Completed: 2023
On April 5, 2022, Gitga’at First Nation (GFN) filed a complaint with the BCUC concerning an annual charge of approximately $85,000, paid to BC Hydro in relation to its electricity service. GFN submits that the charge violates section 63 of the Utilities Commission Act.
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: June 26, 2023 @ 10:23 am |
Decision and G-247-23 | Decision and Order G-247-23 September 18, 2023 |
Title | Document Description |
---|---|
GFN Final Argument | Final Argument April 24, 2023 |
BC Hydro Final Argument - Public | Final Argument-Public May 17, 2023 |
BC Hydro Final Argument - Confidential | Final Argument-Confidential May 17, 2023 |
GFN Reply Argument | Reply Argument May 25, 2023 |
Date | Title | Document Description |
---|---|---|
November 02, 2022 | E-1 | STEIN, G. (STEIN) – Letter of Comment dated November 2, 2022 |
November 06, 2022 | E-2 | YOUNG, J. (YOUNG) – Letter of Comment dated November 6, 2022 |