NorthRiver Midstream Operations LP (NRLP) and NorthRiver Midstream Operations GP Inc. (NRGP) Application for an Exemption Pursuant to Section 88(3) of the Utilities Commission Act ~ Project No. 1598989

Completed: 2019

Hearing and Other Documents

Title Document Description
*_Exhibit List Updated: May 14, 2019 @ 5:32 pm
*_G-134-19 Final Order dated June 19, 2019

Arguments/Submissions

Title Document Description
NRLP and NRGP Final Argument Final Argument dated March 27, 2019

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
January 30, 2019 A-1 Letter dated January 30, 2019 - Appointing the Panel for the review of NorthRiver Midstream Operations LP and NorthRiver Midstream Operations GP Inc. Application for an exemption pursuant to section 88(3) of the Utilities Commission Act
January 30, 2019 A-2 Letter dated January 30, 2019 - BCUC Order G-22-19 establishing the regulatory timetable
February 14, 2019 A-3 Letter dated February 14, 2019 - BCUC Information Request No. 1 to NRLP and NRGP
March 06, 2019 A-4 Letter dated March 6, 2019 - BCUC Order G-49-19 amending the regulatory timetable and providing workshop agenda and scope
March 19, 2019 A-5 Letter dated March 19, 2019 – BCUC Order G-61-19 amending the regulatory timetable
May 14, 2019 A-6 Letter dated May 14, 2019 – BCUC Report to the Minister of Energy, Mines and Petroleum Resources
March 13, 2019 A2-1 Letter dated March 13, 2019 - BCUC Staff submitting National Energy Board document dated June 1998

B Exhibits - Applicant Documents

Date Title Document Description
February 21, 2019 B-2 Letter dated February 21, 2019 – NRLP and NRGP Submitting Responses to BCUC Information Request No. 1
March 15, 2019 B-3 Letter dated March 15, 2019 – NRLP and NRGP Submitting Workshop Information
January 29, 2019 B-1 NORTHRIVER MIDSTREAM OPERATIONS LP (NRLP) AND NORTHRIVER MIDSTREAM OPERATIONS GP INC. (NRGP) Letter dated January 7, 2019 - Application for an exemption pursuant to section 88(3) of the Utilities Commission Act

Transcripts

Date Title Document Description
March 18, 2019 Transcript Volume 1 Workshop March 18, 2019