FortisBC Energy Inc. (gas)

FortisBC Energy Inc. Application for Approval of Biomethane Recovery Charge (BERC) Rate Methodology ~ Project No.3698850

Completed: 2016

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: May 4, 2016 @ 3:33 pm
*_G-133-16 Decision Order G-133-16 and Decision dated August 12, 2016

Arguments/Submissions

Title Document Description
FEI Final Argument Final Argument February 4, 2016
BCSEA Final Argument Final Argument February 16, 2016
CEC Final Argument Final Argument February 16, 2016
BCOAPO Final Argument Final Argument February 16, 2016
FEI Reply Argument Reply Argument February 23, 2016
FEI Supplemental Argument Supplemental Argument May 9, 2016
BCOAPO Supplemental Argument Supplemental Argument May 13, 2016
CEC Supplemental Argument Supplemental Argument May 13, 2016
BCSEA Supplemental Argument Supplemental Argument May 13, 2016
FEI Supplemental Reply Argument Supplemental Reply Argument May 18, 2016

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
September 08, 2015 A-1 Letter dated September 8, 2015 – Appointing Panel for the review of the FortisBC Inc. Application for Approval of Biomethane Energy Recovery Charge Rate Methodology
September 18, 2015 A-2 Letter dated September 18, 2015 – Commission Order G-147-15 establishing the Regulatory Timetable and requesting supplemental information
October 13, 2015 A-3 Letter dated October 13, 2015 – Commission Information Request No. 1 to FEI
November 05, 2015 A-4 Letter dated November 5, 2015 – Granting Extension Request to FEI
November 10, 2015 A-5 Letter dated November 10, 2015 – Procedural Conference Information
November 20, 2015 A-6 Letter dated November 19, 2015 – Commission Order G-181-15 establishing the remainder of the regulatory timetable
January 15, 2016 A-7 Letter dated January 14, 2016 – Commission Information Request No. 2 to FEI - Technical Questions for SRP
January 15, 2016 A-8 Letter dated January 15, 2016 – BCUC Rules of Practice and Procedure to parties
April 22, 2016 A-9 Letter dated April 22, 2016 – Panel request comments regarding submissions on nature of price floors and ceilings
May 04, 2016 A-10 Letter dated May 4, 2016 – Commission Order G-60-16 establishing the remainder of the regulatory timetable
February 04, 2016 A2-2 Submitted at SRP February 3, 2016 – CITY OF SURREY IR 11.4

B Exhibits - Applicant Documents

Date Title Document Description
September 02, 2015 B-1 FORTISBC ENERGY INC. (FEI) Letter dated August 28, 2015 - Application for Approval of Biomethane Energy Recovery Charge (BERC) Rate Methodology
September 02, 2015 B-1-1 Letter dated October 1, 2015 – FEI Submitting Evidentiary Update
September 02, 2015 B-1-2 Errata to the Application
September 21, 2015 B-2 Letter dated September 18, 2015 - FEI Submitting Application Notice
October 01, 2015 B-3 Letter dated October 1, 2015 - FEI Supplementary Information Filing
November 03, 2015 B-4 Letter dated November 3, 2015 - FEI Submitting Request for Filing Extension
November 06, 2015 B-5 Letter dated November 6, 2015 - FEI Submitting Response to BCUC IR No.1
November 06, 2015 B-6 Letter dated November 6, 2015 - FEI Submitting Response to BCOAPO IR No.1
November 06, 2015 B-7 Letter dated November 6, 2015 - FEI Submitting Response to BCSEA IR No.1
November 06, 2015 B-8 Letter dated November 6, 2015 - FEI Submitting Response to CEC IR No.1
February 02, 2016 B-9 Letter dated February 2, 2016 - FEI Submitting Response to BCUC IR No.2
February 04, 2016 B-10 Submitted at SRP February 3, 2016 – FEI SRP Presentation
February 04, 2016 B-11 Submitted at SRP February 3, 2016 – FEI Biomethane Program Marketing Material Samples
February 04, 2016 B-12 Submitted at SRP February 3, 2016 – Rate 1B Customer Quarterly Churn Rate
April 28, 2016 B-13 Letter dated April 27, 2016 – FEI Submitting response regarding nature of price floors and ceilings

C Exhibits - Intervener Documents



Date Title Document Description
September 22, 2015 C1-1 BC SUSTAINABLE ENERGY ASSOCIATION AND THE SIERRA CLUB BC (BCSEA) Letter dated September 22, 2015 – Request for Intervener Status by William Andrews and Thomas Hackney
October 21, 2015 C1-2 Letter dated October 21, 2015 – BCSEA Submitting IR No. 1 to FEI
April 22, 2016 C1-3 Letter dated April 22, 2016 – BCSEA Submitting comments regarding submissions on nature of price floors and ceilings
September 24, 2015 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) Letter dated September 23, 2015 – Request for Intervener Status by Christopher Weafer
October 21, 2015 C2-2 Letter dated October 21, 2015 – CEC Submitting IR No. 1 to FEI
November 04, 2015 C2-3 Letter dated November 4, 2015 - CEC Submitting Comments on FEI Extension Request
April 28, 2016 C2-4 Letter dated April 28, 2016 – CEC Submitting comments regarding submissions on nature of price floors and ceilings
October 13, 2015 C3-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, AND THE TENANT RESOURCE AND ADVISORY CENTRE (BCOAPO) Letter dated October 13, 2015 – Request for Intervener Status by Tannis Braithwaite and James Wightman
October 21, 2015 C3-2 Letter dated October 21, 2015 – BCOAPO Submitting IR No. 1 to FEI
November 04, 2015 C3-3 Letter dated November 4, 2015 - BCOAPO Submitting Comments on FEI Extension Request
January 15, 2016 C3-4 Letter dated January 14, 2016 - BCOAPO Submitting Comments regarding written technical questions
April 28, 2016 C3-5 Letter dated April 27, 2016 – BCOAPO Submitting comments regarding submissions on nature of price floors and ceilings

Transcripts

Date Title Document Description
November 16, 2015 Transcript Volume 1 Procedural Conference ~ November 16, 2015
February 04, 2016 Transcript Volume 2 Streamlined Review Process February 3, 2016

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more