FortisBC Inc. (electric)

Rate Design and Rates for Electric Vehicle Direct Current Fast Charging Service

Completed: 2021

Hearing and Other Documents

Title Document Description
Exhibit List Updated: September 24, 2021 @ 2:01 pm
Decision and Order G-341-21 Decision and Order G-341-21 November 24, 2021
Clarification on Decision and Order G-341-21 Letter dated November 29, 2021 FEI Clarifying Electricity Input Cost in Decision and Order G-341-21
Order G-350-21 RS 96 approved on a permanent basis as per Order G-350-21 dated November 30, 2021

Arguments/Submissions

Title Document Description
FBC Final Argument Final Argument March 16, 2021
Flintoff Final Argument Final Argument March 30, 2021
ChargePoint Final Argument Final Argument March 30, 2021
BCSEA-VEVA Final Argument Final Argument March 30, 2021
CEC Final Argument Final Argument March 30, 2021
BC Hydro Final Argument Final Argument March 30, 2021
BCOAPO Final Argument Final Argument March 30, 2021
FBC Supplemental Argument Supplemental Argument April 6, 2021
BCSEA-VEVA Supplemental Argument Supplemental Argument April 8, 2021
Flintoff Supplemental Argument Supplemental Argument April 12, 2021
BC Hydro Supplemental Argument Supplemental Argument April 13, 2021
CEC Supplementary Final Argument Supplemental Argument April 13, 2021
ChargePoint Supplemental Argument Supplemental Argument April 13, 2021
FBC Reply Argument Reply Argument April 13, 2021
BCOAPO Supplementary Argument Supplementary Argument April 13, 2021
FBC Supplemental Reply Argument Supplemental Reply Argument April 20, 2021

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
January 10, 2018 A-1 Letter dated January 10, 2018 - Appointing the Panel for the review of the FortisBC Inc. Rate Design and Rates for Electric Vehicle (EV) Direct Current Fast Charging (DCFC) Service Application
January 12, 2018 A-2 Letter dated January 12, 2018 – Commission Order G-9-18 approving interim rates and adjourning the proceeding
July 31, 2019 A-3 Letter dated July 31, 2019 – BCUC request FBC submission on further process
August 22, 2019 A-4 Letter dated August 22, 2019 – BCUC response to FBC submission on further process (Exhibit B-2)
July 10, 2020 A-5 Letter dated July 10, 2020 – Panel Amendment
July 10, 2020 A-6 Letter dated July 10, 2020 – BCUC Order G-183-20 establishing the regulatory timetable to restart the proceeding
August 28, 2020 A-7 Letter dated August 28, 2020 —BCUC Order G-223-20 establishing the regulatory timetable for the review of the Application
October 13, 2020 A-8 Letter dated October 13, 2020 – BCUC Order G-254-20 establishing an amended regulatory timetable
October 29, 2020 A-9 Letter dated October 29, 2020 — BCUC Information Request No. 1 to FBC
December 18, 2020 A-10 Letter dated December 18, 2020 – Request for Submissions on Further Process
January 28, 2021 A-11 Letter dated January 28, 2021 – BCUC Order G-33-21 establishing a further regulatory timetable
February 11, 2021 A-12 Letter dated February 11, 2021 – BCUC Information Request No. 2 to FBC
February 24, 2021 A-13 Letter dated February 24, 2021 – Request to address the legal interpretations of GGRR as part of final arguments
March 01, 2021 A-14 Letter dated March 1, 2021 – BCUC Order G-58-21 amending the regulatory timetable
March 23, 2021 A-15 Letter dated March 23, 2021 – BCUC Order G-90-21 establishing the regulatory timetable for supplemental arguments
May 10, 2021 A-16 Letter dated May 10, 2021 – BCUC notice to parties regarding the oral submissions’ session
May 26, 2021 A-17 Letter dated May 26, 2021 – BCUC Request for comments on the summary of the EV fast charging service in the FBC area
July 14, 2021 A-18 Letter dated July 14 – BCUC Order G-215-21 with Reasons for Decision and establishing the regulatory timetable for submissions on proceeding adjournment
September 01, 2021 A-19 Letter dated September 1, 2021 – BCUC response to submissions regarding proceeding adjournment

B Exhibits - Applicant Documents

Date Title Document Description
December 22, 2017 B-1 FORTISBC INC. (FBC) Letter dated December 22, 2017 - Rate Design and Rates for Electric Vehicle (EV) Direct Current Fast Charging (DCFC) Service Application
August 20, 2019 B-2 Letter dated August 20, 2019 – FBC Submission on Further Process
June 30, 2020 B-3 Letter dated June 30, 2020 – FBC Submission on Process Restart
July 28, 2020 B-4 Letter dated July 28, 2020 – FBC Clarification on Application
September 30, 2020 B-5 Letter dated September 30, 2020 – FBC Revision on Application
October 16, 2020 B-6 CONFIDENTIAL - Letter dated October 16, 2020 – FBC Submitting separately Confidential Financial Models to the Application
November 19, 2020 B-7 Letter dated November 19, 2020 - FBC submitting responses to BCUC Information Request No. 1
November 19, 2020 B-8 CONFIDENTIAL - Letter dated November 19, 2020 – FBC submitting responses to BCOAPO Information Request No. 1, Questions 11.4, 11.5 and 11.6
November 19, 2020 B-8-1 REDACTED - Letter dated November 19, 2020 – FBC submitting redacted responses to BCOAPO Information Request No. 1
November 19, 2020 B-9 Letter dated November 19, 2020 – FBC submitting responses to BCSEA Information Request No. 1
November 19, 2020 B-10 Letter dated November 19, 2020 – FBC submitting responses to CEC Information Request No. 1
November 19, 2020 B-11 Letter dated November 19, 2020 – FBC submitting responses to ChargePoint Information Request No. 1
November 19, 2020 B-12 Letter dated November 19, 2020 – FBC submitting responses to Flintoff Information Request No. 1
January 08, 2021 B-13 Letter dated January 8, 2021 – FBC submitting Proposal Regarding Accessibility of Stations
January 20, 2021 B-14 Letter dated January 20, 2021 – FBC submitting comments on further process
February 24, 2021 B-15 Letter dated February 24, 2021 – FBC submitting amendment to the regulatory timetable
February 25, 2021 B-16 Letter dated February 25, 2021 – FBC submitting responses to BCUC Information Request No. 2
February 25, 2021 B-17 Letter dated February 25, 2021 – FBC submitting responses to BCOAPO Information Request No. 2
February 25, 2021 B-18 Letter dated February 25, 2021 – FBC submitting responses to BCSEA-VEVA Information Request No. 2
February 25, 2021 B-19 Letter dated February 25, 2021 – FBC submitting responses to CEC Information Request No. 2
February 25, 2021 B-20 Letter dated February 25, 2021 – FBC submitting responses to Flintoff Information Request No. 2
June 02, 2021 B-21 Letter dated June 2, 2021 – FBC submitting comments on the Summary of the EV Fast Charging Service in FBC Service Area
August 03, 2021 B-22 Letter dated August 3, 2021 – FBC submission regarding Adjournment and Interim Rates
August 24, 2021 B-23 Letter dated August 24, 2021 – FBC submitting reply on proceeding adjournment
September 24, 2021 B-24 Letter dated September 24, 2021 – FBC submitting tax issues at the stations

C Exhibits - Intervener Documents



Date Title Document Description
October 16, 2020 C9-1 ALLIANCE FOR TRANSPORTATION ELECTRIFICATION (ATE OR ALLIANCE) - Letter dated October 16, 2020 Request to Intervene by Michael Krauthamer
August 12, 2021 C8-5 Letter dated August 12, 2021 – BCOAPO submission regarding Adjournment and Interim Rates
February 12, 2021 C8-4 Letter dated February 11, 2021 – BCOAPO Information Request No. 2 to FBC
January 13, 2021 C8-3 Letter dated January 13, 2021 – BCOAPO submitting comments on further process
November 05, 2020 C8-2 Letter dated November 5, 2020 – BCOAPO submitting Information Request No. 1 to FBC
July 31, 2020 C8-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, AND TENANT RESOURCE & ADVISORY CENTRE (BCOAPO ET AL) - Letter dated July 31, 2020 - Request for Intervener Status by Leigha Worth
July 30, 2020 C7-1 DONOVAN WHISTLER (WHISTLER) Letter dated July 30, 2020 Request to Intervene
May 26, 2021 C6-3 Letter dated May 26, 2021 – ChargePoint submission regarding Oral Submission and Argument
November 05, 2020 C6-2 Letter dated November 5, 2020 – ChargePoint submitting Information Request No. 1 to FBC
July 31, 2020 C6-1 CHARGEPOINT (CHARGEPOINT) Letter dated July 30, 2020 Request to Intervene by Suzanne Goldberg
August 12, 2021 C5-5 Letter dated August 12, 2021 – CEC submission regarding Adjournment and Interim Rates
February 11, 2021 C5-4 Letter dated February 11, 2021 – CEC submitting Information Request No. 2 to FBC
January 13, 2021 C5-3 Letter dated January 13, 2021 – CEC submitting comments on further process
November 05, 2020 C5-2 Letter dated November 5, 2020 – CEC submitting Information Request No. 1 to FBC
July 30, 2020 C5-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) Letter dated July 30, 2020 Request to Intervene by Christopher Weafer
August 05, 2021 C4-8 Letter dated August 5, 2021 – BCSEA-Vancouver EVA submission regarding Adjournment and Interim Rates
May 30, 2021 C4-7 Letter dated May 30, 2021 – BCSEA-Vancouver EVA submitting response on the summary of the EV fast charging service in the FBC area
February 11, 2021 C4-6 Letter dated February 11, 2021 – BCSEA-Vancouver EVA submitting Information Request No. 2 to FBC
January 12, 2021 C4-5 Letter dated January 12, 2021 – BCSEA-Vancouver EVA Request submitting comments on further process
December 11, 2020 C4-4 Letter dated December 11, 2020 – BCSEA-Vancouver EVA Request for opportunity for file intervener evidence
November 05, 2020 C4-3 Letter dated November 5, 2020 – BCSEA-Vancouver EVA submitting Information Request No. 1 to FBC
November 04, 2020 C4-2 Letter dated November 4, 2020 – BCSEA Request to also represent Vancouver Electric Vehicle Association (Vancouver EVA)
July 22, 2020 C4-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) - Letter dated July 22, 2020 Request to Intervene by Thomas Hackney
August 10, 2021 C3-6 Letter dated August 10, 2021 – Flintoff submission regarding Adjournment and Interim Rates
June 02, 2021 C3-5 Letter dated June 2, 2021 – Flintoff submitting comments on the Summary of the EV Fast Charging Service in FBC Service Area
May 26, 2021 C3-4 Letter dated May 26, 2021 – Flintoff submission regarding Oral Submission and Argument
February 10, 2021 C3-3 Letter dated January 10, 2021 – Flintoff submitting Information Request No. 2 to FBC
November 05, 2020 C3-2 Letter dated November 5, 2020 – Flintoff submitting Information Request No. 1 to FBC
July 22, 2020 C3-1 DON FLINTOFF (FLINTOFF) - Letter dated July 22, 2020 Request to Intervene
May 26, 2021 C2-2 Letter dated May 26, 2021 – BC Hydro submission regarding Oral Submission and Argument
July 13, 2020 C2-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) - Letter dated July 13, 2020 Request to Intervene by Fred James
June 29, 2020 C1-1 VICTORIA EV ASSOCIATION (VICTORIA EVA) – Letter dated June 29, 2020 – Request for Intervener Status by Jim Hindson

D Exhibits — Interested Party Documents

Date Title Document Description
August 02, 2019 D-1 THOMAS, LYLE – August 2, 2019 Request for Interested Party Status on behalf of the Town of Princeton
August 27, 2019 D-2 NOBLE, COLIN – August 27, 2019 Request for Interested Party Status
September 06, 2019 D-3 TSE, KEVIN – September 6, 2019 Request for Interested Party Status on behalf of the Internat Energy Solutions Canada
July 14, 2020 D-2-1 Noble, C. - Letter of Comment dated July 14, 2020
September 30, 2020 D-4-1 Cownden, R. - Letter of Comment dated September 30, 2020
October 01, 2020 D-2-2 Noble, C. - Letter of Comment dated October 1, 2020
October 15, 2020 D-4 COWNDEN, RYAN – October 15, 2020 Request for Interested Party Status
July 30, 2021 D-4-2 Cownden, R. - Letter of Comment dated July 30, 2021

E Exhibits - Letters of Comment

Date Title Document Description
October 05, 2020 E-2 Stein, C. - Letter of Comment dated October 5, 2020
October 09, 2020 E-1 Garnett, B. – Letter of Comment dated October 9, 2020

Transcripts

Date Title Document Description
May 27, 2021 Transcript Volume 1 Web-Based Oral Submissions May 27 2021

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more