BC Hydro

Electricity Purchase Agreement Extension for Robson Valley

Completed: 2023

On March 31, 2023, BC Hydro filed with the BCUC a 34-month extension agreement between BC Hydro and Robson Valley Power Corporation for the 3.6 MW Robson Valley hydro project. BC Hydro requests an extension of the expiration date for the Robson Valley 2020 Electricity Purchase Agreement from January 31, 2023, to November 30, 2025.

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: June 22, 2023 @ 10:42 am
G-166-23 Final Order June 28, 2023

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
May 11, 2023 A-1 Letter dated May 11, 2023 – Appointing the Panel for the review of BC Hydro Electricity Purchase Agreement Extension for Robson Valley dated March 31, 2023
May 11, 2023 A-2 Letter dated May 11, 2023 – BCUC Order G-114-23 establishing a regulatory timetable
May 25, 2023 A-3 Letter dated May 25, 2023 – BCUC Information Request No. 1 to BC Hydro
May 25, 2023 A-4 CONFIDENTIAL - Letter dated May 25, 2023 – BCUC Confidential Information Request No. 1 to BC Hydro

B Exhibits - Applicant Documents

Date Title Document Description
March 31, 2023 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) - Electricity Purchase Agreement (EPA) Extension for Robson Valley dated March 31, 2023
March 31, 2023 B-1-1 CONFIDENTIAL – Letter dated March 31, 2023 - BC Hydro confidential EPA Extension for Robson Valley
May 19, 2023 B-2 Letter dated May 19, 2023 - BC Hydro submitting Public Notice in compliance with Order G 114-23 Directives 2 and 3
June 08, 2023 B-3 PUBLIC - Letter dated June 8, 2023 - BC Hydro submitting redacted response to BCUC Information Request No. 1
June 08, 2023 B-3-1 CONFIDENTIAL - Letter dated June 8, 2023 - BC Hydro submitting confidential response to BCUC Information Request No. 1
June 08, 2023 B-4 CONFIDENTIAL - Letter dated June 8, 2023 - BC Hydro submitting confidential response to BCUC Confidential Information Request No. 1
June 22, 2023 B-5 Letter dated June 22, 2023 - BC Hydro submitting reply to Letters of Comment

Our Review Process