On June 10, 2025, the BCUC established a public hearing process to determine if Summitt Energy BC LP had contravened the Code of Conduct for Gas Marketers in relation to a customer agreement.
Subject | Date |
---|---|
BCUC Information Request (IR) No. 1 to Summitt | Wednesday, June 25, 2025 |
Summitt Response to IR No. 1 | Wednesday, July 16, 2025 |
Summitt Final Argument | Wednesday, July 30, 2025 |
Title | Document Description |
---|---|
EXHIBIT LIST | Updated: June 18, 2025 @ 8:55 am |
Date | Title | Document Description |
---|---|---|
June 10, 2025 | A-1 | Panel Appointment |
June 10, 2025 | A-2 | BCUC Order G-139-25 establishing a regulatory timetable |
June 10, 2025 | A2-1 | BCUC Staff submitting Staff Investigation Report dated April 25, 2025 |
June 10, 2025 | A2-2 | BCUC Staff submitting BCUC Staff letter dated October 24, 2024 |
June 10, 2025 | A2-2-1 | CONFIDENTIAL – BCUC Staff submitting BCUC Staff letter dated October 24, 2024 |
June 10, 2025 | A2-3 | CONFIDENTIAL – BCUC Staff submitting Summit Energy BC LP (Summit) audio recording dated September 11, 2024 |
Date | Title | Document Description |
---|---|---|
June 18, 2025 | B-1 | SUMMITT ENERGY BC LP (SUMMITT ENERGY) submitting confirmation of Public Notice in compliance with Order G-139-25 Directive 2 |