The BCUC posts upcoming deadlines for proceedings in progress.

All upcoming filing deadlines are listed below by entity and proceeding name.

Entity Proceeding Regulatory Item Due Date Order / Letter
Corix UBC Neighbourhood District Energy System 2025 to 2027 Revenue Requirement and Rates Corix responses to IR No. 1 2025-04-17 G-10-25
Corix UBC Neighbourhood District Energy System 2025 to 2027 Revenue Requirement and Rates BCUC notice of remaining regulatory timetable 2025-04-30 G-10-25
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project BCUC IR No. 6 to FEI 2025-04-24 G-324-24
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project Intervener IR No. 6 to FEI 2025-05-01 G-324-24
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project FEI responses to BCUC and Intervener IR No. 6 2025-05-22 G-324-24
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project Letters of comment deadline 2025-05-29 G-324-24
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project FEI final argument 2025-06-19 G-324-24
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project Intervener final argument 2025-07-10 G-324-24
FortisBC Energy Inc. (gas) Certificate of Public Convenience and Necessity for the Tilbury Liquefied Natural Gas Storage Expansion Project FEI reply argument 2025-07-31 G-324-24
Creative Energy 2024 to 2027 Rates for Heating at South Downtown TES Creative Energy final argument 2025-05-01 G-43-25
Creative Energy 2024 to 2027 Rates for Heating at South Downtown TES Intervener final argument 2025-05-15 G-43-25
Creative Energy 2024 to 2027 Rates for Heating at South Downtown TES Creative Energy reply argument 2025-05-30 G-43-25
FortisBC Inc. (electric) 2025 Cost of Service Allocation and Revenue Rebalancing FBC responses to IR No. 1 2025-05-15 G-60-25
FortisBC Inc. (electric) 2025 Cost of Service Allocation and Revenue Rebalancing FBC final argument 2025-05-29 G-60-25
FortisBC Inc. (electric) 2025 Cost of Service Allocation and Revenue Rebalancing Intervener final argument 2025-06-12 G-60-25
FortisBC Inc. (electric) 2025 Cost of Service Allocation and Revenue Rebalancing FBC reply argument 2025-06-26 G-60-25
Pacific Northern Gas Certificate of Public Convenience and Necessity for Construction of the Ridley Island Energy Export Facility Interconnection Project Letters of comment deadline 2025-04-23 G-63-25
Pacific Northern Gas Certificate of Public Convenience and Necessity for Construction of the Ridley Island Energy Export Facility Interconnection Project PNG responses to letters of comment (if any) and final argument 2025-04-30 G-63-25
Oakridge Energy Reconsideration and Variance of Order G-342-24 Oakridge Energy files an evidentiary update 2025-04-29 G-71-25
Oakridge Energy Reconsideration and Variance of Order G-342-24 BCUC Information Request (IR) No. 1 to Oakridge Energy 2025-05-15 G-71-25
Oakridge Energy Reconsideration and Variance of Order G-342-24 Oakridge Energy responses to BCUC IR No. 1 2025-05-30 G-71-25
Oakridge Energy Reconsideration and Variance of Order G-342-24 Letters of comment deadline 2025-06-05 G-71-25
Oakridge Energy Reconsideration and Variance of Order G-342-24 Oakridge Energy final argument and reply to letters of comment 2025-06-12 G-71-25
BC Hydro 2024 Call for Power Electricity Purchase Agreements BC Hydro responses to BCUC IR No. 1 2025-04-24 G-72-25
BC Hydro 2024 Call for Power Electricity Purchase Agreements Letters of comment deadline 2025-05-01 G-72-25
BC Hydro 2024 Call for Power Electricity Purchase Agreements BC Hydro responses to letters of comment (if any) and final argument 2025-05-15 G-72-25
Plateau Pipe Line Abandonment of Service as a Common Carrier on the Northern Segment of the Western Pipeline System Plateau reply argument 2025-04-17 G-74-25
Nelson Hydro 2025 Revenue Requirements Nelson Hydro final argument and responses to letters of comment 2025-04-30 G-75-25
BC Hydro Terms of Use of Municipal Land in the City of Surrey BC Hydro reply argument 2025-04-28 G-82-25
ICBC Rate Design Compliance Report Extension Request Letter of comment deadline 2025-04-22 G-87-25
ICBC Rate Design Compliance Report Extension Request ICBC final argument and reply to letters of comment (if any) 2025-04-28 G-87-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project BC Hydro to file evidentiary update for the Strathcona Project 2025-05-30 G-90-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project BCUC information request (IR) No. 4 to BC Hydro 2025-06-19 G-90-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Intervener IR No. 4 to BC Hydro 2025-06-26 G-90-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project BC Hydro responses to BCUC and Intervener IR No. 4 2025-07-11 G-90-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project BC Hydro final argument on the Strathcona Project 2025-07-21 G-90-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Intervener final argument on the Strathcona Project 2025-08-05 G-90-25
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project BC Hydro reply argument on the Strathcona Project 2025-08-14 G-90-25
Creative Energy 2025 Core Steam Revenue Requirements Creative Energy final argument 2025-04-23 G-91-25
Creative Energy 2025 Core Steam Revenue Requirements Intervener final argument 2025-05-05 G-91-25
Creative Energy 2025 Core Steam Revenue Requirements Creative Energy reply argument 2025-05-15 G-91-25
Creative Energy 2024 Long-Term Resource Plan Creative Energy final argument 2025-05-01 G-93-25
Creative Energy 2024 Long-Term Resource Plan Intervener final argument 2025-05-15 G-93-25
Creative Energy 2024 Long-Term Resource Plan Creative Energy reply argument 2025-05-29 G-93-25
BC Hydro Fiscal 2024 and 2025 Transmission Service Rate Customer Baseline Loads BC Hydro to provide notice 2025-04-17 G-95-25
BC Hydro Fiscal 2024 and 2025 Transmission Service Rate Customer Baseline Loads BC Hydro confirmation of compliance with notice requirements 2025-04-22 G-95-25
BC Hydro Fiscal 2024 and 2025 Transmission Service Rate Customer Baseline Loads Letters of comment deadline 2025-05-08 G-95-25
BC Hydro Fiscal 2024 and 2025 Transmission Service Rate Customer Baseline Loads BC Hydro responses to Letters of comment 2025-05-15 G-95-25
BC Utilities Commission Review of Resource Planning Guidelines Letters of comment 2025-05-15 G-98-25
Pacific Northern Gas 2025 to 2027 Energy Conservation and Innovation Portfolio Funding PNG responses to Panel IR No. 1 2025-04-30 G-99-25
Pacific Northern Gas 2025 to 2027 Energy Conservation and Innovation Portfolio Funding PNG final argument 2025-05-08 G-99-25
Pacific Northern Gas 2025 to 2027 Energy Conservation and Innovation Portfolio Funding Intervener final argument 2025-05-22 G-99-25
Pacific Northern Gas 2025 to 2027 Energy Conservation and Innovation Portfolio Funding PNG reply argument 2025-06-12 G-99-25
BC Hydro Mandatory Reliability Standards Planning Coordinator Assessment Report Response to IR No. 1 2025-04-30 R-3-25