FortisBC Energy Inc. (gas)

Regional Gas Supply Diversity Development Cost Deferral Account Cost Recovery

In Progress

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: March 6, 2025 @ 4:20 pm
G-123-25 Final Order May 15, 2025

Arguments/Submissions

Title Document Description
FEI Final Argument Final Argument March 19, 2025
BCOAPO Final Argument Final Argument April 3, 2025
CEC Final Argument Final Argument April 3, 2025
FEI Reply Argument Reply Argument April 17, 2025

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
January 06, 2025 A-1 Panel Appointment
January 10, 2025 A-2 BCUC Order G-4-25 establishing a regulatory timetable
February 04, 2025 A-3 BCUC providing information for interveners
February 06, 2025 A-4 BCUC Information Request No. 1 to FEI

B Exhibits - Applicant Documents

Date Title Document Description
December 20, 2024 B-1 FORTISBC ENERGY INC. (FEI) – Regional Gas Supply Diversity (RGSD) Development Cost Deferral Account Cost Recovery
January 20, 2025 B-2 FEI submitting Public Notice confirmation in compliance with Order G-4-25 Directives
March 06, 2025 B-3 PUBLIC - FEI submitting response to BCUC Information Request No. 1
March 06, 2025 B-3-1 CONFIDENTIAL – FEI submitting response to BCUC Information Request No. 1
March 06, 2025 B-4 FEI submitting response to BCOAPO Information Request No. 1
March 06, 2025 B-5 FEI submitting response to CEC Information Request No. 1

C Exhibits - Intervener Documents