Other

Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public

Completed: 2008

Hearing and Other Documents

Title Document Description
* Exhibit List Updated: March 28, 2008 @ 3:51 pm
* Distribution List Updated: January 24, 2008 @ 5:13 pm
* Email Fax List Updated: January 24, 2008 @ 5:13 pm
Order No. C-1-08 - Reasons for Decision

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
January 11, 2008 A-1 Letter dated January 11, 2008 issuing Order No. G-8-08 establishing the a Written Public Hearing and Regulatory Timetable
January 11, 2008 A-2 Letter dated January 11, 2008 issuing Information Request No. 1 to Dockside
February 15, 2008 A-3 Letter dated February 15, 2008, issuing Information Request No. 2 to Dockside
February 29, 2008 A-4 Letter dated February 29, 2008 granting an extension to the filing date for responses to Commission Information Request No. 2 to March 6, 2008
March 05, 2008 A-5 Letter dated March 5, 2008 and Order No. G-33-08 amending the Regulatory Timetable
March 28, 2008 A-6 Letter dated March 28, 2008 denying request for Interim Rates

B Exhibits - Applicant Documents

Date Title Document Description
January 11, 2008 B-1 Letter dated December 21, 2007 filing Dockside Energy's Certificate of Public Convenience and Necessity Application for the District Energy System
August 26, 2008 B-1-2 CONFIDENTIAL – Appendix 1 Memorandum of Understanding with the Delta Hotel
August 26, 2008 B-1-3 Appendices 2 and 3 list
January 21, 2008 B-2 Letter dated January 21, 2008, filing response to the Commission’s Information Request No. 1
February 29, 2008 B-3 Letter dated February 28, 2008 requesting extension to file response to Commission Information Request No. 2 until March 6, 2008
March 05, 2008 B-4 Letter dated March 6, 2008, filing response to Commission’s Information Request No. 2
March 11, 2008 B-5 Letter dated March 11, 2008, filing Dockside’s Final Submission
March 11, 2008 B-6 Letter received March 11, 2008, filing response to outstanding questions Information Request No. 1, question 12.1 and 13.1
March 11, 2008 B-7 CONFIDENTIAL - Letter received March 11, 2008, filing the draft of the Infrastructure Agreement referenced in Information Request No. 1, question 12.1
March 20, 2008 B-8 Letter dated March 20, 2008 requesting Commission approval for Interim Rates pending final decision