BC Hydro

BC Hydro Reconsideration 2008 LTAP - Reconsideration and Variance of condition 7 of Commission Order G-91-09

Completed: 2009

Hearing and Other Documents

Title Document Description
* Email Fax List
* Exhibit List Updated: November 9, 2009 @ 4:47 pm
* Distribution List
Reasons for Decision Order G-150-09 - December 3, 2009 British Columbia Hydro and Power Authority Reconsideration of Order G-91-09 in the 2008 Long-Term Acquisition Plan ~ Decision

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
October 14, 2009 A-1 Letter dated October 13, 2009 Regulatory Timetable

B Exhibits - Applicant Documents

Date Title Document Description
October 13, 2009 B-1 Application for Reconsideration and Variance of condition 7 of Commission Order G-91-09
November 04, 2009 B-2 Letter dated November 4, 2009 filing BC Hydro’s Reply Submissions

C Exhibits - Intervener Documents

B.C. SUSTAINABLE ENERGY ASSOCIATION (BCSEA) AND THE SIERRA CLUB OF BC (SBCC) (BCSEA ET AL) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
COPE 378 – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
COLUMBIA POWER CORPORATION (CPC) – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
HORIZON TECHNOLOGIES INC. / ENERGY SOLUTIONS FOR VANCOUVER ISLAND SOCIETY (ESVI) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
INDEPENDENT POWER PRODUCERS ASSOCIATION OF BC (IPPBC) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
JOINT INDUSTRY ELECTRICITY STEERING COMMITTEE (JIESC) – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
TEXADA ACTION NOW COMMUNITY ASSOCIATION (TAN) – Email dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
TERASEN UTILITIES – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
VANPORT STERILIZERS INC. – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
BRITISH COLUMBIA OLD AGE PENSIONERS ORGANIZATION (BCOAPO) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision


Date Title Document Description
October 29, 2009 C1-1 B.C. SUSTAINABLE ENERGY ASSOCIATION (BCSEA) AND THE SIERRA CLUB OF BC (SBCC) (BCSEA ET AL) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C3-1 COPE 378 – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C4-1 COLUMBIA POWER CORPORATION (CPC) – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C5-1 HORIZON TECHNOLOGIES INC. / ENERGY SOLUTIONS FOR VANCOUVER ISLAND SOCIETY (ESVI) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C6-1 INDEPENDENT POWER PRODUCERS ASSOCIATION OF BC (IPPBC) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
November 09, 2009 C6-1A Revised letter dated October 27, 2009 issuing support for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C7-1 JOINT INDUSTRY ELECTRICITY STEERING COMMITTEE (JIESC) – Letter dated October 28, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C8-1 TEXADA ACTION NOW COMMUNITY ASSOCIATION (TAN) – Email dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C9-1 TERASEN UTILITIES – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C10-1 VANPORT STERILIZERS INC. – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision
October 29, 2009 C11-1 BRITISH COLUMBIA OLD AGE PENSIONERS ORGANIZATION (BCOAPO) – Letter dated October 27, 2009 responding to BC Hydro’s request for Reconsideration of the 2008 LTAP Decision

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more