Request for Interested Party status dated October 5, 2022
January 09, 2023 D-22 POLARIS STRATEGY AND INSIGHT (POLARIS STRATEGY) - Request for Interested Party status dated January 9, 2023 by D. Woynillowicz

E Exhibits — Letters of Comment

E Exhibits are from individuals, organizations, and groups that submit a Letter of Comment to share their views, opinions, and insights about an application or matter under review by the BCUC.

Date Title Document Description
December 24, 2021 E-1 MARSDEN, P AND J. (MARSDEN) – Letter of Comment dated December 24, 2021
February 14, 2022 E-1-1 MARSDEN – Additional Letter of Comment dated February 14, 2022
February 22, 2022 E-1-2 MARSDEN – Additional Letter of Comment dated February 22, 2022
March 15, 2022 E-1-3 MARSDEN, P. AND J. (MARSDEN) – Letter of Comment dated March 15, 2022
March 22, 2022 E-1-4 MARSDEN – Additional Letter of Comment dated March 22, 2022
August 08, 2022 E-1-5 MARSDEN – Additional Letter of Comment dated August 8, 2022
January 28, 2022 E-2 LITTLE, M. (LITTLE) – Letter of Comment dated January 28, 2022
March 05, 2022 E-3 BECKETT, D. (BECKETT) – Letter of Comment dated March 5, 2022
March 22, 2022 E-4 Removed and transferred to E-1-3
March 23, 2022 E-5 GREGORY, H. (GREGORY) – Letter of Comment dated March 23, 2022
May 13, 2022 E-6 CITY OF VANCOUVER (COV) – Letter of Comment dated May 13, 2022
May 13, 2022 E-7 GIBSON, C. (GIBSON) – Letter of Comment dated May 13, 2022
June 10, 2022 E-8 BRYENTON, R. (BRYENTON) – Letter of Comment dated June 10, 2022
July 28, 2022 E-8-1 BRYENTON – Additional Letter of Comment dated July 27, 2022
April 02, 2022 E-9 ZERO WASTE BC – Letter of comment dated April 2, 2022 – formerly Exhibit D-4-1

Transcripts

Transcripts are written scripts from procedural conferences, workshops, oral hearings, and other events. They are included on the proceeding record.

Date Title Document Description