Creative Energy

Creative Energy Vancouver Platforms Inc. Application for Heating Rates for the Heating Thermal Energy System and Cooling Rates for the District Cooling System at the Vancouver House Development

Completed: 2021

Hearing and Other Documents

Title Document Description
Exhibit List Updated: April 15, 2021 @ 12:44 pm
Decision and Order G-222-21 Decision and Order G-222-21 July 22, 2021

Arguments/Submissions

Title Document Description
Creative Energy Final Argument Final Argument March 12, 2021
CEC Final Argument Final Argument March 26, 2021
BCOAPO Final Argument Final Argument March 26, 2021
Creative Energy Reply Argument Reply Argument April 9, 2021
CEC Supplementary Final Argument Supplementary Final Argument April 22, 2021
BCOAPO Supplemental Final Argument Supplementary Final Argument April 23, 2021
Creative Energy Supplementary Reply Argument Supplementary Reply Argument April 27, 2021

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
October 22, 2019 A-1 Letter dated October 22, 2019 - Appointing the Panel for the review of Creative Energy Vancouver Platforms Inc.’s Application for Interim Heating Rates for the Thermal Energy System at the Vancouver House Development
October 28, 2019 A-2 Letter dated October 28, 2019 – BCUC Order G-260-19 approving heating rates on an interim basis
October 31, 2019 A-3 Letter dated October 31, 2019 – BCUC Order G-264-19 establishing a regulatory timetable
November 29, 2019 A-4 Letter dated November 29, 2019 – BCUC Information Request No. 1 to Creative Energy
January 16, 2020 A-5 Letter dated January 15, 2020 – BCUC Order G-9-20 adjourning the proceeding
July 31, 2020 A-6 Letter dated July 31, 2020 – BCUC letter regarding Creative Energy extension request
September 14, 2020 A-7 Letter dated September 14, 2020 – Appointing the Panel for the review of Creative Energy’s Application for Interim Cooling Rates for the District Cooling System at the Vancouver House Development
September 14, 2020 A-8 Letter dated September 14, 2020 – BCUC Order G-225-20 approving cooling rates on an interim basis
September 14, 2020 A-9 Letter dated September 14, 2020 – BCUC Order G-233-20 establishing a regulatory timetable and Public Notice
October 07, 2020 A-10 Letter dated October 7, 2020 – Panel Information Request No. 1 to Creative Energy
October 07, 2020 A-11 Letter dated October 7, 2020 – BCUC Order G-252-20 amending the regulatory timetable
November 17, 2020 A-12 Letter dated November 17, 2020 – BCUC Information Request No. 2 to Creative Energy
December 15, 2020 A-13 Letter dated December 15, 2020 – BCUC response to Creative Energy’s extension request to file IR No. 2 responses
January 08, 2021 A-14 Letter dated January 8, 2021 – BCUC Order G-4-21 establishing a further regulatory timetable
January 28, 2021 A-15 Letter dated January 28, 2021 – BCUC Information Request No. 3 to Creative Energy
March 03, 2021 A-16 Letter dated March 3, 2021 – BCUC Order G-62-21 establishing an amended regulatory timetable
April 08, 2021 A-17 Letter dated April 8, 2021 – BCUC Panel Information Request No. 2 to Creative Energy

B Exhibits - Applicant Documents

Date Title Document Description
December 20, 2019 B-2-1 CONFIDENTIAL - Letter dated December 20, 2019 – Creative Energy Submitting Confidential Response to BCUC Information Request No. 1
October 02, 2019 B-1 CREATIVE ENERGY VANCOUVER PLATFORMS INC. (CREATIVE ENERGY) - Letter dated October 2, 2019 Submitting Application for Interim Heating Rates for the Thermal Energy System at the Vancouver House Development
November 25, 2020 B-11 Letter date November 25, 2020 - Creative Energy Submitting tariff page in compliance with Order G-225-20
April 14, 2021 B-20 Letter dated April 14, 2021 – Creative Energy response to BCUC Panel Information Request No. 2
April 15, 2021 B-21 Letter dated April 15, 2021 – Creative Energy Submitting notice regarding supplemental arguments
August 11, 2020 B-6 Letter dated August 11, 2020 – Creative Energy Submitting Vancouver House Development District Cooling System (DCS) Rates Application
August 27, 2020 B-5 Letter dated August 27, 2020 – Creative Energy Submitting an evidentiary update
December 15, 2020 B-12 Letter dated December 15, 2020 – Creative Energy requesting extension to file responses to Information Request No. 2
December 18, 2020 B-15 Letter dated December 18, 2020 – Creative Energy Submitting responses to BCOAPO Information Request No. 2
December 18, 2020 B-13 Letter dated December 18, 2020 – Creative Energy Submitting responses to BCUC Information Request No. 2
December 18, 2020 B-14 Letter dated December 18, 2020 – Creative Energy Submitting responses to CEC Information Request No. 2
December 20, 2019 B-2 Letter dated December 20, 2019 – Creative Energy Submitting Responses to BCUC Information Request No. 1
December 27, 2019 B-2-2 Letter dated December 27, 2019 – Creative Energy Submitting Revisions to BCUC IR No.1
February 22, 2021 B-18 Letter dated February 22, 2021 – Creative Energy Submitting responses to BCOAPO Information Request No. 3
February 22, 2021 B-16 Letter dated February 22, 2021 – Creative Energy Submitting responses to BCUC Information Request No. 3
February 22, 2021 B-17 Letter dated February 22, 2021 – Creative Energy Submitting responses to CEC Information Request No. 3
January 03, 2020 B-3 Letter dated January 3, 2020 – Creative Energy Submitting Responses to CEC Information Request No. 1
July 30, 2020 B-4 Letter dated July 30, 2020 – Creative Energy Submitting Extension Request to file an evidentiary update
March 03, 2021 B-16-1 Letter dated March 3, 2021 – Creative Energy Submitting errata to responses to BCUC Information Request No. 3 Questions 90.1 and 90.4
March 03, 2021 B-19 Letter dated March 3, 2021 – Creative Energy Submitting proposed amended Regulatory Timetable
October 21, 2020 B-9 Letter dated October 21, 2020 – Creative Energy Submitting responses to Panel Information Request No. 1
October 23, 2019 B-1-1 Letter dated October 23, 2019 – Creative Energy Submitting a Draft Order
October 30, 2020 B-10 Letter dated October 30, 2020 – Creative Energy Submitting Update in compliance with Order G-252-20
September 16, 2020 B-7 Letter dated September 16, 2020 – Creative Energy Submitting confirmation of notification process
September 30, 2020 B-8 Letter dated September 30, 2020 – Creative Energy Submitting notification in compliance with Order G-225-20

C Exhibits - Intervener Documents

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more