FortisBC Energy Inc. (gas)

FortisBC Energy Inc. Application for Use of Lands under Sections 32 and 33 of the Utilities Commission Act in the City of Coquitlam for the Lower Mainland Intermediate Pressure System Upgrade Projects ~ Project No.1598963

Completed: 2019

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: December 6, 2018 @ 10:02 am
*_G-80-19 with Reasons G-80-19 with Reasons for Decision April 15, 2019

Arguments/Submissions

Title Document Description
City of Coquitlam Final Argument Final Argument dated December 19, 2018
FEI Final Argument Final Argument dated December 19, 2018
CEC Final Argument Final Argument dated January 10, 2019
FEI Reply Argument Reply Argument dated January 17, 2019
City of Coquitlam Reply Argument Reply Argument dated January 17, 2019

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
July 10, 2018 A-1 Letter dated July 10, 2018 - Appointing the Panel for the review of FEI of Lands under Sections 32 and 33 of the Utilities Commission Act in the City of Coquitlam for the Lower Mainland Intermediate Pressure System Upgrade (LMIPSU) Projects
July 11, 2018 A-2 Letter dated July 11, 2018 – Request for Submission regarding the Application
August 01, 2018 A-3 Letter dated August 1, 2018 – Replaced by A-4
August 01, 2018 A-4 Letter dated August 1, 2018 – Order G-144-18A Regulatory Timetable
August 08, 2018 A-5 Letter dated August 8, 2018 – Order G-144-18A Reasons for Decision
August 10, 2018 A-6 Letter dated August 10, 2018 – BCUC Information Request No. 1 to FEI
August 10, 2018 A-7 Letter dated August 10, 2018 – BCUC Information Request No.1 to the City of Coquitlam
August 22, 2018 A-8 Letter dated August 22, 2018 – Order G-158-18 Procedural Order
September 12, 2018 A-9 Letter dated September 12, 2018 – BCUC requesting for submissions regarding Phase Two
October 04, 2018 A-10 Letter dated October 4, 2018 – Order G-190-18 establishing Regulatory Timetable for Phase Two
November 15, 2018 A-11 Letter dated November 15, 2018 – BCUC Information Request No. 2 to the City of Coquitlam
November 15, 2018 A-12 Letter dated November 15, 2018 – BCUC Information Request No. 2 to FEI

B Exhibits - Applicant Documents

Date Title Document Description
July 10, 2018 B-1 FORTISBC ENERGY INC. (FEI) – Letter dated June28, 2018 - Application for Use of Lands under Sections 32 and 33 of the Utilities Commission Act in the City of Coquitlam for the Lower Mainland Intermediate Pressure System Upgrade (LMIPSU) Projects
July 10, 2018 B-1-1 Letter dated June28, 2018 – Confidential Attachments to the Application
July 24, 2018 B-2 Letter dated July 24, 2018 – Reply to request for submissions on process
August 03, 2018 B-3 Letter dated August 3, 2018 – Submission of Supplementary Evidence on Phase One Issues
August 10, 2018 B-4 Letter dated August 3, 2018 – FEI filing of redactions in City’s April 6, 2018 responses
August 10, 2018 B-5 Letter dated August 10, 2018 – FEI Information Request No. 1 on the City’s Submissions
August 17, 2018 B-6 Letter dated August 17, 2018 – FEI Responses to BCUC Information Request No. 1
August 17, 2018 B-7 Letter dated August 17, 2018 – FEI and City Final Agreed Terms and Conditions
August 22, 2018 B-8 Letter dated August 22, 2018 – FEI Final Submission on Phase One Issues
September 05, 2018 B-9 Letter dated September 5, 2018 – FEI notice of filing additional evidence for Phase Two
September 20, 2018 B-10 Letter dated September 20, 2018 – FEI Submission Regarding Issues for Phase Two
October 10, 2018 B-11 Letter dated October 10, 2018 – FEI Comments regarding filing evidence for Phase Two
October 31, 2018 B-12 Letter dated October 31, 2018 – FEI filing evidence on Phase Two issues
November 15, 2018 B-13 Letter dated November 15, 2018 – FEI submitting Information Request No. 1 to City on Phase Two evidence
December 06, 2018 B-14 Letter dated December 5, 2018 – FEI submitting responses to BCUC Information Request No. 2
December 06, 2018 B-15 Letter dated December 5, 2018 – FEI submitting responses to CEC Phase Two Information Request No. 1
December 06, 2018 B-16 Letter dated December 5, 2018 – FEI submitting responses to City Phase Two Information Request No. 1

C Exhibits - Intervener Documents



Date Title Document Description
July 19, 2018 C1-1 CITY OF COQUITLAM (CITY) Letter Dated July 19,2018 – Submission Regarding the Regulatory Procedure for the Application
August 03, 2018 C1-2 Letter dated August 3, 2018 – Submission on Project Issues
August 17, 2018 C1-3 Letter dated August 17, 2018 – City Submitting Responses to BCUC Information Request No. 1
August 17, 2018 C1-4 Letter dated August 17, 2018 – City Submitting Responses to FEI Information Request No. 1
August 17, 2018 C1-5 Letter dated August 17, 2018 – City Submitting Revised Terms and Conditions
September 05, 2018 C1-6 Letter dated September 5, 2018 – Notice of filing additional evidence for Phase Two
September 20, 2018 C1-7 Letter dated September 20, 2018 – City Submission Regarding Issues for Phase Two
October 31, 2018 C1-8 Letter dated October 31, 2018 – City filing submission on Phase Two evidence
November 15, 2018 C1-9 Letter dated November 15, 2018 – City submitting Information Request No. 1 to FEI on Phase Two evidence
December 06, 2018 C1-10 Letter dated December 5, 2018 – City of Coquitlam submitting responses to BCUC Information Request No. 2
December 06, 2018 C1-11 Letter dated December 5, 2018 – City of Coquitlam submitting responses to CEC Phase Two Information Request No. 1
December 06, 2018 C1-12 Letter dated December 5, 2018 – City of Coquitlam submitting responses to FEI Phase Two Information Request No. 1
September 11, 2018 C2-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated September 5, 2018 – Request to Intervene by Christopher Weafer
November 21, 2018 C2-2 Letter dated November 21, 2018 – CEC submitting Information Request No. 1 to City of Coquitlam
November 21, 2018 C2-3 Letter dated November 21, 2018 – CEC submitting Information Request No. 1 to FEI

D Exhibits — Interested Party Documents

Date Title Document Description
August 10, 2018 D-1 BC OIL AND GAS COMMISSION (BCOGC) Letter Dated August 8, 2018 - Request for Interested Party Status by Dorothy Foster