Completed: 2022
Creative Energy has submitted to the BCUC the final design for renovation of the Expo Plant at BC Place Stadium, and the Beatty Plant at 720 Beatty St.
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: August 17, 2022 @ 12:06 pm |
Decision and G-360-22 | Decision and Final Order December 13, 2022 |
Date | Title | Document Description |
---|---|---|
July 04, 2022 | D-1 | British Columbia Hydro and Power Authority (BC Hydro) – Submission dated July 4, 2022 Request for Interested Party Status by Chris Sandve |