Creative Energy

2024 Revenue Requirements for the Core Thermal Energy System

Completed: 2024

Creative Energy is seeking BCUC approval to increase its thermal energy service rates by approximately 11 percent for service to buildings in Vancouver’s downtown and Northeast False Creek service areas (Core Thermal Energy System).

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: July 24, 2024 @ 9:06 am
G-272-24 Final Order October 24, 2024

Arguments/Submissions

Title Document Description
Creative Energy Final Argument Final Argument June 20, 2024
RCIA Final Argument Final Argument July 5, 2024
CEC Final Argument Final Argument July 5, 2024
BCOAPO Final Argument Final Argument July 5, 2024
Creative Energy Reply Argument Reply Argument July 30, 2024

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
December 29, 2023 A-1 Letter dated December 29, 2023 – Appointing the Panel for the review of Creative Energy Vancouver Platforms 2024 Revenue Requirements for the Core Thermal Energy System
January 12, 2024 A-2 Letter dated January 12, 2024 - BCUC Order G-13-24 establishing a regulatory timetable
February 29, 2024 A-3 Letter dated February 29, 2024 – BCUC Information Request No. 1 to Creative Energy
March 21, 2024 A-4 Letter dated March 21, 2024 – BCUC accepting extension request from Creative Energy
April 08, 2024 A-5 Letter dated April 8, 2024 - BCUC Order G-104-24 establishing an amended regulatory timetable
May 01, 2024 A-6 Letter dated May 1, 2024 – BCUC Information Request No. 2 to Creative Energy
June 10, 2024 A-7 Letter dated June 10, 2024 - BCUC Order G-158-24 with amended regulatory timetable and Panel Information Request No. 1
July 09, 2024 A-8 Letter dated July 9, 2024 – Order G-182-24 establishing an amended regulatory timetable

B Exhibits - Applicant Documents

Date Title Document Description
December 15, 2023 B-1 CREATIVE ENERGY VANCOUVER PLATFORMS (CREATIVE ENERGY) - 2024 Revenue Requirements for the Core Thermal Energy System dated December 15, 2023
February 05, 2024 B-2 Letter dated February 5, 2024 - Creative Energy submitting Public Notice confirmation in compliance with Order G-13-24
February 05, 2024 B-2-1 CONFIDENTIAL - Letter dated February 5, 2024 - Creative Energy submitting confidential List of Parties in compliance with Order G-13-24
February 16, 2024 B-3 Letter dated February 16, 2024 - Creative Energy submitting Evidentiary Update
February 22, 2024 B-3-1 Letter dated February 22, 2024 - Creative Energy submitting Evidentiary Update errata
March 21, 2024 B-4 Creative Energy submitting extension request for filing response to Information Request No. 1
March 25, 2024 B-5 Letter dated March 25, 2024 – Creative Energy submitting response to BCUC Information Request No. 1
March 25, 2024 B-6 Letter dated March 25, 2024 – Creative Energy submitting response to RCIA Information Request No. 1
March 25, 2024 B-7 Letter dated March 25, 2024 – Creative Energy submitting response to BCOAPO Information Request No. 1
March 25, 2024 B-8 PUBLIC - Letter dated March 25, 2024 – Creative Energy submitting redacted response to CEC Information Request No. 1
March 25, 2024 B-8-1 CONFIDENTIAL - Letter dated March 25, 2024 – Creative Energy submitting confidential response to CEC Information Request No. 1
May 23, 2024 B-9 PUBLIC - Letter dated May 23, 2024 – Creative Energy submitting public response to BCUC Information Request No. 2
May 23, 2024 B-9-1 CONFIDENTIAL - Letter dated May 23, 2024 – Creative Energy submitting confidential response to BCUC Information Request No. 2
May 23, 2024 B-10 Letter dated May 23, 2024 – Creative Energy submitting response to BCOAPO Information Request No. 2
May 23, 2024 B-11 Letter dated May 23, 2024 – Creative Energy submitting response to CEC Information Request No. 2
May 23, 2024 B-12 Letter dated May 23, 2024 – Creative Energy submitting response to RCIA Information Request No. 2
June 18, 2024 B-13 Letter dated June 18, 2024 – Creative Energy submitting response to Panel Information Request No. 1
June 19, 2024 B-13-1 Letter dated June 19, 2024 – Creative Energy submitting supporting information to their response to Panel Information Request No. 1
July 16, 2024 B-14 Letter dated July 16, 2024 – Creative Energy submission on items regarding interim rates

C Exhibits - Intervener Documents



Date Title Document Description
January 24, 2024 C1-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, TENANTS RESOURCE AND ADVISORY CENTRE (BCOAPO) – Letter dated January 24, 2024 submitting request to intervene by Irina Mis
March 07, 2024 C1-2 Letter dated March 7, 2024 – BCOAPO submitting Information Request No. 1 to Creative Energy
May 01, 2024 C1-3 Letter dated May 1, 2024 – BCOAPO submitting Information Request No. 2 to Creative Energy
July 23, 2024 C1-4 Letter dated July 23, 2024 – BCOAPO submission on items regarding interim rates
January 30, 2024 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) - Letter dated January 30, 2024 submitting request to intervene by David Craig
March 07, 2024 C2-2 Letter dated March 7, 2024 – CEC submitting Information Request No. 1 to Creative Energy
May 01, 2024 C2-3 Letter dated May 1, 2024 – CEC submitting Information Request No. 2 to Creative Energy
July 23, 2024 C2-4 Letter dated July 23, 2024 – CEC submission on items regarding interim rates
February 05, 2024 C3-1 RESIDENTIAL CONSUMER INTERVENER ASSOCIATION (RCIA) – Letter dated February 5, 2024 submitting request to intervene by Abdulrahman Abomazid
March 07, 2024 C3-2 Letter dated March 7, 2024 – RCIA submitting Information Request No. 1 to Creative Energy
April 29, 2024 C3-3 Letter dated April 29, 2024 – RCIA submitting Information Request No. 2 to Creative Energy
July 23, 2024 C3-4 Letter dated July 23, 2024 – RCIA submission on items regarding interim rates

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more