In Progress
FortisBC Energy Inc (FEI) is seeking, among other things, BCUC approval to construct and operate a new liquified natural gas (LNG) storage and regasification facility at FEI’s existing Kelowna Gate Station. The project also involves the transportation of LNG by truck from FEI’s existing Tilbury LNG facility to the Kelowna Gate Station. The purpose of the project is to address the projected capacity shortfall of the Interior Transmission System (ITS) for the winter of 2026/2027.
Subject | Date |
---|---|
Intervener registration deadline | Thursday, September 19, 2024 |
BCUC Information Request (IR) No. 1 | Thursday, September 26, 2024 |
Intervener IR No. 1 | Thursday, October 3, 2024 |
FEI responses to IR No. 1 | Thursday, October 24, 2024 |
Letters of comment deadline | Thursday, October 31, 2024 |
FEI final argument | Thursday, November 21, 2024 |
Intervener final argument | Thursday, December 5, 2024 |
FEI reply argument | Thursday, December 19, 2024 |
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: September 5, 2024 @ 2:34 pm |
Date | Title | Document Description |
---|---|---|
August 09, 2024 | A-1 | Panel Appointment |
August 12, 2024 | A-2 | Panel Amendment |
August 21, 2024 | A-3 | BCUC Order G-227-24 establishing a regulatory timetable |
Date | Title | Document Description |
---|---|---|
July 30, 2024 | B-1 | PUBLIC - FORTISBC ENERGY INC. (FEI) – Application for Certificate of Public Convenience and Necessity (CPCN) for the Okanagan Capacity Mitigation Project (OCMP) |
July 30, 2024 | B-1-1 | CONFIDENTIAL – FEI CPCN Application for the OCMP – Confidential Appendices |
September 05, 2024 | B-2 | FEI submitting confirmation of public notice |
Subscribe to a proceeding to receive email notifications when public documents are added to this proceeding.