FortisBC Energy Inc. (gas)

FortisBC Energy Inc. Complaint filed by Cascadia Energy Ltd., Direct Energy Marketing Ltd and Access Gas Services Inc.

Completed: 2020

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: June 22, 2020 @ 11:13 am
G-210-20 G-210-20 with Reasons for Decision

Arguments/Submissions

Title Document Description
BCGMC Final Argument Final Argument May 15, 2020
FEI Reply Argument Reply Argument May 22, 2020
BCGMC Reply Argument Reply Argument May 28, 2020

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
December 26, 2019 A-1 Letter dated September 26, 2019 – Request to FortisBC Energy Inc. regarding administration of Rate Schedules 22, 23 25 and 27
December 20, 2019 A-2 Letter dated December 20, 2019 – Appointing the Panel for the review of Cascadia Energy, Direct Energy and Access Gas’s complaint
December 20, 2019 A-3 Letter dated December 20, 2019 – BCUC Order G-340-19 establishing the regulatory timetable
December 20, 2019 A-4 Letter dated December 20, 2019 – BCUC Information Request No. 1 to FEI
February 11, 2020 A-5 Letter dated February 11, 2020 – BCUC response regarding conflict of interest
February 24, 2020 A-6 Letter dated February 24, 2020 – BCUC request for FEI’s comments
March 03, 2020 A-7 Letter dated March 3, 2020 – BCUC request for BCGMC’s additional comments
March 16, 2020 A-8 Letter dated March 16, 2020 ¬ Commissioner Loski’s response to BC GMC letter regarding conflict of interest
April 07, 2020 A-9 Letter dated April 7, 2020 – BCUC issuing Order G-82-20 with the regulatory timetable
April 17, 2020 A-10 Letter dated April 17, 2020 – BCUC issuing Order G-87-20 with the regulatory timetable
June 09, 2020 A-11 Letter dated June 9, 2020 – BCUC request for submissions on letter of comment

B Exhibits - Applicant Documents

Date Title Document Description
September 04, 2019 B-1 Cascadia Energy Ltd. (Cascadia), Direct Energy Marketing Limited (Direct), and Access Gas Services Inc. (Access) collectively (BC GMC) - Filed a complaint dated September 4, 2019 requesting the BCUC inquire into FortisBC's administration of Rate Schedules 22, 23, 25 and 27
November 06, 2019 B-2 Letter dated November 6, 2019 – BC GMC Submitting reply to FortisBC Energy Inc. letter dated October 11, 2019
January 29, 2020 B-3 Letter dated January 29, 2020 0 BC GMC Submitting reply to FEI information responses
February 20, 2020 B-4 Letter dated February 20, 2020 – BC GMC Submitting reply to BCUC letter regarding conflict of interest
March 04, 2020 B-5 Letter dated March 4, 2020 – BC GMC Submitting additional comments as requested regarding conflict of interest
April 15, 2020 B-6 Letter dated April 15, 2020 – BC GMC Submitting extension request to file Information Request to FEI
April 24, 2020 B-7 Letter dated April 24, 2020 – BC GMC Submitting Information Request No. 1 to FEI
June 22, 2020 B-8 Letter dated June 22, 2020 – BC GMC Submitting comment on Absolute Letter of Comment

C Exhibits - Intervener Documents

E Exhibits - Letters of Comment

Date Title Document Description
June 05, 2020 E-1 Absolute Energy – Letter of Comment dated June 5, 2020

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more