BC Hydro

British Columbia Hydro and Power Authority - Rate Schedule 1893 – Transmission Service Incremental Energy Rate Alternative Baselines Application

Completed: 2020

Hearing and Other Documents

Title Document Description
*_EXHIBIT LIST Updated: March 31, 2020 @ 5:16 pm
*_G-74-20 Final Order April 2, 2020

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
March 13, 2020 A-1 Letter dated March 13, 2020 – Appointing the Panel for the review of British Columbia Hydro and Power Authority Rate Schedule 1893 ¬Transmission Service Incremental Energy Rate Alternative Baselines Application
March 17, 2020 A-2 CONFIDENTIAL – Letter dated March 17, 2020 – BCUC Confidential Staff Questions No. 1 to BC Hydro
March 19, 2020 A-2-1 Letter dated March 19, 2020 – BCUC issuing Public Redacted Staff Questions No. 1 to BC Hydro

B Exhibits - Applicant Documents

Date Title Document Description
March 13, 2020 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Letter dated March 4, 2020 – submitting an Application for Rate Schedule 1893 – Transmission Service Incremental Energy Rate Alternative Baselines
March 13, 2020 B-1-1 CONFIDENTIAL – Letter dated March 4, 2020 – BC Hydro submitting confidential Rate Schedule 1893 – Transmission Service Incremental Energy Rate Alternative Baselines Application
March 31, 2020 B-2 CONFIDENTIAL – Letter dated March 31, 2020 – BC Hydro submitting confidential responses to BCUC Staff Confidential Information Request No. 1
March 31, 2020 B-2-1 Letter dated March 31, 2020 – BC Hydro submitting responses to BCUC Staff Information Request No. 1

Our Review Process