Completed: 2010
Title | Document Description |
---|---|
* Exhibit List | Updated: September 22, 2010 @ 8:13 am |
*February 23, 2011 - Decision G-26-11 | Reasons for Decision |
Title | Document Description |
---|---|
TGI Final Submission - CONFIDENTIAL | CONFIDENTIAL TGI Final Submission -September 27, 2010 |
BCOAPO Final Submission - CONFIDENTIAL | CONFIDENTIAL BCOAPO Final Submission -October 4, 2010 |
CEC Final Submission - CONFIDENTIAL | CONFIDENTIAL CEC Final Submission -October 4, 2010 |
TGI Reply Submission CONFIDENTIAL | TGI Reply Submission CONFIDENTIAL October 13, 2010 |
Date | Title | Document Description |
---|---|---|
July 23, 2010 | A-1 | Letter dated July 13, 2010 – Commission Order G-120-10 |
August 11, 2010 | A-2 | Letter dated August 10, 2010 – Amended Regulatory Timetable |
August 13, 2010 | A-3 | Letter dated August 13, 2010 – CONFIDENTIAL BCUC IR No. 1 |
September 07, 2010 | A-4 | Letter dated September 7, 2010 – CONFIDENTIAL Information Request No. 2 to TGI |
September 17, 2010 | A-5 | Letter dated September 17, 2010 – Commission Order G-145-10 and Written Hearing Timetable |
Date | Title | Document Description |
---|---|---|
July 23, 2010 | B-1 | TERASEN GAS INC. (TGI) Letter dated July 13, 2010 – Public version of the Application for Approval of a Gas Supply Mitigation Incentive Program for the November 1, 2010 to October 31, 2013 Three-Year Period |
July 23, 2010 | B-1-1 | CONFIDENTIAL Letter dated July 13, 2010 – Confidential version of the Application for Approval of a Gas Supply Mitigation Incentive Program for the November 1, 2010 to October 31, 2013 Three-Year Period |
August 30, 2010 | B-2 | CONFIDENTIAL Letter dated August 30, 2010 – Confidential response to BCUC IR No.1 |
August 30, 2010 | B-3 | CONFIDENTIAL Letter dated August 30, 2010 – Confidential response to CEC IR No. 1 |
September 13, 2010 | B-4 | Letter dated September 13, 2010 – TGI Comments on Process |
September 13, 2010 | B-5 | CONFIDENTIAL Letter dated September 13, 2010 – TGI Confidential Response to BCUC IR No. 2 |
September 13, 2010 | B-5-1 | CONFIDENTIAL Letter dated September 14, 2010 – TGI Confidential Clarification to BCUC IR 2.3.1 |
September 13, 2010 | B-6 | CONFIDENTIAL Letter dated September 13, 2010 – TGI Confidential Response to CEC IR No. 2 |
September 16, 2010 | B-7 | CONFIDENTIAL Letter dated September 15, 2010 – TGI Confidential Responses to BCOAPO IR No. 2 |
September 22, 2010 | B-8 | CONFIDENTIAL September 21, 2010 filing - Terasen Gas GSMIP Workshop Presentation |
Date | Title | Document Description |
---|---|---|
July 23, 2010 | C1-1 | COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) - VIA EMAIL Letter dated July 21, 2010 - Request for Intervener Status by Christopher Weafer |
August 19, 2010 | C1-2 | Letter dated August 18, 2010 – CEC CONFIDENTIAL Information Request No. 1 to TGI |
September 07, 2010 | C1-3 | Letter dated September 7, 2010 – CEC CONFIDENTIAL Information Request No. 2 to TGI |
September 15, 2010 | C1-4 | Letter dated September 15, 2010 – CEC Comments on Regulatory Process |
August 23, 2010 | C2-1 | BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION (BCOAPO) VIA EMAIL Letter Dated August 23, 2010 – Request for Late Intervener Status by Jim Quail and James Wightman |
September 13, 2010 | C2-2 | Letter dated September 10, 2010 – BCOAPO Information Request No. 2 |
September 16, 2010 | C2-3 | Letter dated September 15, 2010 – BCOAPO Comments regarding the appropriate process for the determination of the Application |
Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.