FortisBC Energy Inc. (gas)

FortisBC Energy Inc. Application for Approval of an Operating Agreement between the Corporation of the City of Kamloops and FEI ~ Project No. 1598994

Completed: 2019

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated August 6, 2019 @ 4:23 pm
*_G-207-19 Final Order with Reasons August 29, 2019

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
February 13, 2019 A-1 Letter dated February 13, 2019 - Appointing the Panel for the review of FortisBC Energy Inc.’s (FEI) Application for Approval of an Operating Agreement between the Corporation of the City of Kamloops and FEI
February 13, 2019 A-2 Letter dated February 13, 2019 – Order G-33-19 issuing interim approval of the FEI-Kamloops Operating Agreement
February 14, 2019 A-3 Letter dated February 14, 2019 – Amendment to the Panel for the review of FEI’s Application for Approval of an Operating Agreement between the Corporation of the City of Kamloops and FEI
June 14, 2019 A-4 Letter dated June 14, 2019 – Order G-132-19 establishing the regulatory timetable
July 31, 2019 A-5 Letter dated July 31, 2019 – Order G-176-19 establishing a further regulatory timetable

B Exhibits - Applicant Documents

Date Title Document Description
February 13, 2019 B-1 FORTISBC ENERGY INC. (FEI) Letter dated February 6, 2019 – Application for Approval of an Operating Agreement between the Corporation of the City of Kamloops and FEI
June 04, 2019 B-2 FORTISBC ENERGY INC. (FEI) Letter dated June 3, 2019 – Revised Operating Agreement Based on Terms Approved by British Columbia Utilities Commission (BCUC) Order G-99-19
August 06, 2019 B-3 Letter dated August 6, 2019 – FEI Submitting request to withdraw the requested Application for Approval

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more