Completed: 2022
Title | Document Description |
---|---|
G-390-22A | Final Order December 28, 2022 |
EXHIBIT LIST | Updated: January 5, 2023 @ 9:58 am |
Date | Title | Document Description |
---|---|---|
December 21, 2022 | B-1 | PUBLIC - BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Application to Suspend Obligation to Supply Service to Cryptocurrency Mining Project dated December 21, 2022 |
December 21, 2022 | B-1-1 | CONFIDENTIAL – Letter dated December 21, 2022 - BC Hydro submitting Confidential Application to Suspend Obligation to Supply Service to Cryptocurrency Mining Project |