In Progress
PNG(NE) seeks BCUC acceptance of a capital expenditure schedule to inspect, repair, or replace certain equipment at the Tumbler Ridge Gas Plant.
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: September 4, 2024 @ 4:09 pm |
Date | Title | Document Description |
---|---|---|
September 04, 2024 | A-1 | Panel Appointment |
Date | Title | Document Description |
---|---|---|
August 21, 2024 | B-1 | PACIFIC NORTHERN GAS (NE) LTD. (PNG NE) - Tumbler Ridge Gas Plant Rehabilitation Project Section 44.2 Expenditures Application |
August 21, 2024 | B-1-1 | CONFIDENTIAL - PNG NE submitting Tumbler Ridge Gas Plant Rehabilitation Project Section 44.2 Expenditures Application Appendix D |
Subscribe to a proceeding to receive email notifications when public documents are added to this proceeding.