Creative Energy

Creative Energy Vancouver Platforms Inc. 2019–2020 Revenue Requirements Application for the Core Steam System and Northeast False Creek Service Areas

Completed: 2020

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: May 12, 2020 @ 11:25 am
Decision with Order G-227-20 Decision with Order G-227-20 September 2, 2020

Arguments/Submissions

Title Document Description
Creative Energy Reply Argument Reply Argument June 4, 2020
Creative Energy Final Argument Final Argument May 21, 2020
CEC Final Argument Final Argument May 28, 2020

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
January 02, 2020 A-1 Letter dated January 2, 2020 - Appointing the Panel for the review of Creative Energy Vancouver Platforms Inc. 2019–2020 Revenue Requirements Application for the Core Steam System and Northeast False Creek Service Areas
January 22, 2020 A-2 Exhibit removed and replaced by Exhibit A-2-1
January 22, 2020 A-2-1 Letter dated January 22, 2020 – Amended BCUC Order G-7-20A with reasons for decision establishing interim rates and regulatory timetable for the review of the Application
February 21, 2020 A-3 Letter dated February 21, 2020 – BCUC Order G-29-20 amending the regulatory timetable
March 05, 2020 A-4 Letter dated March 5, 2020 – BCUC issuing Information Request No. 1 to Creative Energy
March 12, 2020 A-5 Letter dated March 12, 2020 – BCUC issuing Information Request No. 1 for Fuel Switch Study and LTRP Deferral Account to Creative Energy
April 21, 2020 A-6 Letter dated April 21, 2020 – BCUC issuing Information Request No. 2 to Creative Energy
May 01, 2020 A-7 Letter dated May 1, 2020 – BCUC Order G-103-20 amending regulatory timetable
May 12, 2020 A-8 Letter dated May 12, 2020 – BCUC requesting information from Creative Energy regarding Final Arguments
March 05, 2020 A2-1 Letter dated March 5, 2020 – BCUC staff filing Creative Energy Notes to Financial Statements dated December 31, 2018

B Exhibits - Applicant Documents

Date Title Document Description
December 19, 2019 B-1 CREATIVE ENERGY VANCOUVER PLATFORMS INC. (CREATIVE ENERGY) - 2019–2020 Revenue Requirements Application for the Core Steam System and Northeast False Creek Service Areas dated December 19, 2019
February 20, 2020 B-2 Letter dated February 20, 2020 – Creative Energy request extension to file proposal regarding Fuel Switch Study and LTRP Deferral Account
February 21, 2020 B-1-1 Letter dated February 21, 2020 – Creative Energy Submitting Evidentiary Update to the Application
February 27, 2020 B-3 Letter dated February 27, 2020 – Creative Energy Submitting proposal regarding Fuel Switch Study and LTRP Deferral Account
April 02, 2020 B-4 Letter dated April 2, 2020 – Creative Energy Submitting responses to BCUC Information Request No. 1
April 02, 2020 B-5 Letter dated April 2, 2020 – Creative Energy Submitting responses to BCUC Information Request No. 1 on Fuel Switch Study and LTRP Deferral Account Proposal
April 02, 2020 B-6 Letter dated April 2, 2020 – Creative Energy Submitting responses to CEC Information Request No. 1
April 02, 2020 B-7 Letter dated April 2, 2020 – Creative Energy Submitting responses to CEC Information Request No. 1 on Fuel Switch Study and LTRP Deferral Account Proposal
April 30, 2020 B-8 Letter dated April 30, 2020 – Creative Energy Submitting an extension request to file Final Argument
May 05, 2020 B-9 Letter dated May 5, 2020 – Creative Energy Submitting responses to BCUC Information Request No. 2
May 05, 2020 B-10 Letter dated May 5, 2020 – Creative Energy Submitting responses to CEC Information Request No. 2

C Exhibits - Intervener Documents

D Exhibits — Interested Party Documents

Date Title Document Description
January 23, 2020 D-1 FORTISBC ENERGY INC. (FEI) - Submission dated January 23, 2020 Request for Interested Party Status

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more