BC Hydro

Reconsideration and Variance of Order G-148-20 regarding Electricity Purchase Agreement Renewals for Sechelt Creek Hydro, Brown Lake Hydro and Walden North Hydro

Completed: 2020

Hearing and Other Documents

Title Document Description
G-279-20 with Reasons for Decision Final Order with Reasons for Decision November 2, 2020
EXHIBIT LIST Updated: October 15, 2020 @ 4:41 pm

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
August 25, 2020 A-1 Letter dated August 25, 2020 – BCUC letter appointing the Panel for review of BC Hydro’s Application for Reconsideration and Variance of Order No. G-148-20 in the matter of the BC Hydro Application for Electricity Purchase Agreement Renewals for Sechelt Creek Hydro, Brown Lake Hydro and Walden North Hydro
August 28, 2020 A-2 Letter dated August 28, 2020 – BCUC letter responding to BC Hydro’s request for clarification on Directive 2 to Order G-148-20 and to vary and extend the filing deadline
September 18, 2020 A-3 Letter dated September 18, 2020 – BCUC Order G-239-20 establishing a regulatory timetable with Reasons for Decision

B Exhibits - Applicant Documents

Date Title Document Description
August 06, 2020 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) - Application for Reconsideration and Variance of Order No. G-148-20 in the matter of the BC Hydro Application for Electricity Purchase Agreement Renewals for Sechelt Creek Hydro, Brown Lake Hydro and Walden North Hydro dated August 6, 2020
September 22, 2020 B-2 Letter dated September 22, 2020 – BC Hydro Submitting notice of compliance with Order G-239-20 Directive 3
October 01, 2020 B-3 Letter dated October 1, 2020 – BC Hydro Submission in compliance with Order G-239-20 Directive 3
October 15, 2020 B-4 Letter dated October 15, 2020 – BC Hydro Submitting response to Intervener submission

C Exhibits - Intervener Documents

Our Review Process