In Progress
BC Hydro has applied to the BCUC seeking approval of Electricity Purchase Agreement renewal for the Marion 3 Creek Hydroelectric project (Marion Creek).
Subject | Date |
---|---|
BC Hydro responses to BCUC IR No. 1 | Thursday, May 22, 2025 |
Letters of comment deadline | Thursday, June 5, 2025 |
BC Hydro responses to Letters of comment (if any) and final argument | Thursday, June 19, 2025 |
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: May 6, 2025 @ 4:33 pm |
Date | Title | Document Description |
---|---|---|
April 23, 2025 | A-1 | Panel Appointment |
April 23, 2025 | A-2 | Order G-104-25 establishing a regulatory timetable |
May 06, 2025 | A-3 | BCUC Information Request No. 1 to BC Hydro |
May 06, 2025 | A-4 | CONFIDENTIAL – BCUC Confidential Information Request No. 1 to BC Hydro |
Date | Title | Document Description |
---|---|---|
March 28, 2025 | B-1 | PUBLIC – BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – BC Hydro Electricity Purchase Agreement Renewal for Marion Creek Application |
March 28, 2025 | B-1-1 | CONFIDENTIAL – BC Hydro Electricity Purchase Agreement Renewal for Marion Creek Application |
May 01, 2025 | B-2 | BC Hydro submitting confirmation of public notice in compliance with Order G-104-25 |
Subscribe to a proceeding to receive email notifications when public documents are added to this proceeding.
Subscribe here