Creative Energy

2021 Revenue Requirements for the Core Steam System

Completed: 2021

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: October 12, 2021 @ 2:15 pm
Decision and G-310-21A Errata Decision and Order G-310-21A Errata October 29, 2021
Decision and G-349-21 Decision and Order G-349-21 November 30, 2021

Arguments/Submissions

Title Document Description
Creative Energy Final Argument Final Argument May 13, 2021
CEC Final Argument Final Argument May 26, 2021
RCIA Final Argument Final Argument May 26, 2021
BCOAPO Final Argument Final Argument May 26, 2021
Creative Energy Reply Argument Reply Argument June 2, 2021
BCOAPO Supplemental Final Argument Supplemental Final Argument August 30, 2021
CEC Supplemental Final Argument Supplemental Final Argument August 30, 2021
Creative Energy Supplementary Reply Argument Supplementary Reply Argument September 2, 2021

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
December 09, 2020 A-1 Letter dated December 9, 2020 – Appointing the Panel for the review of Creative Energy Vancouver Platforms Inc. 2021 Revenue Requirements Application for the Core Steam System
December 18, 2020 A-2 Letter dated December 18, 2020 – Request to Creative Energy for further information
January 28, 2021 A-3 Exhibit removed and replaced with Exhibit A-3-1
January 28, 2021 A-3-1 Letter dated January 28, 2021 – Amended BCUC Order G-11-21A establishing a regulatory timetable
February 11, 2021 A-4 Letter dated February 11, 2021 – BCUC Information Request No. 1 to Creative Energy
March 22, 2021 A-5 Letter dated March 22, 2021 – BCUC Order G-88-21 establishing a further regulatory timetable
April 15, 2021 A-6 Letter dated April 15, 2021 – BCUC Information Request No. 2 to Creative Energy
April 15, 2021 A-7 CONFIDENTIAL - Letter dated April 15, 2021 – BCUC Confidential Information Request No. 2 to Creative Energy
August 18, 2021 A-8 Letter dated August 18, 2021 – Panel Information Request No. 1 to Creative Energy and Further Regulatory Timetable
February 11, 2021 A2-1 Letter dated February 11, 2021 – BCUC Staff Submitting Aitken Creek Gas Storage ULC, British Columbia Utilities Commission Order G-39-16, Aitken Creek Gas Storage ULC Code of Conduct and Transfer Pricing Policy, Compliance Filing June 30, 2016
February 11, 2021 A2-2 Letter dated February 11, 2021 – BCUC Staff Submitting FortisBC Energy Inc. Application for Approval of Code of Conduct (COC) and Transfer Pricing Policy (TPP) for Affiliated Regulated Businesses Operating in a Non-Natural Monopoly Environment (ARBNNM), June 27, 2014
February 11, 2021 A2-3 Letter dated February 11, 2021 – BCUC Staff Submitting FortisBC Energy Inc., British Columbia Utilities Commission Order No. G-65-15 Compliance Filing – All-Inclusive Code of Conduct and Transfer Pricing Policy, June 30, 2016
February 11, 2021 A2-4 Letter dated February 11, 2021 – BCUC Staff Submitting Pacific Northern Gas Ltd., PNG-West Division – 2018-2019 Revenue Requirements Application, Commission Order G-151-18 Directive 7: Code of Conduct and Transfer Pricing Policy, Compliance Filing January 31, 2019

B Exhibits - Applicant Documents

Date Title Document Description
December 01, 2020 B-1 CREATIVE ENERGY VANCOUVER PLATFORMS INC. (CREATIVE ENERGY) - 2021 Revenue Requirements Application (RRA) for the Core Steam System (Application) dated December 1, 2020
January 06, 2021 B-2 Letter dated January 6, 2021 - Creative Energy response to Panel request for further information
February 26, 2021 B-3 Letter dated February 26, 2021 – Creative Energy submitting Load Forecast Update and Request for Approval of a Steam Rate Increase
March 05, 2021 B-4 Letter dated March 4, 2021 – Creative Energy submitting response to BCUC Information Request No. 1
March 05, 2021 B-4-1 CONFIDENTIAL - Letter dated March 4, 2021 – Creative Energy submitting confidential response to BCUC Information Request No. 1
March 05, 2021 B-5 Letter dated March 4, 2021 – Creative Energy submitting response to CEC Information Request No. 1
March 05, 2021 B-6 Letter dated March 4, 2021 – Creative Energy submitting response to BCOAPO Information Request No. 1
March 05, 2021 B-6-1 CONFIDENTIAL - Letter dated March 4, 2021 – Creative Energy submitting confidential response to BCOAPO Information Request No. 1
March 05, 2021 B-7 Letter dated March 4, 2021 – Creative Energy submitting response to RCIG Information Request No. 1
April 29, 2021 B-8 Letter dated April 29, 2021 – Creative Energy submitting response to BCUC Information Request No. 2
April 29, 2021 B-9 CONFIDENTIAL - Letter dated April 29, 2021 – Creative Energy submitting response to BCUC confidential Information Request No. 2
April 29, 2021 B-10 Letter dated April 29, 2021 – Creative Energy submitting response to BCOAPO Information Request No. 2
April 29, 2021 B-11 Letter dated April 29, 2021 – Creative Energy submitting response to CEC Information Request No. 2
April 29, 2021 B-12 Letter dated April 29, 2021 – Creative Energy submitting response to RCIA Information Request No. 2
August 25, 2021 B-13 Letter dated August 25, 2021 – Creative Energy submitting response to BCUC Panel Information Request No. 1 and supplementary final submission is included in the Information Request responses and will not be filed separately

C Exhibits - Intervener Documents



Date Title Document Description
January 28, 2021 C1-1 RESIDENTIAL CONSUMER INTERVENOR GROUP (RCIG) - Letter dated January 28, 2021 Request to Intervene by Fredrik Ambrosson, Midgard Consulting
February 19, 2021 C1-2 Letter dated February 19, 2021 – RCIG Information Request No. 1 to Creative Energy
April 15, 2021 C1-3 Letter dated April 15, 2021 – RCIG (Now RCIA) Information Request No. 2 to Creative Energy
February 04, 2021 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) - Letter dated February 4, 2021 Request to Intervene by Christopher Weafer, Owen Bird Law Corporation
February 18, 2021 C2-2 Letter dated February 18, 2021 – CEC Information Request No. 1 to Creative Energy
April 15, 2021 C2-3 Letter dated April 15, 2021 – CEC Information Request No. 2 to Creative Energy
February 12, 2021 C3-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION ET AL. (BCOAPO) - Letter dated February 10, 2021 Request for Late Intervener Status by Leigha Worth and Irina Mis
February 18, 2021 C3-2 Letter dated February 18, 2021 – BCOAPO Information Request No. 1 to Creative Energy
April 15, 2021 C3-3 Letter dated April 15, 2021 – BCOAPO Information Request No. 2 to Creative Energy

D Exhibits — Interested Party Documents

Date Title Document Description
October 06, 2021 D-1 Cadillac Fairview – Submission dated October 6, 2021 Request for Interested Party Status by L. Tummonds

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more