BC Hydro

FortisBC and British Columbia Hydro and Power Authority August 19, 2005 Joint Application for Exemptions under Section 88(3) of the Utilities Commission Act regarding an Amended and Re-stated Canal Plant Agreement and the related FortisBC Entitlement Adjustment Agreement ~ Project No. 3698404

Completed: 2006

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: February 1, 2006 @ 3:49 pm
*_Distribution List Updated: April 27, 2006 @ 12:22 pm
*_Fax-Email-Mail List Updated: April 27, 2006 @ 12:22 pm
G-41-06 & Reasons for Decision Order No. G-41-06 & Reasons for Decision

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
August 24, 2005 A-1 Letter dated August 23, 2005 requesting comments on the BC Hydro and FortisBC filed a joint application requesting that the Commission grant an exemption for FortisBC and BC Hydro from all provisions of the Act in respect to the Canal Plant Agreement, the FortisBC Entitlement Adjustment Agreement, and the Canal Plant Agreement Subagreement
September 30, 2005 A-2 Letter dated September 30, 2005 – Order G-95- 05 Establishing Regulatory Timetable
October 21, 2005 A-3 Letter dated October 21, 2005 submitting Commission Information Reqeust No. 1 to BC Hydro and FortisBC
February 01, 2006 A-4 Letter dated January 24, 2006 to the Attorney General requesting approval to issue an exemption order to BC Hydro and FortisBC

B Exhibits - Applicant Documents

Date Title Document Description
August 24, 2005 B-1 August 19, 2005 Joint Exemption Application by FortisBC and British Columbia Hydro and Power Authority regarding an Amended and Re-stated Canal Plant Agreement and the related FortisBC Entitlement Adjustment Agreement
August 24, 2005 B-2 An Invitation to A Public Workshop Explaining the Canal Plant Agreement - 2005
September 16, 2005 B-3 Letter dated September 16, 2005 from FortisBC Inc. filing a list of attendees as well as a copy of the Workshop presentation
September 22, 2005 B-4 British Columbia Transmission Corporation Application dated August 31, 2005
September 22, 2005 B-5 BC Hydro Letter dated September 22, 2005 - Comments
September 23, 2005 B-6 FortisBC Letter dated September 22, 2005 - Comments
September 30, 2005 B-7 FortisBC Letter dated September 30, 2005 – Erratum to Application
November 04, 2005 B-8 BC Hydro Letter dated November 4, 2005 – Joint responses from BC Hydro and FortisBC to Commission Information Request No. 1
November 04, 2005 B-9 Letter dated November 4, 2005 – Information Responses to IMEU
November 04, 2005 B-10 Letter dated November 4, 2005 – Information Responses to BCOAPO
November 04, 2005 B-11 Letter dated November 4, 2005 – Information Responses to Alan Wait
November 04, 2005 B-12 BC Hydro Letter dated November 4, 2005 – Information Responses to BCOAPO
November 18, 2005 B-12A BC Hydro letter dated November 18,2005 filing a revised response to BCOAPO Information Request 1.6.0(g)
November 25, 2005 B-13 Joint Reply Argument dated November 25, 2005 from BC Hydro and FortisBC

C Exhibits - Intervener Documents



Date Title Document Description
September 12, 2005 C1-1 WAIT, ALAN – Web registration dated September 8, 2005 requesting Intervenor Status
September 22, 2005 C1-2 E-Mail dated September 22, 2005 requesting Oral Public Hearing
September 23, 2005 C1-3 E-Mail dated September 22, 2005 reply to FortisBC September 22, 2005 letter
October 24, 2005 C1-4 Letter dated October 21, 2005 submitting Information Request No. 1
November 08, 2005 C1-5 E-mail dated November 8, 2005 – Comments regarding exemption request
September 15, 2005 C2-1 BCOAPO – E-mail registration dated September 15, 2005 requesting Intervenor Status from Jim Quail, BC Public Interest Advocacy Centre
September 16, 2005 C2-2 Letter dated September 16, 2005 filing the submissions of BCOAPO et al. concerning the appropriate regulatory process
October 21, 2005 C2-3 Letter dated October 18, 2005 – Information Requests to FortisBC
October 21, 2005 C2-4 Letter dated October 18, 2005 – Information Requests to BC Hydro
November 17, 2005 C2-5 Letter dated November 17, 2005 – Submission components of contractual arrangements
October 12, 2005 C3-1 DEMOCRATIC REFORM BC CHILLIWACK/SUMAS – Web registration dated October 11, 2005 from Brian Downey
October 18, 2005 C3-2 E-mail dated October 18, 2005 from Brian Downey – Submission
November 01, 2005 C3-3 E-mail dated November 1, 2005 – Support Province Intervention
October 12, 2005 C4-1 COLUMBIA POWER CORPORATION (CPC), BRILLIANT POWER CORPORATION (BPC), BRILLIANT EXPANSION POWER CORPORATION (BEPC) AND WANETA EXPANSION POWER CORPORATION (WEPC) – Letter dated October 7, 2005 requesting Intervenor Status from David Bursey, Bull Housser & Tupper
November 18, 2005 C4-2 E-mail dated November 18, 2005 - Comments
October 14, 2005 C5-1 I.M.E.U. – E-mail dated October 14, 2005 – Request for Intervenor Status
October 25, 2005 C5-2 Letter dated October 24, 2005 – Information Requests
October 14, 2005 C6-1 TECK COMINCO – Web registration dated October 14, 2005 – Request for Intervenor Status
November 21, 2005 C6-2 Submission dated November 18, 2005 from Teck Cominco
November 01, 2005 C7-1 MINISTRY OF ATTORNEY GENERAL - Letter dated October 31, 2005 requesting Intervenor Status from Christopher H. Jones, Resource, Environmental & Land Law Group also including Peter Ostergaard, ADM, Ministry of Energy, Mines and Petroleum Resources
November 18, 2005 C7-2 Facsimile dated November 18, 2005 – Submissions regarding Application

D Exhibits — Interested Party Documents

Date Title Document Description
November 25, 2005 D-1 British Columbia Transmission Corporation Letter dated November 25, 2005 filing Final Reply

E Exhibits - Letters of Comment

Date Title Document Description
September 22, 2005 E-1 E-mail dated September 22, 2005 from TeckCominco - Comments
September 22, 2005 E-1A E-mail dated September 23, 2005 from TeckCominco – Typographical error in previous submission
September 23, 2005 E-2 E-mail dated September 22, 2005 – Comments from David Bursey, Bull Housser & Tupper on behalf of Brilliant Power Corporation, Brilliant Expansion Power Corporation and Waneta Expansion Power Corporation
September 28, 2005 E-3 E-mail dated September 27, 2005 - Comment from Rod Carle, IMEU regarding Regulatory Process
November 21, 2005 E-4 Submission dated November 18, 2005 from Nelson Hydro (submitted by Russell Leslie, General Manager) commenting on the BC Hydro and FortisBC Amended and Re-stated Canal Plant Agreement and the related FortisBC Entitlement Adjustment Agreement

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more