FortisBC Energy Inc. (gas)

FEI - Biomethane Purchase Agreement between FortisBC Energy Inc. and the Greater Vancouver Sewerage and Drainage District

Completed: 2013

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: September 27, 2013 @ 9:28 am
*_Email Fax List Updated: September 13, 2013 @ 12:08 pm
*E-13-13 Reasons for Decision dated September 30, 2013

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
August 22, 2013 A-1 Letter Dated August 22, 2013 – Appointment of Commission Panel for the review of the FortisBC Energy Inc. Biomethane Purchase Agreement between FortisBC Energy Inc. and the Greater Vancouver Sewerage and Drainage District
August 23, 2013 A-2 Letter Dated August 23, 2013 – Order G-130-13 Establishing the Regulatory Timetable
September 13, 2013 A-3 Letter Dated September 13, 2013 – Commission Information Request No. 1
September 13, 2013 A-4 CONFIDENTIAL Letter Dated September 13, 2013 – Confidential Commission Information Request No. 1
September 20, 2013 A-5 Letter Dated September 20, 2013 – Streamlined Review Process Information
September 10, 2013 A2-1 Letter Dated September 10, 2013 – Commission staff filing FEI Biomethane Post Implementation & Program Modification Proceeding – Exhibit B-16
September 10, 2013 A2-2 Letter Dated September 10, 2013 – Commission staff filing FEI Biomethane Post Implementation & Program Modification Proceeding – Excerpts from Exhibit B-17
September 10, 2013 A2-3 Letter Dated September 10, 2013 – Commission staff filing FEI Biomethane Post Implementation & Program Modification Proceeding – Excerpts from Exhibit B-19

B Exhibits - Applicant Documents

Date Title Document Description
August 22, 2013 B-1 FORTISBC ENERGY INC. (FEI) Letter Dated August 16, 2013 – Application for Approval of Biomethane Purchase Agreement between FEI and the Greater Vancouver Sewerage and Drainage District (GVS&DD)
August 22, 2013 B-1-1 CONFIDENTIAL – Appendices A and B to FEI Application for Approval of Biomethane Purchase Agreement between FEI and the GVS&DD
September 11, 2013 B-1-2 CONFIDENTIAL Letter Dated September 11, 2013 – Confidential Appendix B Cost of Service Financial Model
September 19, 2013 B-2 Letter Dated September 19, 2013 – FEI Response to BCUC IR No. 1
September 19, 2013 B-3 CONFIDENTIAL Letter Dated September 19, 2013 – FEI Response to BCUC Confidential IR No. 1
September 19, 2013 B-4 Letter Dated September 19, 2013 – FEI Response to CEC IR No. 1
September 25, 2013 B-5 Submitted at Oral Proceeding September 25, 2013 - SLIDE PRESENTATION FROM FEI
September 25, 2013 B-6 Submitted at Oral Proceeding September 25, 2013 - OUTLINE OF SUBMISSIONS BY MR. BYSTROM FOR FORTISBC
September 25, 2013 B-7 Submitted at Oral Proceeding September 25, 2013 - DOCUMENT PRESENTED BY MR. GRAMM
September 26, 2013 B-8 Letter Dated September 26, 2013 – FEI Response to Undertakings from the SRP

C Exhibits - Intervener Documents



Date Title Document Description
August 30, 2013 C1-1 GREATER VANCOUVER SEWERAGE AND DRAINAGE DISTRICT (GVS&DD) – Letter dated August 30, 2013 – Request for Intervener Registration Status by Ian Webb, Lawson Lundell
September 25, 2013 C1-2 Submitted at Oral Proceeding September 25, 2013 - SLIDE PRESENTATION FROM GVS&DD
August 30, 2013 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated August 30, 2013 – Request for Intervener Registration Status by Chris Weafer, Owen Bird
September 13, 2013 C2-2 Letter Dated September 13, 2013 – CEC Submitting Information Request No. 1
September 23, 2013 C2-3 Letter Dated September 23, 2013 – CEC Submitting Undertaking of Confidentiality
August 30, 2013 C3-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BCHYDRO) – Letter dated August 30, 2013 – Request for Intervener Registration Status by Janet Fraser, Chief Regulatory Officer
September 11, 2013 C4-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) Letter Dated September 10, 2013 – Request for Late Intervener Registration Status by Williams Andrews and Thomas Hackney
September 11, 2013 C4-2 Letter Dated September 10, 2013 – BSCEA Submitting Undertakings of Confidentiality
September 13, 2013 C4-3 Letter Dated September 13, 2013 – BSCEA Submitting comments regarding Information Request
September 11, 2013 C5-1 PARADIGM ENVIRONMENTAL TECHNOLOGIES INC. (PARADIGM) ) Letter Dated September 11, 2013 – Request for Late Intervener Registration Status by Jeff Plato
September 13, 2013 C5-2 Letter Dated September 13, 2013 – Paradigm Submitting comments regarding Information Request
September 24, 2013 C5-3 Letter Dated September 24, 2013 – Paradigm Submitting Undertaking of Confidentiality

Transcripts

Date Title Document Description
September 25, 2013 Transcript Volume 1 Streamlined Review Oral Proceeding September 25, 2013