FortisBC Energy Inc. (gas)

Certificate of Public Convenience and Necessity for the Okanagan Capacity Mitigation Project

In Progress

FortisBC Energy Inc (FEI) is seeking, among other things, BCUC approval to construct and operate a new liquified natural gas (LNG) storage and regasification facility at FEI’s existing Kelowna Gate Station. The project also involves the transportation of LNG by truck from FEI’s existing Tilbury LNG facility to the Kelowna Gate Station. The purpose of the project is to address the projected capacity shortfall of the Interior Transmission System (ITS) for the winter of 2026/2027.

Timetable

Subject Date
Intervener registration deadline Thursday, September 19, 2024
BCUC Information Request (IR) No. 1 Thursday, September 26, 2024
Intervener IR No. 1 Thursday, October 3, 2024
FEI responses to IR No. 1 Thursday, October 24, 2024
Letters of comment deadline Thursday, October 31, 2024
FEI final argument Thursday, November 21, 2024
Intervener final argument Thursday, December 5, 2024
FEI reply argument Thursday, December 19, 2024

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: September 5, 2024 @ 2:34 pm

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
August 09, 2024 A-1 Panel Appointment
August 12, 2024 A-2 Panel Amendment
August 21, 2024 A-3 BCUC Order G-227-24 establishing a regulatory timetable

B Exhibits - Applicant Documents

Date Title Document Description
July 30, 2024 B-1 PUBLIC - FORTISBC ENERGY INC. (FEI) – Application for Certificate of Public Convenience and Necessity (CPCN) for the Okanagan Capacity Mitigation Project (OCMP)
July 30, 2024 B-1-1 CONFIDENTIAL – FEI CPCN Application for the OCMP – Confidential Appendices
September 05, 2024 B-2 FEI submitting confirmation of public notice