FortisBC Inc. (electric)

FortiBC Inc. 2006 Revenue Requirements and Establishment of a Multi-Year Performance Based Regulation Mechanism ~ Project No. 3698410

Completed: 2006

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: August 10, 2006 @ 10:26 am
Transcript - Volume 1 Pre-Hearing Conference - February 10 2006
*_Distribution List Updated: April 27, 2006 at 2:26 pm
*_Fax Email Mail List Updated: April 27, 2006 at 2:27 pm
Proposed Negotiated Settlement
Status Report Updates - May 12 2006
Order G-58-06 - May 23 2006

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
December 07, 2005 A-1 Letter dated November 7, 2005 and Order No. G-130-05 establishing the Annual Review and Regulatory Timetable
January 20, 2006 A-2 Letter dated January 20, 2006 issuing draft Pre-hearing Conference Issues List, draft Regulatory Timetables and requesting FortisBC to file historical information and continuity schedules
February 16, 2006 A-3 Letter dated February 15, 2006 and Order No. G-13-06 amending the Regulatory Timetable set out in Order No. G-130-05
February 20, 2006 A-4 Letter dated February 20, 2006 and Information Request No. 1 to FortisBC
March 03, 2006 A-5 Letter dated March 1, 2006 advising participants of the time and location for the Negotiated Settlement Process

B Exhibits - Applicant Documents

Date Title Document Description
November 24, 2005 B-1 FortisBC Inc. November 24, 2005 Application for approval of its 2006 Revenue Requirements and establishment of a Multi-Year Performance Based Regulation Mechanism
February 06, 2006 B-2 Letter dated February 6, 2006 responding to BCUC’s request for continuity schedules and information (Exhibit A-2)
February 14, 2006 B-3 2005 Annual Review Presentations on February 9, 2006 in Kelowna BC
February 14, 2006 B-4 2006 Revenue Requirements Presentations on February 9, 2006 in Kelowna, BC
February 14, 2006 B-5 FortisBC PBR Presentations on February 9 and February 10, 2006 in Kelowna
February 14, 2006 B-6 Errata Revenue Requirements dated February 9, 2006
February 14, 2006 B-7 Letter dated February 14, 2006 filing 2006 Revenue Requirements – Update
February 14, 2006 B-8 Letter dated February 14, 2006 filing responses to Information Requests made at the 2006 Revenue Requirements Workshop
February 15, 2006 B-9 Letter dated February 15, 2006 filing 2006 Capital Expenditures Plan – Vehicle Lease to Ownership Conversion and 2006 Revenue Requirements (Order No. G-8-06)
February 21, 2006 B-10 Letter dated February 21, 2006 noting no Intervenor responses received
February 24, 2006 B-11 Letter dated February 21, 2006 filing notice of Technical Committees and inquiry of Intervenors’ participation
March 08, 2006 B-12 Letter dated March 8, 2006 filing responses to Information Request from Commission and Registered Intervenors
March 23, 2006 B-13 Letter dated March 22, 2006 filing the Demand Side Management Technical Committee Report, Power Purchase Expense Technical Committee Report and Load Forecast Technical Committees (Order No. G-13-06)
April 11, 2006 B-14 Letter dated April 11, 2006 filing 2006 Supplemental Information and Schedules

C Exhibits - Intervener Documents



Date Title Document Description
November 29, 2005 C1-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION ET AL. (BCOAPO) – Notice of Intervention dated November 29, 2005 from Sarah Y. Khan, BC Public Interest Advocacy Centre
January 09, 2006 C1-2 BCOAPO Notice of Confirmation of Intervention dated January 5, 2006
February 22, 2006 C1-3 Letter dated February 22, 2006, filing Information Request No. 1 to FortisBC
December 14, 2005 C2-1 KAROW, HANS – Notice of Intervention dated December 12, 2005
December 14, 2005 C3-1 SLACK, BURYL – Notice of Intervention dated December 14, 2005
December 15, 2005 C4-1 NATURAL RESOURCE INDUSTRIES AND HEDLEY IMPROVEMENT DISTRICT – Notice of Intervention dated December 15, 2005 from Richard Tarnoff
January 23, 2006 C4-2 TARNOFF, RICHARD – Email dated January 21, 2006 response to draft issues and request for Elenchus Research Associates to be added to issues list, PBR review under the Performance Based Regulation Mechanism
February 23, 2006 C4-3 Email dated February 22, 2006 filing Information Request No. 1
January 09, 2006 C5-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CECBC) – Notice of Intervention dated January 5, 2006 from Christopher P. Weafer
February 22, 2006 C5-2 Letter dated February 22, 2006 filing Information Request No. 1 to FortisBC
January 09, 2006 C6-1 INTERIOR MUNICIPAL ELECTRICAL UTILITIES (IMEU) – Notice of Intervention dated January 5, 2006 from Rod E. Carle, Chairman
February 22, 2006 C6-2 Letter dated February 22, 2006 filing Information Request No. 1 to FortisBC
January 12, 2006 C7-1 CITY OF CASTLEGAR – Letter dated January 5, 2006 objecting to the proposed 5.9% power rate increase from Mayor Lawrence Chernoff
February 21, 2006 C8-1 Web registration Notice of Intervention dated January 22, 2006
February 22, 2006 C8-2 Letter dated February 22, 2006 filing Information Request No. 1 to FortisBC

D Exhibits — Interested Party Documents

Date Title Document Description
January 25, 2006 D-1 Email dated January 24, 2006 requesting Notice of Interested Party status

E Exhibits - Letters of Comment

Date Title Document Description
February 06, 2006 E-1 Letter of Comment dated January 26, 2006 received from the City of Greenwood
February 06, 2006 E-2 Letter of Comment dated January 28, 2006 received from R.V. MacLeod
February 22, 2006 E-3 Letter of Comment dated February 15, 2006 received from Mayor Libby Nelson, Corporation of the Village of Fruitvale
March 13, 2006 E-4 Letter of Comment dated March 1, 2006 received from Mayor Ann Henderson, Corporation of the Village of Salmo

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more