BC Hydro

British Columbia Hydro and Power Authority Application for Reliability Coordinator Registration with the Mandatory Reliability Standards Program ~ Project No. 1598978

Completed: 2019

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: August 2, 2019 @ 9:55 am
*_Order G-199-19 Final Order with Reasons for Decision dated August 23, 2019

Arguments/Submissions

Title Document Description
BC Hydro Final Argument Final Argument August 6, 2019
FBC Final Argument Final Argument August 9, 2019
BCOAPO Final Argument Final Argument August 12, 2019
BC Hydro Reply Argument Reply Argument August 13, 2019

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
November 30, 2018 A-1 Letter dated November 30, 2018 - Appointing the Panel for the review of British Columbia Hydro and Power Authority Application for Reliability Coordinator Registration with the Mandatory Reliability Standards Program
November 30, 2018 A-2 Letter dated November 30, 2018 – BCUC Order G-227-18 establishing the Regulatory Timetable
December 13, 2018 A-3 Letter dated December 13, 2018 – Request for Western Electricity Coordinating Council Documentation on Full Certification Limitations
December 21, 2018 A-4 Letter dated December 21, 2018 – BCUC Information Request No. 1 to BC Hydro
December 24, 2018 A-5 Letter dated December 24, 2018 - BCUC Order G-253-18 amending the Regulatory Timetable and establishing a procedural conference
January 08, 2019 A-6 Letter dated January 8, 2019 – Response to BC Hydro’s request to reschedule the procedural conference (Exhibit B-4)
January 10, 2019 A-7 Letter dated January 10, 2019 – BCUC Order G-5-19 amending the Regulatory Timetable and procedural conference date
January 11, 2019 A-8 Letter dated January 11, 2019 – BCUC Order G-7-19 amending the Regulatory Timetable
January 24, 2019 A-9 Letter dated January 24, 2019 – Procedural conference information
January 29, 2019 A-10 Letter dated January 29, 2019 – Panel Information Request No. 1 to BC Hydro
February 06, 2019 A-11 Letter dated February 6, 2019 – BCUC Order G-25-19 dated January 30, 2019 following oral order at the procedural conference
February 13, 2019 A-12 Letter dated February 13, 2019 – BCUC Order G-32-19 with reasons amending the Regulatory Timetable
April 30, 2019 A-13 Letter dated April 30, 2019 – Cancellation of the Streamlined Review Process
May 03, 2019 A-14 Letter dated May 3, 2019 – BCUC Order G-89-19 amending the Regulatory Timetable
May 10, 2019 A-15 Letter dated May 10, 2019 – BCUC Information Request No. 2 to BC Hydro
June 18, 2019 A-16 Letter dated June 18, 2019 – Panel Information Request No. 2 to BC Hydro
July 04, 2019 A-17 Letter dated July 4, 2019 – Procedural conference information
July 05, 2019 A-17-1 Letter dated July 5, 2019 – Procedural conference information correction
July 05, 2019 A-18 Letter dated July 5, 2019 – Responding to the procedural conference cancellation request
July 15, 2019 A-19 Letter dated July 15, 2019 – BCUC Order G-158-19 amending the Regulatory Timetable
August 02, 2019 A2-1 Letter dated August 2, 2019 – Western Electricity Coordinating Council Completion Notice for BC Hydro RC Certification Bucket Items dated July 31, 2019

B Exhibits - Applicant Documents

Date Title Document Description
November 30, 2018 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) - Letter dated October 29, 2018 – Application for Reliability Coordinator Registration with the Mandatory Reliability Standards Program
December 18, 2018 B-2 Letter dated December 18, 2018 – BC Hydro response to BCUC request
December 20, 2018 B-3 Letter dated December 19, 2018 – BC Hydro workshop presentation
January 04, 2019 B-4 Letter dated January 4, 2019 – BC Hydro request to reschedule procedural conference
January 10, 2019 B-5 Letter dated January 10, 2019 – BC Hydro request extension to file Information Request response and procedural conference
January 23, 2019 B-6 Letter dated January 23, 2019 – BC Hydro responses to BCUC and intervener Information Requests No. 1
January 30, 2019 B-7 Letter dated January 30, 2019 – BC Hydro responses to Panel Information Request No. 1
January 31, 2019 B-8 Letter dated January 30, 2019 – BC Hydro submission at Procedural Conference - RC Registration Timeline
March 01, 2019 B-9 Letter dated March 1, 2019 – BC Hydro confirmation of distribution of draft documents
April 30, 2019 B-10 Letter dated April 30, 2019 – BC Hydro submission on Four Key Documents and Reply Submission
May 29, 2019 B-11 Letter dated May 29, 2019 – BC Hydro responses to BCUC Information Request No. 2
June 25, 2019 B-12 Letter dated June 25, 2019 – BC Hydro responses to BCUC Panel Information Request No. 2
July 04, 2019 B-13 Letter dated July 4, 2019 – BC Hydro request for cancellation of procedural conference - WECC’s Certification Report and letter to BCUC (BCHA RC Certification Acceptance Letter) Attached
July 30, 2019 B-14 Letter dated July 30, 2019 – BC Hydro confirming Bucket 2 items to BCUC and Interveners

C Exhibits - Intervener Documents



Date Title Document Description
December 18, 2018 C1-1 CATALYST PAPER CORPORATION (CATALYST) - Letter dated December 11, 2018 – Request for Intervener Status by Jouni Martiskainen
January 07, 2019 C1-2 Letter dated January 7, 2019 – Catalyst submitting Information Request No. 1 to BC Hydro
December 18, 2018 C2-1 FORTISBC INC. (FBC) - Letter dated December 12, 2018 – Request for Intervener Status by Doug Slater
December 21, 2018 C2-2 Letter dated December 21, 2018 – FBC Submit right to file Evidence
January 07, 2019 C2-3 Letter dated January 7, 2019 – FBC submitting Information Request No. 1 to BC Hydro
January 25, 2019 C2-4 Letter dated January 25, 2019 – FBC will not file Evidence and will attend Procedural Conference
April 15, 2019 C2-5 Letter dated April 15, 2019 – FBC submission on Four Key Documents
April 24, 2019 C2-6 Letter dated April 24, 2019 – FBC submission on Public Interest
December 18, 2018 C3-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, TOGETHER AGAINST POVERTY SOCIETY”, AND THE TENANT RESOURCE AND ADVISORY CENTRE (BCOAPO) - Letter dated December 12, 2018 – Request for Intervener Status by Leigha Worth and Irina Mis
January 07, 2019 C3-2 Letter dated January 7, 2019 – BCOAPO submitting Information Request No. 1 to BC Hydro
January 25, 2019 C3-3 Letter dated January 25, 2019 – BCOAPO will not file Evidence and will attend Procedural Conference
April 15, 2019 C3-4 Letter dated April 15, 2019 – BCOAPO submission on Four Key Documents
April 26, 2019 C3-5 Letter dated April 26, 2019 – BCOAPO submission on Public Interest

E Exhibits - Letters of Comment

Date Title Document Description
December 19, 2018 E-1 Western Electricity Coordinating Council (WECC) – Letter of Comment dated December 19, 2018

Transcripts

Date Title Document Description
December 20, 2018 Transcript Volume 1 Workshop December 19, 2018
January 31, 2019 Transcript Volume 2 2019-01-30-Procedural Conference Transcript-Vol2

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more